2020 Archive
Chapter 463-58 WAC
Last Update: 2/13/09
CHARGES FOR INDEPENDENT CONSULTANT STUDY, REGULAR AND EXPEDITED APPLICATION PROCESSING, ELECTRICAL TRANSMISSION PREAPPLICATIONS, DETERMINING COMPLIANCE AND POTENTIAL SITE STUDY
|
WAC Sections |
463-58-010 | Purpose. |
463-58-020 | Costs for the independent consultant studies. |
463-58-030 | Costs for regular application processing. |
463-58-040 | Costs for expedited application processing. |
463-58-050 | Costs for determining compliance. |
463-58-060 | Costs for potential site studies. |
463-58-065 | Costs for preapplication process for electrical transmission facilities. |
463-58-070 | Failure to provide necessary costs. |
463-58-080 | Payment, reporting and auditing procedures. |