2347-S2 AMH MORR LIPS 129

                 

2SHB 2347 - H AMD TO H AMD (H-4279.6/14) 791

By Representative Morris

ADOPTED 02/18/2014

    On page 2, line 19 of the amendment, after "90.56.010" strike all material through "90.56.210" on line 20 and insert "required to have a contingency plan pursuant to RCW 90.56.210, other than:

    (I)  A transmission pipeline; or

    (II) A facility that had a permitted receiving capacity of more than fifty thousand barrels of oil per day as of January 1, 2014"

 

 

 

    EFFECT: Removes facilities with a receiving capacity of over 50,000 barrels of oil per day from the facilities whose expansion of receiving capacity by over 15,000 barrels per day authorizes the Department of Ecology to initiate rule-making in certain state waters.

 