Growth Management Act.
The Growth Management Act (GMA) is the comprehensive land use planning framework for counties and cities in Washington. The GMA establishes land use designation and environmental protection requirements for all Washington counties and cities. The GMA also establishes a significantly wider array of planning duties for 28 counties, and the cities within those counties, that are obligated to satisfy all planning requirements of the GMA. These jurisdictions are sometimes said to be fully planning under the GMA.
Counties that fully plan under the GMA are required to designate urban growth areas (UGAs) within their boundaries sufficient to accommodate a planned 20-year population projection range provided by the Office of Financial Management (OFM). Each city located within a planning county must be included within a UGA. Urban growth must be encouraged within the UGAs, and only growth that is not urban in nature can occur outside of the UGAs. Each UGA must permit urban densities and include greenbelt and open space areas.
Comprehensive Plans.
The GMA directs fully planning jurisdictions to adopt internally consistent, comprehensive land use plans that are generalized, coordinated land use policy statements of the governing body. When developing their comprehensive plans, counties and cities must consider various goals set forth in statute and include mandatory elements such as housing and a capital facilities plan. Comprehensive plans are implemented through locally adopted development regulations, and both the plans and the local regulations must be reviewed and revised every 10 years.
The Department of Commerce (Commerce) must establish a program of technical and
financial assistance to encourage and facilitate cities and counties to adopt and implement
comprehensive plans.
Mandatory Housing Element.
Comprehensive plans must include a housing element that ensures the vitality and character of established residential neighborhoods. The housing element must include the following:
Planning Actions to Increase Residential Building Capacity.
Fully planning cities are encouraged to take an array of specified planning actions to increase residential building capacity. Specified planning actions include:
In general, ordinances and other nonproject actions taken to implement these specified planning actions, if adopted by April 1, 2023, are not subject to administrative or judicial appeal under SEPA or legal challenge under the GMA.
Common Interest Communities.
A common interest community (CIC) is a form of real estate in which each unit owner or homeowner has an exclusive interest in a unit or lot and a shared or undivided interest in common area property. In Washington, several statutes govern residential CICs, such as condominiums and homeowners' associations. Generally these groups can regulate or limit the use of property by its members.
A restrictive covenant or deed is a restriction or limitation of the use of the property that runs with the land.
Density Requirements.
A fully planning city meeting the population criteria must provide by ordinance, and incorporate into its development regulations, zoning regulations, and other official controls, authorization for the development of a minimum number of units on all lots zoned predominately for residential use by six months after the city's next required comprehensive plan update. A city not meeting the population threshold must comply with the density and middle housing requirements by 12 months after its next comprehensive plan implementation progress report after a determination by the OFM that the city has reached the population threshold.
A fully planning city with a population of at least 25,000 but less than 75,000 must include authorization for at least:
A fully planning city with a population of at least 75,00 must include authorization for at least:
A fully planning city with a population less than 25,000, within a contiguous UGA with the largest city in a county with a population of more than 275,000, must include authorization for the development of at least two units per lot.
A major transit stop includes a stop on a high-capacity transportation system, commuter rail stops, stops on rail or fixed guideway systems, and stops on bus rapid transit routes.
To qualify as affordable housing, the unit must be maintained as affordable for at least 50 years and record a covenant or deed restriction that ensures continued affordability. The affordable units also must be comparable in size and number of bedrooms as other units and be generally distributed throughout the development. A city with an affordable housing incentive program may vary from these affordable housing requirements and require any development to provide affordable housing, either onsite or through an in-lieu payment.
The density requirements do not apply to:
Alternative Density Requirement.
A city subject to the density requirements may choose to implement the density requirements for at least 75 percent of lots in the city that are primarily dedicated to single-family detached housing units. Unless identified as at higher risk of displacement, the 75 percent of lots allowing the minimum density requirements must include any areas:
The 25 percent of lots for which the minimum density requirements are not authorized must include:
A city implementing the alternative density requirement may apply to Commerce for an extension from the implementation timelines for areas at risk of displacement as determined by the city's antidisplacement analysis. A city granted an extension must create a plan for implementing antidisplacement policies by their next comprehensive plan implementation progress report. Commerce may certify one further extension based on evidence of significant ongoing displacement risk in the impacted area.
A city implementing the alternative density requirements also may apply for an extension to specific areas where a city can demonstrate that water, sewer, stormwater, transportation infrastructure, or fire protection services lack capacity to accommodate an increased density. To qualify for an extension, the city must have included one or more improvements, as needed, within its capital facilities plan to adequately increase capacity or identified which special district is responsible for providing the necessary infrastructure. If an extension is requested due to lack of water supply from the city or the purveyors who serve water within the city, Commerce's evaluation must be based on the applicable water system plans in effect and approved by the Department of Health. Any granted extension remains in effect until the earliest of:
A city may reapply for an additional timeline extension with its next periodic comprehensive plan update or five-year comprehensive plan implementation progress report. The extension application must include a list of infrastructure improvements necessary to meet the required capacity. Commerce must provide the Legislature with a list of those projects identified in a city's capital facilities plan that were the basis for the extension. A city granted an extension for a specific area must allow development if the developer commits to providing the necessary water, sewer, or stormwater infrastructure.
Middle Housing Requirements.
A city must allow at least six of the nine types of middle housing and may allow ADUs to achieve the minimum density requirements. Middle housing is defined as buildings that are compatible in scale, form, and character with single-family houses and contain two or more attached, stacked, or clustered homes including duplexes, triplexes, fourplexes, fiveplexes, sixplexes, townhouses, stacked flats, courtyard apartments, and cottage housing. A city is not required to allow ADUs or middle housing types beyond the density requirements.
A city subject to the density requirements must include specific provisions related to middle housing in their development regulations. Any city subject to the middle housing requirements:
A SEPA categorical exemption is established for development regulations that remove parking requirements for infill development. The limits on off-street parking requirements do not apply if a city submits to Commerce an empirical study prepared by a credentialed transportation or land use planning expert that clearly demonstrates, and Commerce certifies, that parking limits for middle housing will be significantly less safe for vehicle drivers or passengers, pedestrians, or bicyclists than if the jurisdiction's parking requirements were applied to the same location for the same number of detached houses. Commerce must develop guidance to assist cities on items to include in the study. The off-street parking requirements also do not apply to any portion of a city within a 1-mile radius of a commercial airport with at least 9 million annual enplanements.
A city may not approve a building permit if other federal, state, and local requirements for a
building permit are not met, including adequate water supply requirements. If an area zoned for residential use is currently served only by private wells, group B water systems, or group A water systems with less than 50 connections, or if a city or water providers within the city do not have an adequate water supply or available connections to serve the zoning increase, the city may limit the areas subject to the density requirements to match current water availability.
Development may be limited to two units per lot in an area served only by on-site sewage systems until either the landowner or local government provides sewer service or demonstrates a sewer system will serve the development at the time of construction.
A city adopting the density and middle housing requirements is not required to update its capital facilities plan element to accommodate the increased housing until its first comprehensive plan update required on or after June 30, 2034, unless Commerce grants a timeline extension.
Department of Commerce.
Commerce must provide technical assistance to cities in implementing density and middle housing requirements. Commerce must develop and publish model middle housing ordinances within six months after this bill takes effect. The model ordinances supersede, preempt, and invalidate local development regulations until the city takes action to adopt the density and middle housing requirements.
Commerce must establish a process for cities to seek approval of alternative local actions to
meet density requirements and may approve actions for cities that have adopted the
following by January 1, 2023:
Commerce must find as substantially similar plans and regulations that:
If a city can clearly demonstrate that the regulations adopted will allow for a greater
increase in middle housing production within single family zones than would be allowed
through the density requirements, Commerce may determine that a comprehensive plan and
development regulations that do not meet these criteria are substantially similar. Any alternative local actions approved by Commerce are exempt from appeals under the GMA and SEPA.
Commerce may establish by rule any standards or procedures necessary to implement the
density and middle housing requirements and issue guidance for local jurisdictions to
ensure that the levels of middle housing zoning can be integrated with the methods used by cities to calculate zoning densities and intensities in local zoning and development regulations.
Common Interest Communities.
Governing documents and declarations of CICs within cities subject to the density and middle housing requirements that are created after this bill takes effect may not prohibit the construction, development, or use of the additional housing units.
House | 75 | 21 | |
Senate | 35 | 14 | (Senate amended) |
House | 79 | 18 | (House concurred) |
July 23, 2023