Permitting and the Growth Management Act.
The Growth Management Act (GMA) requires that certain counties, and the cities within those counties, engage in planning for future population growth. Currently, 28 counties fully plan under the GMA and 11 do not. The centerpiece of the planning process is the comprehensive plan. Comprehensive plans must be reviewed and, if necessary, revised every 10 years. The city or county (local government) must also adopt development regulations to implement the comprehensive plan. Development regulations include zoning ordinances, official controls, subdivision ordinances, and other regulations.
In enforcing these regulations, local governments generally require that a developer obtain one or more permits before development or redevelopment of land is allowed to occur. These permits can be building permits, land use permits, environmental permits, or other permits, and are collectively known as project permits. The development regulations often provide for how each type of project permit is processed. When a county or city planning under the GMA is reviewing a project, its comprehensive plan and development regulations must serve as the basis for the project permit review. These regulations determine the types of land use permitted at a site, the density of residential development in urban growth areas, and the availability of public facilities identified in the comprehensive plan.
In determining if a proposed project is consistent with the development regulations, the local government must consider the type of land use; the level of development or density proposed; the infrastructure needed to service the development; and the characteristics of the development.
Local governments can generally determine which permitting processes are applicable to which project permit types. All local governments, however, including those not planning under the GMA, are required to combine the environmental review process with the project permit review process, and to hold no more than one open record hearing and one closed record appeal on a project permit application, excluding a determination of significance determined under the State Environmental Policy Act. An open record hearing is a hearing that creates a record through testimony and submission of evidence. An open record hearing can be held prior to the local government's decision on a project permit, or held after the decision if the decision is appealed. A closed record appeal is an administrative appeal from the decision on the project permit application that is held on the record established in the open record hearing with little or no new evidence allowed.
One aspect of the permitting process may be site plan review. Site plan review generally involves the review of the physical details and the type of use of a proposed project for compliance with site-specific requirements. These requirements can deal with subjects like building design, landscaping, parking, compatibility with adjacent land uses, access to and from the development, and utility standards. Site plan review may be required prior to, or concurrent with, other types of review. It is generally required on projects involving commercial or industrial uses, or on residential projects involving multifamily housing. Site plan review can apply to new developments as well as to the remodeling or expansion of existing developments.
Local governments planning under the GMA must comply with additional project permit processing requirements, including establishing an integrated or consolidated permit process that:
Determination of Completeness.
When an application for a permit is submitted, the local government must determine if the application is complete for subsequent processing. An application is complete when it meets the procedural submission requirements of the local government and is sufficient for continued processing, even though additional information or modifications may be subsequently required. A determination that an application is complete does not preclude the local government from requesting additional information or studies at the time of the determination, or later if new information is required or if there are substantial changes in the proposed action.
The local government must provide a written determination of whether the application is complete to the applicant by mail or in person within 28 days of the of the submission of the application. If the local government does not provide the written determination by the deadline, then the application is deemed complete. If the local government notifies the applicant that the application is incomplete, the local government must identify what is necessary to make the application complete. Once an applicant provides additional information to the local government, the local government has 14 days to notify the applicant that the application is complete or that some specified additional information is necessary.
Notice of Application.
Once an application is determined to be complete, local governments planning under the GMA must provide notice of the application to the public and to agencies that may have jurisdiction over some part of the application. This notice must be provided within 14 days of the application having been found complete, and at least 15 days prior to an open record predecision hearing. This notice must include:
The required notice can be provided in various ways, as determined by the local government through an ordinance or resolution, and different methods of providing notice can be used for different types of permits. In the absence of an ordinance or resolution governing how notice will be provided, it must be posted at the property if the proposal relates to a property, and published in a newspaper of general circulation. A local government cannot issue a decision on a project permit until the expiration of the public comment period. Any hearing on the application may be combined with any hearing held by a federal, state, or local agency, as long as the hearing is held within the local government's jurisdiction. Hearings must be combined if requested by an applicant and the applicant agrees to a revised schedule if additional time is necessary to coordinate the hearing.
Permit Processing Timelines.
After an application is determined to be complete, the application must be processed. As part of the consolidated permit process required of local governments planning under the GMA, the local government must establish deadlines for processing each type of project permit application. These deadlines cannot exceed 120 days unless the local government makes written findings that additional time is necessary to process specific permit applications or certain project types. The development regulations must specify what is required of a completed project permit application for the deadline to be met.
Notice of Decision and Exclusions from the Permitting Process.
Once an application is processed, a local government planning under the GMA must provide a notice of decision. The notice must include any appeals rights available to the applicant. The notice must also include any threshold determination made under the State Environmental Policy Act that determines whether the project is likely to have any significant adverse environmental impact. The notice must be provided to the applicant as well as to anyone who requested notice.
A local government does not need to provide for administrative appeals, but, if an administrative appeal is provided, it must be requested within 14 days of a decision.
Local governments can, by ordinance or resolution, exclude certain project permits from the required permitting processes. These project permits include street vacations, landmark designations, approvals related to the use of public areas or facilities, lot line adjustments, building or construction permits, permits related to the construction of less than four residential dwelling units, permits related to the construction of commercial buildings of less than 4,000 square feet and fewer than 20 parking spaces, other permits subject to administrative approval, or other project permits that the local government has determined warrant a different review process.
Permit Application Reporting Requirements.
Clark, King, Kitsap, Pierce, Snohomish, Thurston, and Whatcom counties, and the cities within those counties, are subject to additional requirements under the GMA. These counties and cities are required to establish a review and evaluation program. Part of this program involves identifying land suitable for development, and this program is often referred to as the Buildable Lands Program.
Counties subject to the Buildable Lands Program, and cities within those counties that have a population of 20,000 or more, are also subject to additional project permit application reporting requirements. These local governments must prepare an annual permitting performance report that includes:
The county or city must provide notice of, and access to, the annual reports through the local government's website, or, if the local government does not have a website, by other reasonable means.
Permit Application Fees and Additional Permit Provisions.
Local governments can impose fees on project permit applications. These fees often correspond to the nature of the project, the valuation of the project, and the type of permit. These fees must be reasonable, and are limited to the recovery of the costs of processing applications, inspecting or reviewing plans, or preparing detailed statements under the State Environmental Policy Act.
Local governments are encouraged to adopt additional project review provisions to provide prompt, coordinated review, and to ensure accountability to applicants and to the public. Providing expedited review for project permit applications that are consistent with development regulations and within the capacity of systemwide infrastructure improvements is one such provision that may be adopted.
International Residential Code.
The International Residential Code (IRC) is a comprehensive building code published by the International Code Council that applies to new one- and two-family dwellings and townhouses of up to three stories. It has been adopted by Washington through the State Building Code.
Determination of Completeness.
A determination of completeness must be provided in writing to an applicant within 20 days of the local government's receipt of the application. An application is complete if it meets the procedural submission requirements of the local government as outlined on the project permit application. The determination must state that the application is complete, or that the application is incomplete and that the procedural submission requirements of the local government have not been met. A determination that the application is incomplete must outline what is necessary to make the application procedurally complete. Additional information and studies may be required after the determination of completeness, and project modifications may subsequently be undertaken, but the need for additional information or studies may not preclude a determination of completeness.
When determining whether the local government has met the deadline to provide a written determination of completeness within 20 days, the time is computed by counting five days per week, excluding holidays.
If a written determination is not provided by the twenty-ninth day after the project permit application was received by the local government, then the application is deemed procedurally complete. The local government may still seek additional information or studies after an application is deemed complete in this way.
Permit Processing Timelines.
For project permits submitted after January 1, 2025, the default deadline for processing a permit depends on the processing requirements applicable to the permit. For permits that do not require public notice of the application to be provided, the deadline is 45 days from the determination of completeness. For permits that do require public notice, the deadline is 70 days from the determination of completeness. For permits that require both public notice and a public hearing, the deadline is 120 days from the determination of completeness.
The time that a permit takes to process is calculated by counting five days a week, excluding holidays and the following time periods:
If an applicant informs the local government in writing that the applicant would like to suspend the review of the application for more than 60 days, or if the applicant is not making demonstrable progress or responding to the local government for 60 consecutive days after the local government has requested, in writing, additional information needed to process the application, an additional 30 day may be added to the time period for the local government to issue a final decision. Any written notice from the local government to the applicant seeking additional information must inform the applicant of the possibility of the 30-day extension if the applicant does not make demonstrable progress or respond within 60 days.
Local governments may exclude certain permit types and timelines, provide for different timelines if special circumstances warrant it, add new permit types not identified, change permit names or types in each category, address how two or more permits consolidated for processing may change the time needed for processing, and differentiate projects of a certain size or type. If a local government does not adopt an ordinance or resolution modifying the timelines, then the default timelines apply.
If the time frames are not met when processing a permit, a portion of the permitting fee that the local government charged the applicant must be refunded. If the deadline was missed by less than 20 percent of the original time frame, then 10 percent of the permitting fee must be refunded. If the deadline was missed by more than 20 percent of the original time frame, then 20 percent must be refunded.
The adoption of permitting time frames and related regulations by a local government is not subject to appeal, unless a permit type is included for which more than 120 days are provided.
Additional Project Review Provisions.
Local governments are encouraged to adopt additional project review and code provisions to provide prompt, coordinated permit review, and to ensure accountability to the applicant and the public by:
A local government that adopts at least three of these additional project review provisions is not required to provide a refund if it misses a permitting time frame. When a local government has adopted additional project review provisions, and permit time frames are not being met at least 50 percent of the time, the local government must adopt new measures to reduce permit time frames at the time of its next comprehensive plan update.
Local governments that have adopted at least three of the optional project review provisions must be prioritized by the Department of Commerce (Department) when providing technical assistance. The Department's technical assistance must include guidance to local governments in setting reasonable fee structures that are sufficient to recover true permitting costs. The Department must also provide guidance for increasing these fees over time to reflect cost increases.
Permit Reporting Requirements.
The permit reporting requirements applicable to the counties subject to the Buildable Lands Program, and cities within those counties of 20,000 or more, are repealed. Instead, beginning in 2025, those counties and cities must provide a new annual permitting performance report to the Department including information about the time frames for certain permit types associated with housing. The report does not need to demonstrate the total time for a project to receive final approval, but must include:
The report must be provided to the Department by March 1 of each year, with the first report due March 1, 2025. The report must also be posted on the local government's website.
The Department must provide templates for the local governments to use when providing data. Local governments must begin collecting data in 2024.
By July 1 of each year, the Department must produce a report which includes the information received from the local governments, a list of those local governments that provide for shorter processing deadlines than the default time frames, and key metrics and findings from the report.
Interior Alterations and Site Plan Review.
Interior alterations are construction activities that do not modify an existing building's layout or its current use, and do not involve work on the exterior that adds to the building's footprint.
Local governments must exclude project permits for interior alterations from site plan review requirements as long as the interior alterations do not add sleeping quarters or bedrooms, cost more than 50 percent of the value of the structure, or increase the total square footage or valuation of the structure sufficiently to require upgraded fire access or fire suppression systems. Interior alterations remain subject to applicable building, plumbing, mechanical, and electrical codes.
Consolidated Permit Review Grant Program.
The Department must, subject to funding from the Legislature, establish a Consolidated Permit Review Grant Program (Program). This Program may award grants to local governments that commit through the passage of an ordinance, a resolution, or by other action to the following permitting requirements:
Local governments in the Program may contract with a third-party business to conduct the consolidated review or to operate as inspection staff. The funds used for such a contract may be reimbursed through the Program.
Any local government that is awarded a grant must provide a quarterly report to the Department including the average and maximum time for permit review during the local government's participation in the Program. If a local government fails to satisfy the terms of the grant, it must enter a 90-day probationary period. If it is still out of compliance at the end of the probationary period, it is no longer eligible to receive grants through the Program.
Digital Permit Review Grant Program and Work Group.
Subject to funding from the Legislature, the Department must establish a grant program to provide grants to local governments to transition their permit review processes from paper systems to software systems capable of processing digital permit applications, virtual inspections, electronic review, and with capacity for video storage.
Subject to funding from the Legislature, the Department must also convene a digital permitting process work group to examine potential licensing and permitting software that local governments can use to make permit review more streamlined and efficient. The Department, along with the Association of Washington Cities and the Washington State Association of Counties, must appoint members to the work group, including a representative of cities and counties, a representative of building industries, and a representative of building officials.
The work group must convene by August 1, 2023, and must issue a final report to the Governor and the appropriate committees of the Legislature by August 1, 2024. This report must evaluate the need for digital permitting systems; the barriers preventing access to, or adoption of, digital permitting systems; the costs and benefits of a statewide system; and provide budgetary, policy, and legislative recommendations to increase the adoption of digital permit review systems, or to establish a statewide system of digital permit review.
(In support) Washington faces a housing affordability and supply crisis. We are currently hundreds of thousands of units short of meeting the demand, and only 15 percent of Washingtonians can afford the cost of a medium-priced home. Permitting timelines are a top concern, as slow permitting adds costs and delays projects, particularly as interest rates rise. Fast and predictable permitting is a key piece of getting more housing built. This bill will establish more certainty in the permitting process, will standardize timelines, and will support new technology for streamlined permitting in the future. This bill is trying to speed up permit processing timelines, and the grant program will help to facilitate that through enabling faster permitting with electronic systems. The bill creates incentives for local governments to be responsive to the permit processing timelines. The goal is to incentivize efficient permitting processes so that more housing can be built. Permit processing, planning reform, and housing funding are the key components of fixing the housing crisis. The state has a vested interest in speeding up permitting, as permitting delays cost the state money, and new housing construction is a huge revenue generator for the state. Cities, counties, and builders have agreed on all of the items in the bill. This bill is one part of the Governor's plan for addressing housing. Building permits need to be included in the permits that should be streamlined, as some cities do not have other permit types.
(Opposed) None.
(Other) The goals of the bill are good, but the current bill would inadvertently lengthen timelines. The bill removes the ability of cities to adjust permitting timelines for specific, outlier projects. This will incentivize cities to adopt longer timelines than necessary to mitigate the risk of an outlier going outside of the timelines and requiring a refund. This will lead to all timelines being extended in order to accommodate the outliers. Cities will also need to be stricter in accepting permits for processing to ensure that the timelines can be met before the clock is started. The cities should retain the option to have longer timelines for specific permits if the city makes written findings. The need to rewrite the city's code will use staff that would otherwise be working on permits.