On page 2, line 28, after "development" insert ", except that a project involving the handling, storage, and processing of volatile or potentially hazardous materials is excluded from this subsection (5) when the project includes construction of a structure on or near a shoreline more than one thousand feet in length"
EFFECT: Projects involving the handling, storage, and processing of volatile or potentially hazardous materials may not be considered for expedited permit processing when the project includes construction of a shoreline structure more than 1000 feet long.