AN ACT Relating to consistency of growth management act plans and development regulations with the Revised Code of Washington; amending RCW 36.70A.120, 36.70A.130, 36.70A.280, and 36.70A.280; and creating a new section.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
NEW SECTION.  Sec. 1.  When the legislature enacts a statute, the provisions of the law become effective before local governments have the opportunity to update their comprehensive plans and development regulations. The local jurisdiction is not in violation of the growth management act in situations where it complies with the Revised Code of Washington in advance of the comprehensive plan updates set out within this chapter. Local jurisdictions may not prevent what the Revised Code of Washington authorizes just because the comprehensive plan has not been updated.
Sec. 2.  RCW 36.70A.120 and 1993 sp.s. c 6 s 3 are each amended to read as follows:
Each county and city that is required or chooses to plan under RCW 36.70A.040 shall perform its activities and make capital budget decisions in conformity with its comprehensive plan. Each county and city may authorize, permit, and perform activities in compliance with the Revised Code of Washington without being in conformance with a comprehensive plan or land use map.
Sec. 3.  RCW 36.70A.130 and 2012 c 191 s 1 are each amended to read as follows:
(1)(a) Each comprehensive land use plan and development regulations shall be subject to continuing review and evaluation by the county or city that adopted them. Except as otherwise provided, a county or city shall take legislative action to review and, if needed, revise its comprehensive land use plan and development regulations to ensure the plan and regulations comply with the requirements of this chapter according to the deadlines in subsections (4) and (5) of this section.
(b) Except as otherwise provided, a county or city not planning under RCW 36.70A.040 shall take action to review and, if needed, revise its policies and development regulations regarding critical areas and natural resource lands adopted according to this chapter to ensure these policies and regulations comply with the requirements of this chapter according to the deadlines in subsections (4) and (5) of this section. Legislative action means the adoption of a resolution or ordinance following notice and a public hearing indicating at a minimum, a finding that a review and evaluation has occurred and identifying the revisions made, or that a revision was not needed and the reasons therefor.
(c) The review and evaluation required by this subsection shall include, but is not limited to, consideration of critical area ordinances and, if planning under RCW 36.70A.040, an analysis of the population allocated to a city or county from the most recent ten-year population forecast by the office of financial management.
(d) Any amendment of or revision to a comprehensive land use plan shall conform to this chapter. Any amendment of or revision to development regulations shall be consistent with and implement the comprehensive plan. A development regulation that implements a section of the Revised Code of Washington does not have to be consistent with the comprehensive plan and land use map.
(2)(a) Each county and city shall establish and broadly disseminate to the public a public participation program consistent with RCW 36.70A.035 and 36.70A.140 that identifies procedures and schedules whereby updates, proposed amendments, or revisions of the comprehensive plan are considered by the governing body of the county or city no more frequently than once every year, except that, until December 31, 2015, the program shall provide for consideration of amendments of an urban growth area in accordance with RCW 36.70A.1301 once every year. "Updates" means to review and revise, if needed, according to subsection (1) of this section, and the deadlines in subsections (4) and (5) of this section or in accordance with the provisions of subsection (6) of this section. Amendments may be considered more frequently than once per year under the following circumstances:
(i) The initial adoption of a subarea plan. Subarea plans adopted under this subsection (2)(a)(i) must clarify, supplement, or implement jurisdiction-wide comprehensive plan policies, and may only be adopted if the cumulative impacts of the proposed plan are addressed by appropriate environmental review under chapter 43.21C RCW;
(ii) The development of an initial subarea plan for economic development located outside of the one hundred year floodplain in a county that has completed a state-funded pilot project that is based on watershed characterization and local habitat assessment;
(iii) The adoption or amendment of a shoreline master program under the procedures set forth in chapter 90.58 RCW;
(iv) The amendment of the capital facilities element of a comprehensive plan that occurs concurrently with the adoption or amendment of a county or city budget; or
(v) The adoption of comprehensive plan amendments necessary to enact a planned action under RCW ((43.21C.031)) 43.21C.440(2), provided that amendments are considered in accordance with the public participation program established by the county or city under this subsection (2)(a) and all persons who have requested notice of a comprehensive plan update are given notice of the amendments and an opportunity to comment.
(b) Except as otherwise provided in (a) of this subsection, all proposals shall be considered by the governing body concurrently so the cumulative effect of the various proposals can be ascertained. However, after appropriate public participation a county or city may adopt amendments or revisions to its comprehensive plan that conform with this chapter whenever an emergency exists or to resolve an appeal of a comprehensive plan filed with the growth management hearings board or with the court.
(3)(a) Each county that designates urban growth areas under RCW 36.70A.110 shall review, according to the schedules established in subsection (5) of this section, its designated urban growth area or areas, and the densities permitted within both the incorporated and unincorporated portions of each urban growth area. In conjunction with this review by the county, each city located within an urban growth area shall review the densities permitted within its boundaries, and the extent to which the urban growth occurring within the county has located within each city and the unincorporated portions of the urban growth areas.
(b) The county comprehensive plan designating urban growth areas, and the densities permitted in the urban growth areas by the comprehensive plans of the county and each city located within the urban growth areas, shall be revised to accommodate the urban growth projected to occur in the county for the succeeding twenty-year period. The review required by this subsection may be combined with the review and evaluation required by RCW 36.70A.215.
(4) Except as provided in subsection (6) of this section, counties and cities shall take action to review and, if needed, revise their comprehensive plans and development regulations to ensure the plan and regulations comply with the requirements of this chapter as follows:
(a) On or before December 1, 2004, for Clallam, Clark, Jefferson, King, Kitsap, Pierce, Snohomish, Thurston, and Whatcom counties and the cities within those counties;
(b) On or before December 1, 2005, for Cowlitz, Island, Lewis, Mason, San Juan, Skagit, and Skamania counties and the cities within those counties;
(c) On or before December 1, 2006, for Benton, Chelan, Douglas, Grant, Kittitas, Spokane, and Yakima counties and the cities within those counties; and
(d) On or before December 1, 2007, for Adams, Asotin, Columbia, Ferry, Franklin, Garfield, Grays Harbor, Klickitat, Lincoln, Okanogan, Pacific, Pend Oreille, Stevens, Wahkiakum, Walla Walla, and Whitman counties and the cities within those counties.
(5) Except as otherwise provided in subsections (6) and (8) of this section, following the review of comprehensive plans and development regulations required by subsection (4) of this section, counties and cities shall take action to review and, if needed, revise their comprehensive plans and development regulations to ensure the plan and regulations comply with the requirements of this chapter as follows:
(a) On or before June 30, 2015, and every eight years thereafter, for King, Pierce, and Snohomish counties and the cities within those counties;
(b) On or before June 30, 2016, and every eight years thereafter, for Clallam, Clark, Island, Jefferson, Kitsap, Mason, San Juan, Skagit, Thurston, and Whatcom counties and the cities within those counties;
(c) On or before June 30, 2017, and every eight years thereafter, for Benton, Chelan, Cowlitz, Douglas, Kittitas, Lewis, Skamania, Spokane, and Yakima counties and the cities within those counties; and
(d) On or before June 30, 2018, and every eight years thereafter, for Adams, Asotin, Columbia, Ferry, Franklin, Garfield, Grant, Grays Harbor, Klickitat, Lincoln, Okanogan, Pacific, Pend Oreille, Stevens, Wahkiakum, Walla Walla, and Whitman counties and the cities within those counties.
(6)(a) Nothing in this section precludes a county or city from conducting the review and evaluation required by this section before the deadlines established in subsections (4) and (5) of this section. Counties and cities may begin this process early and may be eligible for grants from the department, subject to available funding, if they elect to do so.
(b) A county that is subject to a deadline established in subsection (4)(b) through (d) of this section and meets the following criteria may comply with the requirements of this section at any time within the thirty-six months following the deadline established in subsection (4) of this section: The county has a population of less than fifty thousand and has had its population increase by no more than seventeen percent in the ten years preceding the deadline established in subsection (4) of this section as of that date.
(c) A city that is subject to a deadline established in subsection (4)(b) through (d) of this section and meets the following criteria may comply with the requirements of this section at any time within the thirty-six months following the deadline established in subsection (4) of this section: The city has a population of no more than five thousand and has had its population increase by the greater of either no more than one hundred persons or no more than seventeen percent in the ten years preceding the deadline established in subsection (4) of this section as of that date.
(d) A county or city that is subject to a deadline established in subsection (4)(d) of this section and that meets the criteria established in (b) or (c) of this subsection may comply with the requirements of subsection (4)(d) of this section at any time within the thirty-six months after the extension provided in (b) or (c) of this subsection.
(e) A county that is subject to a deadline established in subsection (5)(b) through (d) of this section and meets the following criteria may comply with the requirements of this section at any time within the twenty-four months following the deadline established in subsection (5) of this section: The county has a population of less than fifty thousand and has had its population increase by no more than seventeen percent in the ten years preceding the deadline established in subsection (5) of this section as of that date.
(f) A city that is subject to a deadline established in subsection (5)(b) through (d) of this section and meets the following criteria may comply with the requirements of this section at any time within the twenty-four months following the deadline established in subsection (5) of this section: The city has a population of no more than five thousand and has had its population increase by the greater of either no more than one hundred persons or no more than seventeen percent in the ten years preceding the deadline established in subsection (5) of this section as of that date.
(g) State agencies are encouraged to provide technical assistance to the counties and cities in the review of critical area ordinances, comprehensive plans, and development regulations.
(7)(a) The requirements imposed on counties and cities under this section shall be considered "requirements of this chapter" under the terms of RCW 36.70A.040(1). Only those counties and cities that meet the following criteria may receive grants, loans, pledges, or financial guarantees under chapter 43.155 or 70.146 RCW:
(i) Complying with the deadlines in this section;
(ii) Demonstrating substantial progress towards compliance with the schedules in this section for development regulations that protect critical areas; or
(iii) Complying with the extension provisions of subsection (6)(b), (c), or (d) of this section.
(b) A county or city that is fewer than twelve months out of compliance with the schedules in this section for development regulations that protect critical areas is making substantial progress towards compliance. Only those counties and cities in compliance with the schedules in this section may receive preference for grants or loans subject to the provisions of RCW 43.17.250.
(8)(a) Except as otherwise provided in (c) of this subsection, if a participating watershed is achieving benchmarks and goals for the protection of critical areas functions and values, the county is not required to update development regulations to protect critical areas as they specifically apply to agricultural activities in that watershed.
(b) A county that has made the election under RCW 36.70A.710(1) may only adopt or amend development regulations to protect critical areas as they specifically apply to agricultural activities in a participating watershed if:
(i) A work plan has been approved for that watershed in accordance with RCW 36.70A.725;
(ii) The local watershed group for that watershed has requested the county to adopt or amend development regulations as part of a work plan developed under RCW 36.70A.720;
(iii) The adoption or amendment of the development regulations is necessary to enable the county to respond to an order of the growth management hearings board or court;
(iv) The adoption or amendment of development regulations is necessary to address a threat to human health or safety; or
(v) Three or more years have elapsed since the receipt of funding.
(c) Beginning ten years from the date of receipt of funding, a county that has made the election under RCW 36.70A.710(1) must review and, if necessary, revise development regulations to protect critical areas as they specifically apply to agricultural activities in a participating watershed in accordance with the review and revision requirements and timeline in subsection (5) of this section. This subsection (8)(c) does not apply to a participating watershed that has determined under RCW 36.70A.720(2)(c)(ii) that the watershed's goals and benchmarks for protection have been met.
Sec. 4.  RCW 36.70A.280 and 2014 c 147 s 3 are each amended to read as follows:
(1) The growth management hearings board shall hear and determine only those petitions alleging either:
(a) That, except as provided otherwise by this subsection, a state agency, county, or city planning under this chapter is not in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to the adoption of shoreline master programs or amendments thereto, or chapter 43.21C RCW as it relates to plans, development regulations, or amendments, adopted under RCW 36.70A.040 or chapter 90.58 RCW. Nothing in this subsection authorizes the board to hear petitions alleging noncompliance with RCW 36.70A.5801;
(b) That the twenty-year growth management planning population projections adopted by the office of financial management pursuant to RCW 43.62.035 should be adjusted;
(c) That the approval of a work plan adopted under RCW 36.70A.735(1)(a) is not in compliance with the requirements of the program established under RCW 36.70A.710;
(d) That regulations adopted under RCW 36.70A.735(1)(b) are not regionally applicable and cannot be adopted, wholly or partially, by another jurisdiction;
(e) That a department certification under RCW 36.70A.735(1)(c) is erroneous; or
(f) That a department determination under RCW 36.70A.060(1)(d) is erroneous.
(2) Actions and development regulations enacted, adopted, or implemented by a county or city in conformance with provisions of the Revised Code of Washington enacted within one year of or subsequent to the adoption of a comprehensive plan under the eight-year schedule of RCW 36.70A.130 are not subject to challenge as being inconsistent with the comprehensive plan until at least eight years have passed without the comprehensive plan being updated to reflect modified provisions of the Revised Code of Washington.
(3) A petition may be filed only by: (a) The state, or a county or city that plans under this chapter; (b) a person who has participated orally or in writing before the county or city regarding the matter on which a review is being requested; (c) a person who is certified by the governor within sixty days of filing the request with the board; or (d) a person qualified pursuant to RCW 34.05.530.
(((3))) (4) For purposes of this section "person" means any individual, partnership, corporation, association, state agency, governmental subdivision or unit thereof, or public or private organization or entity of any character.
(((4))) (5) To establish participation standing under subsection (((2))) (3)(b) of this section, a person must show that his or her participation before the county or city was reasonably related to the person's issue as presented to the board.
(((5))) (6) When considering a possible adjustment to a growth management planning population projection prepared by the office of financial management, the board shall consider the implications of any such adjustment to the population forecast for the entire state.
The rationale for any adjustment that is adopted by the board must be documented and filed with the office of financial management within ten working days after adoption.
If adjusted by the board, a county growth management planning population projection shall only be used for the planning purposes set forth in this chapter and shall be known as the "board adjusted population projection." None of these changes shall affect the official state and county population forecasts prepared by the office of financial management, which shall continue to be used for state budget and planning purposes.
Sec. 5.  RCW 36.70A.280 and 2011 c 360 s 17 are each amended to read as follows:
(1) The growth management hearings board shall hear and determine only those petitions alleging either:
(a) That, except as provided otherwise by this subsection, a state agency, county, or city planning under this chapter is not in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to the adoption of shoreline master programs or amendments thereto, or chapter 43.21C RCW as it relates to plans, development regulations, or amendments, adopted under RCW 36.70A.040 or chapter 90.58 RCW. Nothing in this subsection authorizes the board to hear petitions alleging noncompliance with RCW 36.70A.5801;
(b) That the twenty-year growth management planning population projections adopted by the office of financial management pursuant to RCW 43.62.035 should be adjusted;
(c) That the approval of a work plan adopted under RCW 36.70A.735(1)(a) is not in compliance with the requirements of the program established under RCW 36.70A.710;
(d) That regulations adopted under RCW 36.70A.735(1)(b) are not regionally applicable and cannot be adopted, wholly or partially, by another jurisdiction; or
(e) That a department certification under RCW 36.70A.735(1)(c) is erroneous.
(2) Actions and development regulations enacted, adopted, or implemented by a county or city in conformance with provisions of the Revised Code of Washington enacted within one year of or subsequent to the adoption of a comprehensive plan under the eight-year schedule of RCW 36.70A.130 are not subject to challenge as being inconsistent with the comprehensive plan until at least eight years have passed without the comprehensive plan being updated to reflect modified provisions of the Revised Code of Washington.
(3) A petition may be filed only by: (a) The state, or a county or city that plans under this chapter; (b) a person who has participated orally or in writing before the county or city regarding the matter on which a review is being requested; (c) a person who is certified by the governor within sixty days of filing the request with the board; or (d) a person qualified pursuant to RCW 34.05.530.
(((3))) (4) For purposes of this section "person" means any individual, partnership, corporation, association, state agency, governmental subdivision or unit thereof, or public or private organization or entity of any character.
(((4))) (5) To establish participation standing under subsection (((2))) (3)(b) of this section, a person must show that his or her participation before the county or city was reasonably related to the person's issue as presented to the board.
(((5))) (6) When considering a possible adjustment to a growth management planning population projection prepared by the office of financial management, the board shall consider the implications of any such adjustment to the population forecast for the entire state.
The rationale for any adjustment that is adopted by the board must be documented and filed with the office of financial management within ten working days after adoption.
If adjusted by the board, a county growth management planning population projection shall only be used for the planning purposes set forth in this chapter and shall be known as the "board adjusted population projection." None of these changes shall affect the official state and county population forecasts prepared by the office of financial management, which shall continue to be used for state budget and planning purposes.