WSR 08-09-023

PERMANENT RULES

SUPERINTENDENT OF

PUBLIC INSTRUCTION

[ Filed April 8, 2008, 11:35 a.m. , effective May 9, 2008 ]


     Effective Date of Rule: Thirty-one days after filing.

     Purpose: WAC 392-343-080 Value engineering studies, constructability reviews, and building commissioning -- Requirements and definition, lowers the threshold for state match funding for building commissioning for common school construction; allows for state match funding for school construction starting at 5,000 SF.

     Citation of Existing Rules Affected by this Order: Amending WAC 392-343-080.

     Statutory Authority for Adoption: RCW 28A.525.020 Duties of superintendent of public instruction.

      Adopted under notice filed as WSR 08-04-084 on February 5, 2008.

     Number of Sections Adopted in Order to Comply with Federal Statute: New 0, Amended 0, Repealed 0; Federal Rules or Standards: New 0, Amended 0, Repealed 0; or Recently Enacted State Statutes: New 0, Amended 0, Repealed 0.

     Number of Sections Adopted at Request of a Nongovernmental Entity: New 0, Amended 0, Repealed 0.

     Number of Sections Adopted on the Agency's Own Initiative: New 0, Amended 0, Repealed 0.

     Number of Sections Adopted in Order to Clarify, Streamline, or Reform Agency Procedures: New 0, Amended 1, Repealed 0.

     Number of Sections Adopted Using Negotiated Rule Making: New 0, Amended 0, Repealed 0;      Pilot Rule Making: New 0, Amended 0, Repealed 0; or Other Alternative Rule Making: New 0, Amended 0, Repealed 0.

     Date Adopted: April 8, 2008.

Dr. Terry Bergeson

Superintendent of

Public Instruction

OTS-1315.1


AMENDATORY SECTION(Amending WSR 06-16-032, filed 7/25/06, effective 8/25/06)

WAC 392-343-080   Value engineering studies, constructability reviews, and building commissioning -- Requirements and definition.   At the appropriate time in the design process for a school facility approved by the superintendent of public instruction, the district shall prepare a value engineering study, complete a constructability review, and perform building commissioning for all projects greater than fifty thousand square feet. Value engineering studies((,)) and constructability reviews((, and building commissioning)) shall be optional for projects larger than fifteen thousand square feet but less than fifty thousand square feet. Any project which includes fifteen thousand square feet or less shall be exempt from this requirement. For projects subject to chapter 39.35D RCW, building commissioning must be performed for all projects over five thousand square feet. For the purpose of this section, a value engineering study is defined as a cost control technique which is based on the use of a systematic, creative analysis of the functions of the facility with the objective of identifying unnecessary high costs or functions and/or identifying cost savings that may result in high maintenance and operation costs. The study shall consist of a forty-hour workshop involving a minimum of a five-person team pursuant to WAC 392-344-065. A constructability review is defined as a cost control technique which is based on the review of project documents by mechanical, electrical, structural, construction, and design professionals prior to a request for bids. The purpose of a constructability review is to identify potential claim or problem areas and deficiencies that may occur as a result of errors, ambiguities, omissions, discrepancies, and conflicts in design documents. The study shall consist of a forty-hour workshop involving a minimum of a five-person team pursuant to WAC 392-344-066. Building commissioning is defined as the process of verifying that the installation and performance of selected building systems meet or exceed the specified design criteria and therefore satisfy the design intent. Building commissioning shall include a physical inspection, functional performance testing, listing of noted deficiencies, and a final commissioning report. Building commissioning shall be performed by a professional agent or authority not contractually or otherwise financially associated with the project design team or contractor. A district shall be eligible for state assistance for a value engineering study, a constructability review, and building commissioning for each qualifying project. The maximum amount of assistance for ((each component)) value engineering studies and constructability reviews of the study package shall be the state matching percentage multiplied by the greater of the following:

     (1) Two-fifths of one percent of the area cost allowance multiplied by the square foot area for the fiscal year funded; or

     (2) Twenty thousand dollars.

     The maximum amount of assistance for building commissioning shall be as follows:

     (a) Seven thousand five hundred dollars for projects larger than five thousand square feet but less than ten thousand square feet;

     (b) Ten thousand dollars for projects ten thousand square feet but less than fifteen thousand square feet;

     (c) The larger of the following for projects fifteen thousand square feet and above:

     (i) Two-fifths of one percent of the area cost allowance multiplied by the square foot area for the fiscal year funded; or

     (ii) Twenty thousand dollars.

[Statutory Authority: RCW 28A.525.020. 06-16-032, amended and recodified as § 392-343-080, filed 7/25/06, effective 8/25/06. Statutory Authority: RCW 28A.47.830 and 28A.525.020. 01-19-042, § 180-27-080, filed 9/14/01, effective 10/15/01. Statutory Authority: RCW 28A.525.020. 99-24-127, § 180-27-080, filed 12/1/99, effective 1/1/00; 98-19-143, § 180-27-080, filed 9/23/98, effective 10/24/98. Statutory Authority: RCW 28A.47.830. 83-21-066 (Order 11-83), § 180-27-080, filed 10/17/83.]

© Washington State Code Reviser's Office