Airport Aid Grant Program.
The Washington State Department of Transportation (WSDOT) is responsible for the general supervision over the Airport Aid Grant Program (Program), which provides financial assistance to public-use airports. Any city, county, airport authority, political subdivision, federally recognized Indian tribe, public corporation, or person that owns and operates a public-use airport included in the Washington Aviation System Plan is considered an eligible airport sponsor within the Program and may apply for Program funds. The municipality, tribe, or person may act jointly with other municipalities, tribes, or persons to plan or carry out the project. Airport sponsors applying for grants must own or have a long-term lease for the land upon which the project will be completed. There are 137 public-use airports eligible to receive funding from the Program. The maximum grant amount the WSDOT may provide to an individual sponsor in a single Program grant is $750,000.
Airport Investment Study.
In 2013 the WSDOT began an Airport Investment Study to evaluate short- and long-term airport preservation needs at public-use airports. Analysis of the study resulted in 10 core solutions detailed in the Airport Investment Solution Handbook produced in July 2015. These solutions include public-private partnerships, realignment of current transportation revenue allocations, and developing a "best management practices" guidebook for airports. In addition to the core solutions, a number of recommendations were provided, including establishing a state-sponsored revolving aviation infrastructure loan fund for a self-generated aviation funding source for revenue-generating projects.
Legislative History.
The 2018 Capital Budget (Chapter 2, Laws of 2018) created a new Aviation Loan Program (loan program) and appropriated $5 million to be deposited into a new revolving loan account. Loans must be approved by a board for the purpose of airport improvements. Substitute House Bill 1656 (SHB 1656) passed in the 2018 Legislative Session and would have permanently codified a community aviation revitalization loan program, but the legislation was vetoed. The 2019 Supplemental Capital Budget (Chapter 413, Laws of 2019) reappropriated the original funding and extended the loan program through June 2021 with modifications to the loan program per SHB 1656. Similar legislation to SHB 1656 was offered in the 2019 and 2020 legislative sessions, but did not pass the Legislature.
Creation and Administration of the Community Aviation Revitalization Board.
The WSDOT must convene a Community Aviation Revitalization Board (Board) to make direct loans to certain airports for improvements that primarily support general aviation activities. The WSDOT is required to staff the Board and to manage its fiscal and contract services. Terms, expectations, and procedures for vacancies of Board members are established. The Board must meet three times a year or as deemed necessary by the WSDOT.
The Board consists of the following members:
Loan Application Process and Evaluation.
Airports must apply to the Board for loan consideration. Eligible airports must be available for public use and have less than 75,000 annual commercial air service passenger enplanements as published by the Federal Aviation Administration. An application must be supported by the port district, city, or county in which the project is located, or clearly identify the source of funds intended to repay the loan. The Board must prioritize applications providing conclusive justification that completion of the loan application project (project) will create revenue-generating opportunities.
The Board must use, but is not limited to, the following criteria when evaluating loan applications:
Loan Terms and Account Use.
The Board must develop rules to implement the program and determine the interest rate, terms and conditions of loans, and any local match. Loan interest rates must not exceed the amount needed to cover the administrative expenses of the Board and the loan program. Loan repayment must begin within three years after a loan is awarded and loans cannot exceed 20 years.
The Public Use General Aviation Airport Loan Revolving Account (Account) created in Chapter 2, Laws of 2018 (2018 Capital Budget) is codified. Funds in the Account may be used to fund only authorized loans as approved by the Board, and loan repayments must be deposited into the Account. Loans issued to airport sponsors of nongovernmental airports must be made only from repaid loan funds deposited into the Account.
Definitions.
The following terms are defined for use in aeronautics statutes:
(In support) The Board has been established and has loaned out money with provisions in the Capital Budget to help small airports with funding revenue-generating projects. The loans have a great multiplier effect in creating economic activity and providing funds to small airports who have shown a history of repaying their loans in other states like Colorado. Loans were made to very small airports for projects such as extending utility connections, replacing underground fuel systems with above ground fuel systems to remove environmental hazards, and replacing an airport building that is home to a well known restaurant. The 2015 Airport Investment Study showed that there is a great shortfall in investments at public-use airports. This loan program allows the state to provide some of the shortfall. These loans are for airports that do not qualify for federal funds, but can access these funds for revenue generating projects. The first round of loans received 26 applications and 11 projects received loans. Without additional funds, a lack of sufficient funds will cause this much needed program to die, so support of this legislation is imperative.
(Opposed) None.
(In support) The bill codifies the procedures for the community aviation revitalization program to issue low-interest loans and creates a revolving fund. The loan will support construction of a multipurpose facility, including an airport restaurant, hanger, offices and a pilot flight planning facility. The State of Colorado established a similar program in 1999 with a robust account balance supporting funding for airport projects with no loan defaults.
(Opposed) None.