WSR 14-01-078
PROPOSED RULES
DEPARTMENT OF ECOLOGY
[Order 13-01—Filed December 16, 2013, 11:36 a.m.]
Original Notice.
Preproposal statement of inquiry was filed as WSR 13-05-019.
Title of Rule and Other Identifying Information: The department of ecology (ecology) proposes to adopt amendments to certain portions of State Environmental Policy Act (SEPA), chapter 197-11 WAC. This rule provides uniform requirements for compliance with SEPA. Ecology proposes repealing the SEPA model ordinance, chapter 173-806 WAC and providing this information in guidance. Ecology also proposes repealing public records, chapter 197-06 WAC. This rule is out of date and refers to the council on environmental policy that no longer exists. The sections of the rule relating to public records have been superseded by chapter 173-03 WAC.
Hearing Location(s): Department of Ecology, 300 Desmond Drive, Lacey, WA 98503, call-in number to participate and provide comments by phone 1-800-704-9804 – Pin number 8386377#, on January 29, 2014. Hearing #1 starts at 1:30 p.m. and Hearing #2 starts at 6:30 p.m. Ecology will have a brief presentation, followed by a question and answer session followed by the formal hearing.
Date of Intended Adoption: March 12, 2014.
Submit Written Comments to: Fran Sant, Department of Ecology, 300 Desmond Drive, Lacey, WA 98503, (360) 407-6004, e-mail separulemaking@ecy.wa.gov, fax (360) 407-6904, by February 5, 2014.
Assistance for Persons with Disabilities: Contact shorelands and environmental assistance program, by January 22, 2014, (360) 407-6600.
Purpose of the Proposal and Its Anticipated Effects, Including Any Changes in Existing Rules: Ecology proposes to adopt amendments to chapter 197-11 WAC, State Environmental Policy Act (SEPA). The rule changes include, but are not limited to the following:
Expanded use of NEPA documentation by lead agencies.
Update of definition for "lands covered by water."
For adoption of increased flexible thresholds for minor new construction, more specific requirements regarding cultural resources and an increase in notice to sixty days.
Expanded minor new construction exemptions for installation or removal of tanks and solar energy projects.
New maintenance exemption for smaller dredging projects.
Update of exemption for land use decisions to provide that most land use decisions will be exempt for otherwise exempt projects, with some limited exceptions.
New exemption for formation of special districts.
New exemption for text amendments of ordinances or codes that do not change environmental standards.
Update of utility exemption for water pipe size to align with industry standards.
Allow department of natural resources (DNR) rock sales on state owned land.
Updated Washington state department of transportation (WSDOT) maintenance exemptions.
Environmental checklist updates.
Other minor updates, clarifications and technical corrections.
Ecology proposes to repeal chapter 173-806 WAC in response to changes being made in chapter 197-11 WAC and will make the model ordinance available as guidance rather than rule.
Ecology also proposes to repeal chapter 197-06 WAC. This rule is being repealed because (1) a number of the provisions are specific to the council on environmental policy that was established in the 1970s and no longer exists; (2) the sections of the rule related to public records have been superseded by chapter 173-03 WAC.
Reasons Supporting Proposal: Section 301, chapter 1, Laws of 2012 1st sp. sess. (2ESSB 6406) directed ecology to update the SEPA rules. The 2012 legislature directed ecology to modernize the SEPA rules in 2013:
Update, but not decrease, the thresholds for all other projects actions in WAC 197-11-800.
Create categorical exemptions for minor code amendments that do not lessen environmental protection.
Propose methods for integrating the SEPA process with provisions of the Growth Management Act.
In addition ecology was also directed by 2ESSB 6406 to convene an advisory committee to assist ecology in:
Updating the environmental checklist.
Ensure that state agencies, other interested parties and federally recognized tribes receive notice about projects under chapter 43.21C RCW and through other means.
Ecology is also making technical corrections to rule language in order to update and modernize the SEPA rules.
Ecology is repealing chapter 173-806 WAC and making the SEPA model ordinance available as guidance rather than rule. Ecology will be able to more easily update the guidance in the future.
Ecology is repealing chapter 197-06 WAC because the rule is out-of-date and makes reference to the council on environmental policy that no longer exists.
Statutory Authority for Adoption: SEPA, RCW 43.21C.110, see also RCW 43.21C.100 which abolished the council of environmental policy as of June 30, 1976.
Statute Being Implemented: Chapter 43.21C RCW.
Rule is not necessitated by federal law, federal or state court decision.
Name of Proponent: Department of ecology, governmental.
Name of Agency Personnel Responsible for Drafting and Implementation: Brenden McFarland, Department of Ecology, Lacey, Washington, (360) 407-6976; and Enforcement: Not applicable.
No small business economic impact statement has been prepared under chapter 19.85 RCW. The proposed amendments meet the criteria of exemption from analysis under RCW 19.85.030 which requires an agency to prepare a small business economic impact state [statement] (SBEIS) "if the proposed rule will impose more than minor cost on business or any industry." The proposed amendments to ecology's SEPA rules don't impose any costs on business. Therefore, an SBEIS is not required for the proposed rule amendments.
A cost-benefit analysis is required under RCW 34.05.328. A preliminary cost-benefit analysis may be obtained by contacting Fran Sant, Department of Ecology, P.O. Box 47703, Olympia, WA 98504, phone (360) 407-6004, fax (360) 407-6904, e-mail separulemaking@ecy.wa.gov.
December 15, 2013
Polly Zehm
Deputy Director
AMENDATORY SECTION (Amending WSR 97-21-030, filed 10/10/97, effective 11/10/97)
WAC 197-11-158 SEPA/GMA project review—Reliance on existing plans, laws, and regulations.
(1) In reviewing the environmental impacts of a project and making a threshold determination, a GMA county/city may, at its option, determine that the requirements for environmental analysis, protection, and mitigation measures in the GMA county/city's development regulations and comprehensive plan adopted under chapter 36.70A RCW, and in other applicable local, state, or federal laws or rules, provide adequate analysis of and mitigation for some or all of the specific adverse environmental impacts of the project.
(2) In making the determination under subsection (1) of this section, the GMA county/city shall:
(a) Review the environmental checklist and other information about the project;
(b) Identify the specific probable adverse environmental impacts of the project and determine whether the impacts have been:
(i) Identified in the comprehensive plan, subarea plan, or applicable development regulations through the planning and environmental review process under chapter 36.70A RCW or this chapter, or in other local, state, or federal rules or laws; and
(ii) Adequately addressed in the comprehensive plan, subarea plan, applicable development regulations, or other local, state, or federal rules or laws by:
(A) Avoiding or otherwise mitigating the impacts; or
(B) The legislative body of the GMA county/city designating as acceptable the impacts associated with certain levels of service, land use designations, development standards, or other land use planning required or allowed by chapter 36.70A RCW;
(c) Base or condition approval of the project on compliance with the requirements or mitigation measures in the comprehensive plan, subarea plan, applicable development regulations, or other local, state, or federal rules or laws; and
(d) Place the following statement in the threshold determination if all of a project's impacts are addressed by other applicable laws and no conditions will be required under SEPA: "The lead agency has determined that the requirements for environmental analysis, protection, and mitigation measures have been adequately addressed in the development regulations and comprehensive plan adopted under chapter 36.70A RCW, and in other applicable local, state, or federal laws or rules, as provided by RCW 43.21C.240 and WAC 197-11-158. Our agency will not require any additional mitigation measures under SEPA."
(3) Project specific impacts that have not been adequately addressed as described in subsection (2) of this section might be probable significant adverse environmental impacts requiring additional environmental review. Examples of project specific impacts that may not have been adequately addressed include, but are not limited to, impacts resulting from changed conditions, impacts indicated by new information, impacts not reasonably foreseeable in the GMA planning process, or impacts specifically reserved in a plan EIS for project review.
(4) In deciding whether a project specific adverse environmental impact has been adequately addressed by an existing rule or law of another agency with jurisdiction, the GMA county/city shall consult orally or in writing with that agency and may expressly defer to that agency. In making this deferral, the GMA county/city shall base or condition its project approval on compliance with these other existing rules or laws.
(5) If a GMA county/city's comprehensive plan, subarea plan, or development regulations adequately address some or all of a project's probable specific adverse environmental impacts, as determined under subsections (1) and (2) of this section, the GMA county/city shall not require additional mitigation under this chapter for those impacts.
(6) In making the determination in subsection (1) of this section, nothing in this section requires review of the adequacy of the environmental analysis associated with the comprehensive plans and development regulations that are being relied upon to make that determination.
AMENDATORY SECTION (Amending WSR 97-21-030, filed 10/10/97, effective 11/10/97)
WAC 197-11-164 Planned actions—Definition and criteria.
(1) Under RCW ((43.21C.031)) 43.21C.440, GMA counties/cities may designate a planned action. A planned action means one or more types of project action that:
(a) Are designated planned actions by an ordinance or resolution adopted by a GMA county/city;
(b) Have had the significant environmental impacts adequately addressed in an EIS prepared in conjunction with:
(i) A comprehensive plan or subarea plan adopted under chapter 36.70A RCW; or
(ii) A fully contained community, a master planned resort, a master planned development, or a phased project;
(c) Are subsequent or implementing projects for the proposals listed in (b) of this subsection;
(d) Are located within an urban growth area, as defined in RCW 36.70A.030, or are located within a master planned resort;
(e) Are not essential public facilities, as defined in RCW 36.70A.200; and
(f) Are consistent with a comprehensive plan adopted under chapter 36.70A RCW.
(2) A GMA county/city shall limit planned actions to certain types of development or to specific geographical areas that are less extensive than the jurisdictional boundaries of the GMA county/city.
(3) A GMA county/city may limit a planned action to a time period identified in the EIS or the designating ordinance or resolution adopted under WAC 197-11-168.
AMENDATORY SECTION (Amending WSR 95-07-023, filed 3/6/95, effective 4/6/95)
WAC 197-11-235 SEPA/GMA integration documents.
(1) "Integrating documents." Formal SEPA documents may be prepared as companion documents to accompany proposed GMA actions or may be integrated into the documentation of GMA actions. This section clarifies how WAC 197-11-640 (all SEPA documents) and WAC 197-11-425 through 197-11-442 (EISs) apply to integrated SEPA/GMA documents. The overriding consideration is the quality of information and analysis at the appropriate scope and level of detail for the particular GMA document, and not the format, length or bulk of the document.
(2) "Document format."
(a) There is no standard format for an integrated GMA document. For example an integrated comprehensive plan may look more like a plan preceded by an environmental summary (see WAC 197-11-235(5)), in contrast to a format described in WAC 197-11-430. Any separately bound supporting documents shall be clearly identified in the integrated document.
(b) An integrated GMA document is not required to contain a separate section on affected environment, significant impacts, and mitigation measures under WAC 197-11-440(6), as long as this information is summarized as required by this section, and the basis for this information can be readily found in the document and the supporting record.
(3) "Integrated non-EIS documents."
(a) If a proposed GMA action is not likely to have a significant adverse environmental impact, an integrated GMA document shall be prepared that combines the formal SEPA document (such as an environmental checklist/DNS, a notice of adoption or addendum) with the GMA document. The provisions of WAC 197-11-235 (1) and (2) apply to these integrated documents.
(b) If an environmental checklist is used and a DNS issued, only Parts A (which serves as a fact sheet), C (responsible official's signature), and D (nonproject checklist) need be prepared, plus an environmental summary as specified in WAC 197-11-235(5). Part D and the summary may be combined.
(c) If an addendum is to accompany or be incorporated into an integrated GMA document, it shall contain the information specified in WAC 197-11-235(5) for an environmental summary.
(4) "Plan/EIS documents." Because these documents need to contain sufficient environmental analysis for GMA actions, the same documents that meet GMA planning needs should constitute the SEPA documents for GMA actions and should provide a basis for future decisions on projects. An integrated document will constitute the necessary formal SEPA document, if accompanied by the following (as further specified by subsections (5) through (7) of this section):
(a) Environmental summary and fact sheet;
(b) Concise analysis of alternatives;
(c) Comments and responses; and
(d) Appropriate technical and other materials.
(5) "Environmental summary and fact sheet."
(a) The environmental summary includes the contents required in WAC 197-11-440(4). It should emphasize the major conclusions, significant areas of controversy and uncertainty, if any, and the issues to be resolved, including the environmental choices to be made and the effectiveness of mitigation measures. The summary is not to be a summary of the GMA action.
(b) The summary should highlight from an environmental perspective the main options that would be preserved or foreclosed by the proposed GMA action. It should reflect SEPA's substantive policies and focus on any significant irreversible or irretrievable commitments of natural resources that would be likely to harm long-term environmental productivity, taking into account cumulative impacts. A summary of the principal environmental impacts may be presented in chart or matrix form, summarizing the relevant elements of the environment and impact assessment required by WAC 197-11-440 (6)(b) through (e). The summary may discuss nonenvironmental factors and should do so if relevant to resolving issues concerning the main environmental choices facing decision makers.
(c) The summary should be no longer than necessary (generally fifteen to thirty pages for a plan/EIS, less for other integrated documents) and include tables or graphics to assist readability.
(d) At a minimum the fact sheet shall contain the information required in WAC 197-11-440(2). The fact sheet shall precede the summary in the integrated GMA document.
(6) "Concise analysis of alternatives."
(a) This analysis focuses on a comparative evaluation of the environmental consequences of the principal alternative courses of action that are or have been under consideration in the GMA planning process, as provided by WAC 197-11-440(5). The alternatives analysis shall evaluate the proposed GMA action compared to the principal alternative concepts and plan elements or regulatory options that were considered. This analysis allows decision makers, other agencies and the public to determine if the proposed GMA action can or should be revised before adoption to avoid or reduce environmental or other impacts. These alternatives may be:
(i) Those which are actively being considered; or
(ii) Those considered and screened earlier as part of a public GMA planning process.
(b) Descriptive material on the features of the alternatives (in contrast to comparing their impacts) should be kept to the minimum necessary to understand the comparative evaluation. If more description is necessary, it should be cited or located in the supporting record. Depending on the scope of the GMA action, the text of the alternatives analysis should be less than forty pages.
(7) "Comments and responses." The inclusion of comments and responses is not required for a draft integrated GMA document. For a final integrated document, comments (or a summary of comments) shall be compiled and response prepared as provided in WAC 197-11-560(3). A jurisdiction may include comments (or a summary of comments) received during the scoping process or on preliminary documents, as well as general or specific responses to these comments if any have been prepared, with the integrated GMA document on a proposed GMA action. If this approach is not used, these preliminary comments shall be included in the supporting record.
(8) "Supporting record, analyses, and materials."
(a) The integrated GMA document shall contain a list of the principal analytical documents and other materials (such as meeting minutes, maps, models, tapes or videos) that have been prepared, received, or used in developing the GMA action (see WAC 197-11-090). These materials shall be considered to be incorporated by reference under SEPA and part of the supporting record for SEPA compliance, and their contents need not be further described as required in WAC 197-11-635. Annotated lists are encouraged, but not required, to assist current and future reviewers.
(b) Materials in the supporting record should enable agencies and members of the public to identify and review the planning basis for the conclusions and analysis presented in the integrated GMA document as provided in the "procedural criteria" for preparing plan documents.
AMENDATORY SECTION (Amending WSR 97-21-030, filed 10/10/97, effective 11/10/97)
WAC 197-11-238 SEPA/GMA integration monitoring.
Monitoring information is important to maintain the usefulness of the environmental analysis in plans and development regulations for project-level review and to update plans under chapter 36.70A RCW. GMA counties/cities are encouraged to establish a process for monitoring the cumulative impacts of permit decisions and conditions, and to use that data to update the information about existing conditions for the built and natural environment. If a monitoring process is developed, it should be established at the time information on existing conditions is developed. Annual or periodic reports summarizing the data and documenting trends are encouraged.
AMENDATORY SECTION (Amending WSR 97-21-030, filed 10/10/97, effective 11/10/97)
WAC 197-11-508 SEPA register.
(1) The department of ecology shall prepare a SEPA register ((at least weekly)) that is web-based and updated daily, giving notice of all environmental documents required to be sent to the department of ecology under these rules, specifically:
(a) DNSs under WAC 197-11-340(2);
(b) DSs (scoping notices) under WAC 197-11-408;
(c) EISs under WAC 197-11-455, 197-11-460, 197-11-620, and 197-11-630;
(d) Notices of action under RCW 43.21C.080 and 43.21C.087; and
(e) Notices in the optional DNS process under WAC 197-11-355 (2)(d)(i) and (5).
(2) All agencies shall submit the environmental documents listed in subsection (1) of this section to the department promptly and in accordance with procedures established by the department.
(3) Agencies are encouraged to refer to the SEPA register for notice of SEPA documents which may affect them.
(4) The department:
(a) Shall establish the method for distributing the SEPA register, which may include listing on internet, publishing and mailing to interested persons, or any other method deemed appropriate by the department((.));
(b) May establish a reasonable format for the SEPA register;
(c) May charge a reasonable fee for the SEPA register as allowed by law, in at least the amount allowed by chapter 42.17 RCW, from agencies, members of the public, and interested organizations.
(5) Members of the public, citizen and community groups, and educational institutions are encouraged to refer to the SEPA register for notice of SEPA actions which may affect them.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-510 Public notice.
(1) When these rules require notice to be given under this section, the lead agency must use reasonable methods to inform the public and other agencies that an environmental document is being prepared or is available and that public hearing(s), if any, will be held. The agency may use its existing notice procedures.
Examples of reasonable methods to inform the public are:
(a) Posting the property, for site-specific proposals;
(b) Publishing notice in a newspaper of general circulation in the county, city, or general area where the proposal is located;
(c) Notifying public or private groups with known interest in a certain proposal or in the type of proposal being considered;
(d) Notifying the news media;
(e) Placing notices in appropriate regional, neighborhood, ethnic, or trade journals; ((and/or))
(f) Publishing notice in agency newsletters and/or sending notice to agency mailing lists (either general lists or lists for specific proposals or subject areas); and/or
(g) Mailing or e-mailing notice to any person, group or agency who has requested notice.
(2) Each agency shall specify its method of public notice in its SEPA procedures, WAC 197-11-904 and 197-11-906. If an agency does not specify its method of public notice or does not adopt SEPA procedures, the agency shall use methods (a) and (b) in subsection (1).
(3) Documents which are required to be sent to the department of ecology under these rules will be published in the SEPA register, which will also constitute a form of public notice. However, publication in the SEPA register shall not, in itself, meet compliance with this section.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-610 Use of NEPA documents.
(1) An agency may adopt any environmental analysis prepared under the National Environmental Policy Act (NEPA) by following WAC 197-11-600 and 197-11-630.
(2) A NEPA environmental assessment (EA) or documented categorical exclusion may be adopted to satisfy requirements for a determination of nonsignificance ((or EIS)), if the requirements of WAC 197-11-340, 197-11-600, and 197-11-630 are met and elements of the environment in WAC 197-11-444 are adequately addressed.
(3) An agency may adopt a NEPA EIS as a substitute for preparing a SEPA EIS if:
(a) The requirements of WAC 197-11-360, 197-11-600, and 197-11-630 are met (in which case the procedures in Parts Three ((through)), Four, and Five of these rules for preparing an EIS shall not apply); and
(b) The federal EA or EIS is not found inadequate: (i) By a court; (ii) by the council on environmental quality (CEQ) (or is at issue in a predecision referral to CEQ) under the NEPA regulations; or (iii) by the administrator of the United States Environmental Protection Agency under section 309 of the Clean Air Act, 42 U.S.C 1857.
(4) Subsequent use by another agency of a federal EIS, adopted under subsection (3) of this section, for the same (or substantially the same) proposal does not require adoption, unless the criteria in WAC 197-11-600(3) are met.
(5) If the lead agency has not held a public hearing within its jurisdiction to obtain comments on the adequacy of adopting a federal environmental document as a substitute for preparing a SEPA EIS, a public hearing for such comments shall be held if, within thirty days of circulating its statement of adoption, a written request is received from at least fifty persons who reside within the agency's jurisdiction or are adversely affected by the environmental impact of the proposal. The agency shall reconsider its adoption of the federal document in light of public hearing comments.
Reviser's note: The typographical error in the above section occurred in the copy filed by the agency and appears in the Register pursuant to the requirements of RCW 34.08.040.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-756 Lands covered by water.
(1) "Lands covered by water" means lands underlying the water areas of the state below the ordinary high water mark, including salt waters, tidal waters, estuarine waters, natural water courses, lakes, ponds, artificially impounded waters, ((marshes, and swamps)) and wetlands. As specified in Part Nine certain categorical exemptions do not apply ((to)) when a portion or all of a project or proposal is undertaken on lands covered by water((, as specified in Part Nine)).
(2) Wetlands - Wetlands are defined as areas that are inundated or saturated by surface water or groundwater at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, bogs, and similar areas. Wetlands include those artificial wetlands intentionally created from nonwetland areas created to mitigate conversion of wetlands. Wetlands do not include those artificial wetlands intentionally created from nonwetland sites including, but not limited to, irrigation and drainage ditches, grass-lined swales, canals, detention facilities, wastewater treatment facilities, farm ponds, and landscape amenities, or those wetlands created after July 1, 1990, that were unintentionally created as a result of the construction of a road, street, or highway.
(3) "Lands covered by water" does not include adjacent lands and designated buffers above the ordinary high water mark.
AMENDATORY SECTION (Amending WSR 13-02-065, filed 12/28/12, effective 1/28/13)
WAC 197-11-800 Categorical exemptions.
The proposed actions contained in Part Nine are categorically exempt from threshold determination and EIS requirements, subject to the rules and limitations on categorical exemptions contained in WAC 197-11-305.
Note:
The statutory exemptions contained in chapter 43.21C RCW are not included in Part Nine. Chapter 43.21C RCW should be reviewed in determining whether a proposed action not listed as categorically exempt in Part Nine is exempt by statute from threshold determination and EIS requirements.
(1) Minor new construction - Flexible thresholds.
(a) The exemptions in this subsection apply to all licenses required to undertake the construction in question((, except when a rezone or any license governing emissions to the air or discharges to water is required)). To be exempt under this subsection, the project must be equal to or smaller than the exempt level. For a specific proposal, the exempt level in (b) of this subsection shall control, unless the city/county in which the project is located establishes an exempt level under (c) of this subsection. If the proposal is located in more than one city/county, the lower of the agencies' adopted levels shall control, regardless of which agency is the lead agency. The exemptions in this subsection apply except when the project:
(i) Is undertaken wholly or partly on lands covered by water;
(ii) Requires a license governing discharges to water that is not exempt under RCW 43.21C.0383;
(iii) Requires a license governing emissions to air that is not exempt under RCW 43.21C.0381 or WAC 197-11-800 (7) or (8); or
(iv) Requires a land use decisions that is not exempt under WAC 197-11-800(6).
(b) The following types of construction shall be exempt((, except when undertaken wholly or partly on lands covered by water)):
(i) The construction or location of four detached single family residential units.
(ii) The construction or location of four multifamily residential units.
(iii) The construction of a barn, loafing shed, farm equipment storage building, produce storage or packing structure, or similar agricultural structure, covering 10,000 square feet, and to be used only by the property owner or his or her agent in the conduct of farming the property. This exemption shall not apply to feed lots.
(iv) The construction of an office, school, commercial, recreational, service or storage building with 4,000 square feet of gross floor area, and with associated parking facilities designed for twenty automobiles. This exemption includes ((stand-alone)) parking lots for twenty or fewer automobiles not associated with a structure.
(v) Any ((landfill)) fill or excavation of 100 cubic yards throughout the total lifetime of the fill or excavation ((not associated with an exempt project in subsection (b)(i), (ii), (iii), or (iv); and any fill or excavation classified as a Class I, II, or III forest practice under RCW 76.09.050 or regulations thereunder)) and any excavation, fill or grading necessary for an exempt project in (i), (ii), (iii), or (iv) of this subsection shall be exempt.
(c) Cities, towns or counties may raise the exempt levels up to the maximum specified in (d) of this subsection by implementing ordinance or resolution. Such levels shall be specified in the agency's SEPA procedures (WAC 197-11-904). Separate maximum optional thresholds are established in (d) of this subsection applying to both incorporated areas and unincorporated urban growth areas in fully planning jurisdictions under RCW 36.70A.040; other unincorporated areas in fully planning counties; and jurisdictions in all other counties. Agencies may adopt the maximum level or a level between the minimum and maximum level. An agency may adopt a system of several exempt levels ((()), such as different levels for different geographic areas(())), and mixed use projects.
At a minimum, the following process shall be met in order to raise the exempt levels.
(i) Documentation that the requirements for environmental analysis, protection and mitigation for impacts to elements of the environment (listed in WAC 197-11-444) have been adequately addressed for the development exempted. The requirements may be addressed in specific adopted development regulations, and applicable state and federal regulations.
(ii) Description in the findings or other appropriate section of the adopting ordinance or resolution of the locally established project-level public comment opportunities that are provided for proposals included in these increased exemption levels.
(iii) Before adopting the ordinance or resolution containing the proposed new exemption levels, the local government shall provide a minimum of ((twenty-one)) sixty days notice to affected tribes, agencies with expertise, affected jurisdictions, the department of ecology, and the public and provide an opportunity for comment.
(iv) For cultural and historic resources (per WAC 197-11-444), documentation that environmental analysis, protection and mitigation have been adequately addressed for the development exempted shall include a minimum of the following:
• Use of available data and other project review tools regarding known and likely cultural and historic resources, such as inventories and predictive models provided by the Washington department of archaeology and historic preservation, other agencies, and tribal governments.
• Planning and permitting processes that ensure compliance with applicable laws including chapters 27.44, 27.53, 68.50, and 68.60 RCW.
• Local development regulations that include at minimum preproject cultural resource review where warranted, and standard inadvertent discovery language (SIDL) for all projects.
(d) The maximum exemption levels applicable to (c) of this subsection are:
 
Fully planning GMA counties
All other counties
Project types
Incorporated and unincorporated UGA
Other unincorporated areas
Incorporated and unincorporated areas
Single family residential
30 units
20 units
20 units
Multifamily residential
60 units
25 units
25 units
Barn, loafing shed, farm equipment storage, produce storage or packing structure
40,000 square feet
40,000 square feet
40,000 square feet
Office, school, commercial, recreational, service, storage building, parking facilities
30,000 square feet and 90 parking spaces
12,000 square feet and 40 parking spaces
12,000 square feet and 40 parking spaces
((Landfill)) Fill or excavation
1,000 cubic yards
1,000 cubic yards
1,000 cubic yards
(2)(a) Other minor new construction. The following types of construction shall be exempt except ((where undertaken wholly or in part on lands covered by water (unless specifically exempted in this subsection); the exemptions provided by this section shall apply to all licenses required to undertake the construction in question, except where a rezone or any license governing emissions to the air or discharges to water is required)) when the project:
(((a))) (i) Is undertaken wholly or partly on lands covered by water;
(ii) Requires a license governing discharges to water that is not exempt under RCW 43.21C.0383; or
(iii) Requires a license governing emissions to air that is not exempt under RCW 43.21C.0381 or WAC 197-11-800 (7) or (8);
(iv) Requires a land use decision that is not exempt under WAC 197-11-800(6).
(b) The construction or designation of bus stops, loading zones, shelters, access facilities and pull-out lanes for taxicabs, transit and school vehicles.
(((b))) (c) The construction and/or installation of commercial on-premise signs, and public signs and signals.
(((c))) (d) The construction or installation of minor road and street improvements by any agency or private party that include the following:
(i) Safety structures and equipment: Such as pavement marking, freeway surveillance and control systems, railroad protective devices (not including grade-separated crossings), grooving, glare screen, safety barriers, energy attenuators((,));
(ii) Transportation corridor landscaping (including the application of state of Washington ((state department of agriculture)) approved herbicides by licensed personnel for right of way weed control as long as this is not within watersheds controlled for the purpose of drinking water quality in accordance with WAC 248-54-660)((,));
(iii) Temporary traffic controls and detours((,));
(iv) Correction of substandard curves and intersections within existing rights of way, widening of a highway by less than a single lane width where capacity is not significantly increased and no new right of way is required((,));
(v) Adding auxiliary lanes for localized purposes, (weaving, climbing, speed change, etc.), where capacity is not significantly increased and no new right of way is required((,));
(vi) Channelization and elimination of sight restrictions at intersections, street lighting, guard rails and barricade installation((,));
(vii) Installation of catch basins and culverts((, and)) for the purposes of road and street improvements;
(viii) Reconstruction of existing roadbed (existing curb-to-curb in urban locations), including adding or widening of shoulders((,)) where capacity is not increased and no new right of way is required;
(ix) Addition of bicycle lanes, paths and facilities, and pedestrian walks and paths, but not including additional automobile lanes.
(((d))) (e) Grading, excavating, filling, septic tank installations, and landscaping necessary for any building or facility exempted by subsections (1) and (2) of this section, as well as fencing and the construction of small structures and minor facilities accessory thereto.
(((e))) (f) Additions or modifications to or replacement of any building or facility exempted by subsections (1) and (2) of this section when such addition, modification or replacement will not change the character of the building or facility in a way that would remove it from an exempt class.
(((f))) (g) The demolition of any structure or facility, the construction of which would be exempted by subsections (1) and (2) of this section, except for structures or facilities with recognized historical significance such as listing in a historic register.
(((g))) (h) The installation or removal of impervious underground or above-ground tanks, having a capacity of 10,000 gallons or less except on agricultural and industrial lands. On agricultural and industrial lands, the installation or removal of impervious underground or above-ground tanks, having a total capacity of 60,000 gallons or less.
(((h))) (i) The vacation of streets or roads.
(((i))) (j) The installation of hydrological measuring devices, regardless of whether or not on lands covered by water.
(((j))) (k) The installation of any property, boundary or survey marker, other than fences, regardless of whether or not on lands covered by water.
(l) The installation of accessory solar energy generation equipment on or attached to existing structures and facilities whereby the existing footprint and size of the building is not increased.
(3) Repair, remodeling and maintenance activities. The following activities shall be categorically exempt: The repair, remodeling, maintenance, or minor alteration of existing private or public structures, facilities or equipment, including utilities, recreation, and transportation facilities involving no material expansions or changes in use beyond that previously existing; except that, where undertaken wholly or in part on lands covered by water, only minor repair or replacement of structures may be exempt (examples include repair or replacement of piling, ramps, floats, or mooring buoys, or minor repair, alteration, or maintenance of docks). The following maintenance activities shall not be considered exempt under this subsection:
(a) Dredging of over fifty cubic yards of material;
(b) Reconstruction((/)) or maintenance of groins and similar shoreline protection structures; ((or))
(c) Replacement of utility cables that must be buried under the surface of the bedlands((.)); or
(d) Repair/rebuilding of major dams, dikes, and reservoirs shall also not be considered exempt under this subsection.
(4) Water rights. Appropriations of one cubic foot per second or less of surface water, or of 2,250 gallons per minute or less of groundwater, for any purpose. The exemption covering not only the permit to appropriate water, but also any hydraulics permit, shoreline permit or building permit required for a normal diversion or intake structure, well and pumphouse reasonably necessary to accomplish the exempted appropriation, and including any activities relating to construction of a distribution system solely for any exempted appropriation.
(5) Purchase or sale of real property. The following real property transactions by an agency shall be exempt:
(a) The purchase or acquisition of any right to real property.
(b) The sale, transfer or exchange of any publicly owned real property, but only if the property is not subject to ((an)) a specific designated and authorized public use approved by the public landowner of the property related to the use of land by the public.
(c) ((The lease of real property)) Leasing, granting an easement, or otherwise authorizing when the use of ((the)) real property for the term of the ((lease)) agreement will remain essentially the same as the existing use, or when the use under the lease, easement or other authorization is otherwise exempted by this chapter.
(6) ((Minor)) Land use decisions. The following land use decisions shall be exempt:
(a) Land use decisions for exempt projects, except that rezones must comply with (c) of this subsection.
(b) Other land use decisions not qualified for exemption under subsection (a) (such as a home occupation or change of use) are exempt provided:
(i) The authorized activities will be conducted within an existing building or facility qualifying for exemption under WAC 197-11-800 (1) and (2); and
(ii) The activities will not change the character of the building or facility in a way that would remove it from an exempt class.
(c) Where an exempt project requires a rezone, the rezone is exempt only if:
(i) The project is in an urban growth area in a city or county planning under RCW 36.70A.040;
(ii) The proposed rezone is consistent with and does not require an amendment to the comprehensive plan; and
(iii) The applicable comprehensive plan was previously subjected to environmental review and analysis through an EIS under the requirements of this chapter prior to adoption; and the EIS adequately addressed the environmental impacts of the rezone.
(d) Except upon lands covered by water, the approval of ((short plats or)) short subdivisions pursuant to the procedures required by RCW 58.17.060, ((but not including further)) and short subdivisions ((or short platting within a plat or subdivision previously exempted under this subsection.
(b) Granting of variances based on special circumstances, not including economic hardship, applicable to the subject property, such as size, shape, topography, location or surroundings and not resulting in any change in land use or density.
(c) Classifications of land for current use taxation under chapter 84.34 RCW, and classification and grading of forest land under chapter 84.33 RCW)) within the original short subdivision boundaries provided the cumulative divisions do not exceed the total lots allowed to be created under RCW 58.17.020. This exemption includes binding site plans authorized by RCW 58.17.035 up to the same number of lots allowed by the jurisdiction as a short subdivision.
(e) Granting of variance based on special circumstances, not including economic hardship, applicable to the subject property, such as size, shape, topography, location or surroundings and not resulting in any change in land use or density.
(7) Open burning. Opening burning and the issuance of any license for open burning shall be exempt. The adoption of plans, programs, objectives or regulations by any agency incorporating general standards respecting open burning shall not be exempt.
(8) Clean Air Act. The granting of variances under RCW 70.94.181 extending applicable air pollution control requirements for one year or less shall be exempt.
(9) Water quality certifications. The granting or denial of water quality certifications under the Federal Clean Water Act (Federal Water Pollution Control Act amendments of 1972, 33 U.S.C. 1341) shall be exempt.
(10) Activities of the state legislature. All actions of the state legislature are exempted. ((This subsection does not exempt the proposing of legislation by an agency (WAC 197-11-704).))
(11) Judicial activity. The following shall be exempt:
(a) All adjudicatory actions of the judicial branch.
(b) Any quasi-judicial action of any agency if such action consists of the review of a prior administrative or legislative decision. Decisions resulting from contested cases or other hearing processes conducted prior to the first decision on a proposal or upon any application for a rezone, conditional use permit or other similar permit not otherwise exempted by this chapter, are not exempted by this subsection.
(12) Enforcement and inspections. The following enforcement and inspection activities shall be exempt:
(a) All actions, including administrative orders and penalties, undertaken to enforce a statute, regulation, ordinance, resolution or prior decision. No license shall be considered exempt by virtue of this subsection; nor shall the adoption of any ordinance, regulation or resolution be considered exempt by virtue of this subsection.
(b) All inspections conducted by an agency of either private or public property for any purpose.
(c) All activities of fire departments and law enforcement agencies except physical construction activity.
(d) Any action undertaken by an agency to abate a nuisance or to abate, remove or otherwise cure any hazard to public health or safety. The application of pesticides and chemicals is not exempted by this subsection but may be exempted elsewhere in these guidelines. No license or adoption of any ordinance, regulation or resolution shall be considered exempt by virtue of this subsection.
(e) Any suspension or revocation of a license for any purpose.
(13) Business and other regulatory licenses. The following business and other regulatory licenses are exempt:
(a) All licenses to undertake an occupation, trade or profession.
(b) All licenses required under electrical, fire, plumbing, heating, mechanical, and safety codes and regulations, but not including building permits.
(c) All licenses to operate or engage in amusement devices and rides and entertainment activities((,)) including, but not limited to, cabarets, carnivals, circuses and other traveling shows, dances, music machines, golf courses, and theaters, including approval of the use of public facilities for temporary civic celebrations, but not including licenses or permits required for permanent construction of any of the above.
(d) All licenses to operate or engage in charitable or retail sales and service activities((,)) including, but not limited to, peddlers, solicitors, second hand shops, pawnbrokers, vehicle and housing rental agencies, tobacco sellers, close out and special sales, fireworks, massage parlors, public garages and parking lots, and used automobile dealers.
(e) All licenses for private security services((,)) including, but not limited to, detective agencies, merchant and/or residential patrol agencies, burglar and/or fire alarm dealers, guard dogs, locksmiths, and bail bond services.
(f) All licenses for vehicles for-hire and other vehicle related activities including, but not limited to, taxicabs, ambulances, and tow trucks: Provided, That regulation of common carriers by the utilities and transportation commission shall not be considered exempt under this subsection.
(g) All licenses for food or drink services, sales, and distribution((,)) including, but not limited to, restaurants, liquor, and meat.
(h) All animal control licenses((,)) including, but not limited to, pets, kennels, and pet shops. Establishment or construction of such a facility shall not be considered exempt by this subsection.
(i) The renewal or reissuance of a license regulating any present activity or structure so long as no material changes are involved.
(14) Activities of agencies. The following administrative, fiscal and personnel activities of agencies shall be exempt:
(a) The procurement and distribution of general supplies, equipment and services authorized or necessitated by previously approved functions or programs.
(b) The assessment and collection of taxes.
(c) The adoption of all budgets and agency requests for appropriation: Provided, That if such adoption includes a final agency decision to undertake a major action, that portion of the budget is not exempted by this subsection.
(d) The borrowing of funds, issuance of bonds, or applying for a grant and related financing agreements and approvals.
(e) The review and payment of vouchers and claims.
(f) The establishment and collection of liens and service billings.
(g) All personnel actions, including hiring, terminations, appointments, promotions, allocations of positions, and expansions or reductions in force.
(h) All agency organization, reorganization, internal operational planning or coordination of plans or functions.
(i) Adoptions or approvals of utility, transportation and solid waste disposal rates.
(j) The activities of school districts pursuant to desegregation plans or programs; however, construction of real property transactions or the adoption of any policy, plan or program for such construction of real property transaction shall not be considered exempt under this subsection.
(k) Classification of land for current use taxation under chapter 84.34 RCW, and classification and grading of forest land under chapter 84.33 RCW.
(15) Financial assistance grants. The approval of grants or loans by one agency to another shall be exempt, although an agency may at its option require compliance with SEPA prior to making a grant or loan for design or construction of a project. This exemption includes agencies taking nonproject actions that are necessary to apply for federal or other financial assistance.
(16) Local improvement districts and special purpose districts. The formation of local improvement districts and special purpose districts, unless such formation constitutes a final agency decision to undertake construction of a structure or facility not exempted under WAC 197-11-800 and 197-11-880. A special district or special purpose district is a local government entity designated by the Revised Code of Washington (RCW) and is not a city, town, township, or county.
(17) Information collection and research. Basic data collection, research, resource evaluation, requests for proposals (RFPs), and the conceptual planning of proposals shall be exempt. These may be strictly for information-gathering, or as part of a study leading to a proposal that has not yet been approved, adopted or funded; this exemption does not include any agency action that commits the agency to proceed with such a proposal. (Also see WAC 197-11-070.)
(18) Acceptance of filings. The acceptance by an agency of any document or thing required or authorized by law to be filed with the agency and for which the agency has no discretionary power to refuse acceptance shall be exempt. No license shall be considered exempt by virtue of this subsection.
(19) Procedural actions. The proposal, amendment or adoption of legislation, rules, regulations, resolutions or ordinances, or of any plan or program shall be exempt if they are:
(a) Relating solely to governmental procedures, and containing no substantive standards respecting use or modification of the environment shall be exempt.
(b) Text amendments resulting in no substantive changes respecting use or modification of the environment.
(c) Agency SEPA procedures ((shall be exempt)).
(20) ((Building codes. The adoption by ordinance of all codes as required by the state Building Code Act (chapter 19.27 RCW).)) Reserved.
(21) Adoption of noise ordinances. The adoption by counties/cities of resolutions, ordinances, rules or regulations concerned with the control of noise which do not differ from regulations adopted by the department of ecology under chapter 70.107 RCW. When a county/city proposes a noise resolution, ordinance, rule or regulation, a portion of which differs from the applicable state regulations (((and thus requires approval of the department of ecology under RCW 70.107.060(4)))), SEPA compliance may be limited to those items which differ from state regulations.
(22) Review and comment actions. Any activity where one agency reviews or comments upon the actions of another agency or another department within an agency shall be exempt.
(23) Utilities. The utility-related actions listed below shall be exempt, except for installation, construction, or alteration on lands covered by water. The exemption includes installation and construction, relocation when required by other governmental bodies, repair, replacement, maintenance, operation or alteration that does not change the action from an exempt class.
(a) All communications lines, including cable TV, but not including communication towers or relay stations.
(b) All storm water, water and sewer facilities, lines, equipment, hookups or appurtenances including, utilizing or related to lines ((eight)) twelve inches or less in diameter.
(c) All electric facilities, lines, equipment or appurtenances, not including substations, with an associated voltage of 55,000 volts or less; the overbuilding of existing distribution lines (55,000 volts or less) with transmission lines (up to and including 115,000 volts); within existing rights of way or developed utility corridors, all electric facilities, lines, equipment or appurtenances, not including substations, with an associated voltage of 115,000 volts or less; and the undergrounding of all electric facilities, lines, equipment or appurtenances.
(d) All natural gas distribution (as opposed to transmission) lines and necessary appurtenant facilities and hookups.
(e) All developments within the confines of any existing electric substation, reservoir, pump station vault, pipe, or well: ((Provided, That)) Additional appropriations of water are not exempted by this subsection.
(f) Periodic use of chemical or mechanical means to maintain a utility or transportation right of way in its design condition: Provided, ((That)) the chemicals used are approved by ((the)) Washington state ((department of agriculture)) and applied by licensed personnel. This exemption shall not apply to the use of chemicals within watersheds that are controlled for the purpose of drinking water quality in accordance with WAC 248-54-660.
(g) All grants of rights of way by agencies to utilities for use for distribution (as opposed to transmission) purposes.
(h) All grants of franchises by agencies to utilities.
(i) All disposals of rights of way by utilities.
(24) Natural resources management. In addition to the other exemptions contained in this section, the following natural resources management activities shall be exempt:
(a) Issuance of new grazing leases covering a section of land or less; and issuance of all grazing leases for land that has been subject to a grazing lease within the previous ten years.
(b) Licenses or approvals to remove firewood.
(c) Issuance of agricultural leases covering one hundred sixty contiguous acres or less.
(d) Issuance of leases for Christmas tree harvesting or brush picking.
(e) Issuance of leases for school sites.
(f) Issuance of leases for, and placement of, mooring buoys designed to serve pleasure craft.
(g) Development of recreational sites not specifically designed for all-terrain vehicles and not including more than twelve campsites.
(h) Periodic use of chemical or mechanical means to maintain public park and recreational land: Provided, That chemicals used are approved by the Washington state department of agriculture and applied by licensed personnel. This exemption shall not apply to the use of chemicals within watersheds that are controlled for the purpose of drinking water quality in accordance with WAC 248-54-660.
(i) Issuance of rights of way, easements and use permits to use existing roads in nonresidential areas.
(j) Establishment of natural area preserves to be used for scientific research and education and for the protection of rare flora and fauna, under the procedures of chapter 79.70 RCW.
(25) ((Personal)) Wireless service facilities.
(a) The siting of ((personal)) wireless service facilities are exempt if ((the facility)):
(i) ((Is a microcell and is to be attached to an existing structure that is not a residence or school and does not contain a residence or a school;
(ii) Includes personal wireless service antennas, other than a microcell, and is to be attached to an existing structure (that may be an existing tower) that is not a residence or school and does not contain a residence or school, and the existing structure to which it is to be attached is located in a commercial, industrial, manufacturing, forest, or agriculture zone; or
(iii))) The collocation of new equipment, removal of equipment, or replacement of existing equipment on existing or replacement structures that does not substantially change the physical dimensions of such structures; or
(ii) The siting project involves constructing a ((personal)) wireless service tower less than sixty feet in height that is located in a commercial, industrial, manufacturing, forest, or agricultural zone.
(b) For the purposes of this subsection:
(i) "((Personal)) Wireless services" means wireless data and telecommunications services, including commercial mobile services, commercial mobile data services, unlicensed wireless services, and common carrier wireless exchange access services, as defined by federal laws and regulations.
(ii) "((Personal)) Wireless service facilities" means facilities for the provision of ((personal)) wireless services.
(iii) (("Microcell" means a wireless communication facility consisting of an antenna that is either:
(A) Four feet in height and with an area of not more than five hundred eighty square inches; or
(B) If a tubular antenna, no more than four inches in diameter and no more than six feet in length)) "Collocation" means the mounting or installation of equipment on an existing tower, building, structure for the purposes of either transmitting or receiving, or both, radio frequency signals for communication purposes.
(iv) "Existing structure" means any existing tower, pole, building, or other structure capable of supporting wireless service facilities.
(v) "Substantially change the physical dimensions" means:
(A) The mounting of equipment on a structure that would increase the height of the structure by more than ten percent, or twenty feet, whichever is greater; or
(B) The mounting of equipment that would involve adding an appurtenance to the body of the structure that would protrude from the edge of the structure more than twenty feet, or more than the width of the structure at the level of the appurtenance, whichever it greater.
(c) This exemption does not apply to projects within a critical area designated under GMA (RCW 36.70A.060).
AMENDATORY SECTION (Amending WSR 03-16-067, filed 8/1/03, effective 9/1/03)
WAC 197-11-820 Department of licensing.
All licenses ((required under programs administered by the department of licensing as of December 12, 1975)) issued by the department of licensing are exempted, except the following:
(1) Camping club promotional permits under chapter 19.105 RCW.
(2) Motor vehicle wrecker licenses under chapter 46.80 RCW; WAC 197-11-800 (13)(i) shall apply to allow possible exemption of renewals of camping club promotional permits and motor vehicle wrecker licenses.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-825 Department of labor and industries.
All licenses ((required under programs administered by the department of labor and industries as of December 12, 1975)) issued by the department of labor and industries are exempted, except the issuance of any license for the manufacture of explosives or the adoption or amendment by the department of any regulations incorporating general standards respecting the issuance of licenses authorizing the storage of explosives under chapter 70.74 RCW. The adoption of any industrial health or safety regulations containing noise standards shall be considered a major action under this chapter.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-830 Department of natural resources.
The following actions and licenses of the department of natural resources are exempted:
(1) Forest closures, shutdowns and permit suspensions due to extreme unusual fire hazards.
(2) Operating permits to use power equipment on forest land.
(3) Permits to use fuse on forest land.
(4) Log patrol licenses.
(5) Permits for drilling for which no public hearing is required under RCW 79.76.070 (geothermal test drilling).
(6) Permits for the dumping of forest debris and wood waste in forested areas.
(7) Those sales of timber from public lands that the department of natural resources determines, by rules adopted pursuant to RCW 43.21C.120 do not have potential for a substantial impact on the environment.
(8) Except on aquatic lands under state control, leases for mineral prospecting under RCW 79.01.616 or 79.01.652, but not including issuance of subsequent contracts for mining.
(9) Sales of rock from public lands involving rock pits less than three acres in size that are used for activities regulated under a forest practices application that is exempt under RCW 43.21C.037 and sales of rock from public lands for uses not associated with timber management that do not exceed the total volume threshold for excavation exempted under WAC 197-11-800 (1)(v).
AMENDATORY SECTION (Amending WSR 03-16-067, filed 8/1/03, effective 9/1/03)
WAC 197-11-835 Department of ((fisheries)) fish and wildlife.
The following activities of the department of ((fisheries)) fish and wildlife are exempted:
(1) The establishment of seasons, catch limits or geographical areas for fishing or shellfish removal.
(2) All hydraulic project approvals (RCW 75.20.100) for activities incidental to a Class I, II, III forest practice as defined in RCW 76.09.050 or regulations thereunder.
(3) Hydraulic project approvals where there is no other agency with jurisdiction (besides the department of ((game)) fish and wildlife) requiring a nonexempt permit, except for proposals involving removal of fifty or more cubic yards of streambed materials or involving realignment into a new channel. For purposes of this paragraph, the term new channel shall not include existing channels which have been naturally abandoned within the twelve months previous to the hydraulic permit application.
(4) All clam farm licenses and oyster farm licenses, except where cultural practices include structures occupying the water column or where a hatchery or other physical facility is proposed for construction on adjoining uplands.
(5) All other licenses (other than those excepted in (2) and (3) above) authorized to be issued by the department as of December 12, 1975 except the following:
(a) Fish farming license, or other licenses allowing the cultivation of aquatic animals for commercial purposes;
(b) Licenses for the mechanical and/or hydraulic removal of clams, including geoducks; and((,))
(c) Any license authorizing the discharge of explosives in water. WAC 197-11-800 (13)(i) shall apply to allow possible exemption of renewals of the above licenses.
(6) The routine release of hatchery fish or the reintroduction of endemic or native species into their historical habitat where only minor documented effects on other species will occur.
(7) The establishment of hunting, trapping or fishing seasons, bag or catch limits, and geographical areas where such activities are permitted.
(8) The issuance of falconry permits.
(9) The issuance of all hunting or fishing licenses, permits, or tags.
(10) Artificial wildlife feeding.
(11) The issuance of scientific collector permits.
(12) Minor repair work to be done by hand tools. Examples include:
(a) Maintenance of fish screen or intake structures; or
(b) Silt and debris removal from boat launches, docks, and piers.
(13) Collection of fish and wildlife for research.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-845 Department of social and health services and department of health.
All department of social and health services and department of health actions ((under programs administered by the department of social and health services as of December 12, 1975,)) are exempted, except the following:
(1) The adoption or amendment by the department of any regulations incorporating general standards for issuance of licenses authorizing the possession, use and transfer of radioactive source material under RCW 70.98.080, except that the issuance, revocation or suspension of individual licenses thereto shall be exempt. However, licenses to operate low level burial facilities or licenses to operate or expand beyond design capacity, mineral processing facilities or their tailings areas whose products or byproducts have concentrations of naturally occurring radioactive materials in excess of exempt concentrations, as specified in WAC 402-20-250, shall not be exempt.
(2) The approval of a comprehensive plan for public water supply systems servicing one thousand or more units under WAC 248-54-065.
(3) The approval of engineering reports or plans and specifications under WAC 248-54-085 and 248-54-095, for all surface water source development, all water system storage facilities greater than one-half million gallons, new transmission lines longer than one thousand feet located in new rights of way and major extensions to existing water distribution systems.
(4) The approval of an application for a certificate of need under RCW 70.38.120 for construction of a new hospital or medical facility or for major additions to existing service capacity of such institutions.
(5) The approval of an application for any system of sewerage and/or water general plan or amendments under RCW 36.94.100.
(6) The approval of any plans and specifications for new sewage treatment works or major extensions to existing sewer treatment works submitted to the department under WAC 248-92-040.
(7) The construction of any building, facility or other installation not exempt by WAC 197-11-800 for the purpose of housing department personnel, or fulfilling statutorily directed or authorized functions (((e.g.)) for example, prisons).
(8) The approval of any final plans for construction of a nursing home pursuant to WAC 248-14-100, construction of a private psychiatric hospital pursuant to WAC 248-22-005 or construction of an alcoholism treatment center pursuant to WAC 248-22-510.
AMENDATORY SECTION (Amending WSR 03-16-067, filed 8/1/03, effective 9/1/03)
WAC 197-11-850 Department of agriculture.
All department of agriculture actions ((under programs administered by the department of agriculture as of December 12, 1975)) are exempted, except for the following:
(1) The approval of any application for a commercial registered feedlot, quarantined registered feedlot under chapter 16.36 RCW, or chapters 16-28 and 16-30 WAC.
(2) The issuance or amendment of any regulation respecting restricted-use pesticides under chapter 15.58 RCW that would have the effect of allowing the use of a pesticide previously prohibited by Washington state.
(3) The removal of any pesticide from the list of restricted-use pesticides established in WAC 16-228-155 so as to permit sale of such pesticides to home and garden users, unless the pesticide is no longer manufactured and is not available.
(4) The removal of any pesticide from the list of highly toxic and restricted-use pesticides established under WAC 16-228-165 so as to authorize sale of such pesticides to persons not holding an annual user permit, an applicator certificate, or an applicator operator license, unless the pesticide is no longer manufactured and is not available.
(5) The removal of any pesticide from the category of highly toxic pesticide formulations established in WAC 16-228-165 so as to permit the sale of such pesticides by persons not possessing a pesticide dealer's license, unless the pesticide is no longer manufactured and is not available.
(6) The approval of any use of the pesticide DDT or DDD except for those uses approved by the centers for disease control of the United States Department of Health and Human Services (such as control of rabid bats).
(7) The issuance of a license to operate a public livestock market under RCW 16.65.030.
(8) The provisions of WAC 197-11-800 (13)(i) shall apply to allow possible exemption of renewals of the licenses in (1) through (7) above.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-860 Department of transportation.
The following activities of the department of transportation shall be exempt:
(1) Approval of the annual highway safety work program involving the highway-related safety standards pursuant to 23 U.S.C. 402;
(2) Issuance of road approach permits and right of way rental agreements;
(3) Establishment and changing of speed limits of 55 miles per hour or less;
(4) Revisions of existing access control involving a single property owner;
(5) Issuance of a "motorist information signing permit," granting a private business person the privilege of having a sign on highway right of way which informs the public of the availability of his or her services;
(6) Issuance of permits for special units relative to state highways;
(7) Issuance of permits for the movement of over-legal size and weight vehicles on state highways;
(8) Issuance of encroachment permits for road approaches, fences and landfills on highway right of way; ((and))
(9) Issuance of permits for utility occupancy of highway rights of way for use for distribution (as opposed to transmission)((.)); and
(10) The repair, reconstruction, restoration, retrofitting, or replacement of any road, highway, bridge, tunnel, or transit facility (such as a ferry dock or bus transfer station), including ancillary transportation facilities (such as pedestrian/bicycle paths and bike lanes), that is in operation, as long as the action:
(a) Occurs within the existing right-of-way and in a manner that substantially conforms to the preexisting design, function, and location as the original except to meet current engineering standards or environmental permit requirements; and
(b) The action does not result in addition of automobile lanes, a change in capacity, or a change in functional use of the facility.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-865 Utilities and transportation commission.
All utilities and transportation commission actions ((of the utilities and transportation commission under statutes administered as of December 12, 1975,)) are exempted, except the following:
(1) Issuance of common carrier motor freight authority under chapter 81.80 RCW that would authorize a new service, or extend an existing transportation service in the fields of petroleum and petroleum products in bulk in tank type vehicles, radioactive substances, explosives, or corrosives;
(2) Authorization of the openings or closing of any highway/railroad grade crossing, or the direction of physical connection of the line of one railroad with that of another;
(3) Regulation of oil and gas pipelines under chapter 81.88 RCW; and
(4) The approval of utility and transportation rates where the funds realized as a result of such approved rates will or are intended to finance construction of a project, approval of which would not be otherwise exempt under WAC 197-11-800, and where at the time of such rate approval no responsible official of any state or federal agency has conducted the environmental analysis prescribed by this chapter or the appropriate provisions of NEPA, whichever is applicable.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-870 Department of commerce ((and economic development)).
The following activities of the department of commerce ((and economic development)) shall be exempt:
(1) The provisions of business consulting and advisory services that include tourist promotion under RCW 43.31.050.
(2) The promotion and development of foreign trade under RCW 43.31.370.
(3) The furnishing of technical and information services under RCW 43.31.060.
(4) The provision of technical assistance to applicants for loans and aid and/or grants by the community of economic revitalization board under chapter 43.160 RCW.
(5) The conduct of research and economic analysis under RCW 43.31.070, including the provision of consulting and advisory services and recommendations to state and local officials, agencies and governmental bodies as authorized under RCW 43.31.160, 43.31.200 and 43.31.210.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-875 Other agencies.
Except for building construction (the majority of which is undertaken through the department of ((general administration)) enterprise services), all activities of the following state agencies ((under programs they administer as of December 12, 1975,)) are exempted:
(1) Office of the attorney general.
(2) Office of the auditor.
(3) Department of employment security.
(4) Office of the insurance commissioner ((and state fire marshal)).
(5) Department of ((personnel)) enterprise services.
(6) ((Department of printing.)) Office of financial management.
(7) Department of revenue.
(8) Office of the secretary of state.
(9) Office of the treasurer.
(10) Arts commission.
(11) Washington state patrol.
(12) ((Interagency committee for outdoor recreation.)) Recreation and conservation office.
(13) ((Department of emergency services.)) Emergency management division.
(14) Department of ((general administration, division of banking and division of savings and loan associations.
(15) Forest practices appeals board)) financial institutions.
(((16))) (15) Public employees' retirement system.
(((17))) (16) Law enforcement officers' and firefighters' retirement board.
(((18))) (17) Board for volunteer ((fireman's retirement system board)) firefighters and reserve officers.
(((19))) (18) State department of retirement systems.
(((20) Teachers' retirement system board.
(21) Higher education personnel board.
(22) Commission for vocational education.
(23) State energy office.))
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-920 Agencies with environmental expertise.
The following agencies shall be regarded as possessing special expertise relating to those categories of the environment under which they are listed:
(1) Air quality.
(a) Department of ecology.
(b) Department of natural resources (only for burning in forest areas).
(c) Department of ((social and)) health ((services)).
(d) Regional air pollution control authority or agency.
(2) Water resources and water quality.
(a) Department of ((game)) fish and wildlife.
(b) Department of ecology.
(c) Department of natural resources (state-owned tidelands, shorelands, harbor areas or beds of navigable waters).
(d) Department of ((social and)) health ((services)) (public water supplies, sewer systems, shellfish habitats).
(((e) Department of fisheries.))
(3) Hazardous and toxic substances (including radiation).
(a) Department of ecology.
(b) Department of ((social and)) health ((services)).
(c) Department of agriculture (foods or pesticides).
(d) Department of ((fisheries)) fish and wildlife (introduction into waters).
(((e) Department of game (introduction into waters).))
(4) Solid and hazardous waste.
(a) Department of ecology.
(b) Department of ((fisheries)) fish and wildlife (dredge spoils).
(c) Department of ((social and)) health ((services)).
(((d) Department of game (dredge spoils).))
(5) Fish and wildlife.
(a) Department of game.
(b) Department of fisheries.
(6) Natural resources development.
(a) ((Department of commerce and economic development.
(b))) Department of ecology.
(((c))) (b) Department of natural resources.
(((d))) (c) Department of ((fisheries)) fish and wildlife.
(((e) Department of game.))
(7) Energy production, transmission and consumption.
(a) Department of ecology.
(b) Department of natural resources (geothermal, coal, uranium).
(c) ((State energy office.)) Department of commerce.
(d) Energy facility site evaluation council.
(e) Utilities and transportation commission.
(8) Land use and management.
(a) Department of commerce ((and economic development)).
(b) Department of ecology.
(c) Department of ((fisheries)) fish and wildlife (affecting surface or marine waters).
(d) Department of natural resources (tidelands, shorelands, or state-owned or managed lands).
(((e) Planning and community affairs agency.
(f) Department of game.))
(9) Noise.
(a) Department of ecology.
(b) Department of ((social and)) health ((services)).
(10) Recreation.
(a) Department of commerce ((and economic development)).
(b) Department of ((game)) fish and wildlife.
(c) ((Department of fisheries.
(d))) Parks and recreation commission.
(((e))) (d) Department of natural resources.
(11) Archaeological/historical.
(((a) Office)) Department of archaeology and historic preservation.
(((b) Washington State University at Pullman (Washington archaeological research center).))
(12) Transportation.
(a) Department of transportation.
(b) Utilities and transportation commission.
AMENDATORY SECTION (Amending WSR 84-05-020, filed 2/10/84, effective 4/4/84)
WAC 197-11-936 Lead agency for private projects requiring licenses from more than one state agency.
(1) For private projects which require licenses from more than one state agency, but require no license from a county/city, the lead agency shall be one of the state agencies requiring a license, based upon the following order of priority:
(a) Department of ecology.
(b) Department of ((social and)) health ((services)).
(c) Department of natural resources.
(d) Department of ((fisheries)) fish and wildlife.
(e) ((Department of game.
(f))) Utilities and transportation commission.
(((g))) (f) Department of ((motor vehicles)) licensing.
(((h))) (g) Department of labor and industries.
(2) When none of the state agencies requiring a license is on the above list, the lead agency shall be the licensing agency that has the largest biennial appropriation.
(3) When, under subsection (1), an agency would be the lead agency solely because of its involvement in a program jointly administered with another agency, the other agency shall be designated the lead agency for proposals for which it is primarily responsible under agreements previously made between the two agencies for joint operation of the program.
AMENDATORY SECTION (Amending WSR 97-21-030, filed 10/10/97, effective 11/10/97)
WAC 197-11-938 Lead agencies for specific proposals.
Notwithstanding the lead agency designation criteria contained in WAC 197-11-926 through 197-11-936, the lead agency for proposals within the areas listed below shall be as follows:
(1) For all governmental actions relating to energy facilities for which certification is required under chapter 80.50 RCW, the lead agency shall be the energy facility site evaluation council (EFSEC); however, for any public project requiring such certification and for which the study under RCW 80.50.175 will not be made, the lead agency shall be the agency initiating the project.
(2) For all private projects relating to the use of geothermal resources under chapter 79.76 RCW, the lead agency shall be the department of natural resources.
(3) For all private projects requiring a license or other approval from the oil and gas conservation committee under chapter 78.52 RCW, the lead agency shall be the department of natural resources; however, for projects under RCW 78.52.125, the EIS shall be prepared in accordance with that section.
(4) For private activity requiring a license or approval under the Forest Practices Act of 1974, chapter 76.09 RCW, the lead agency shall be either the department of natural resources or the city/county where the project is located, as set forth below:
(a) The interagency agreements authorized by WAC 222-50-030 between the department of natural resources and other governmental agencies may be used to identify SEPA lead agency status for forest practice applications. If used, this agreement shall meet the requirements for a lead agency agreement in WAC 197-11-942.
(b) If no interagency agreement exists, the SEPA lead agency determination shall be based on information in the environmental checklist required as part of the forest practice application requiring SEPA review. The applicant shall, as part of the checklist, submit all information on future plans for conversion, and shall identify any known future license requirements.
(c) For any proposal involving forest practices (i) ((on lands platted after January 1, 1960, (ii))) on lands beings converted to another use, or (((iii))) (ii) on lands which, pursuant to RCW 76.09.070 as now or hereafter amended, are not to be reforested because of the likelihood of future conversion to urban development, the applicable county or city is the lead agency if the county or city will require a license for the proposal. Upon receipt of a forest practice application and environmental checklist, natural resources shall determine lead agency for the proposal. If insufficient information is available to identify necessary permits, natural resources shall ask the applicant for additional information. If a permit is not required from the city/county, natural resources shall be lead agency. If a city/county permit is required, natural resources shall send copies of the environmental checklist and forest practice application together with the determination of the lead agency to the city/county.
(d) Upon receipt and review of the environmental checklist and forest practice application, the city/county shall within ten business days:
(i) Agree that a city/county license is required, either now or at a future point, and proceed with environmental review as lead agency.
(ii) Determine that a license is not required from the city/county, and notify natural resources that the city/county is not lead agency; or
(iii) Determine there is insufficient information in the environmental checklist to identify the need for a license, and either:
(A) Assume lead agency status and conduct appropriate environmental analysis for the total proposal;
(B) Request additional information from the applicant; or
(C) Notify natural resources of the specific additional information needed to determine permit requirements, who shall request the information from the applicant.
(5) For all private projects requiring a license or lease to use or affect state lands, the lead agency shall be the state agency managing the lands in question; however, this subsection shall not apply to the sale or lease of state-owned tidelands, harbor areas or beds of navigable waters, when such sale or lease is incidental to a larger project for which one or more licenses from other state or local agencies is required.
(6) For a pulp or paper mill or oil refinery not under the jurisdiction of EFSEC, the lead agency shall be the department of ecology, when a National Pollutant Discharge Elimination System (NPDES) permit is required under section 402 of the Federal Water Pollution Control Act (33 U.S.C. 1342).
(7) For proposals to construct a pipeline greater than six inches in diameter and fifty miles in length, used for the transportation of crude petroleum or petroleum fuels or oil or derivatives thereof, or for the transportation of synthetic or natural gas under pressure not under the jurisdiction of EFSEC, the lead agency shall be the department of ecology.
(8) For proposals that will result in an impoundment of water with a water surface in excess of forty acres, the lead agency shall be the department of ecology.
(9) For proposals to construct facilities on a single site designed for, or capable of, storing a total of one million or more gallons of any liquid fuel not under the jurisdiction of EFSEC, the lead agency shall be the department of ecology.
(10) For proposals to construct any new oil refinery, or an expansion of an existing refinery that shall increase capacity by ten thousand barrels per day or more not under the jurisdiction of EFSEC, the lead agency shall be the department of ecology.
(11) For proposed metal mining and milling operations regulated by chapter 78.56 RCW, except for uranium and thorium operations regulated under Title 70 RCW, the lead agency shall be the department of ecology.
(12) For proposals to construct, operate, or expand any uranium or thorium mill, any tailings areas generated by uranium or thorium milling or any low-level radioactive waste burial facilities, the lead agency shall be the department of social and health services.
AMENDATORY SECTION (Amending WSR 13-02-065, filed 12/28/12, effective 1/28/13)
WAC 197-11-960 Environmental checklist.
ENVIRONMENTAL CHECKLIST
Purpose of checklist:
The State Environmental Policy Act (SEPA), chapter 43.21C RCW, requires all governmental agencies to consider the environmental impacts of a proposal before making decisions. An environmental impact statement (EIS) must be prepared for all proposals with probable significant adverse impacts on the quality of the environment. The purpose of this checklist is to provide information to help you and the agency identify impacts from your proposal (and to reduce or avoid impacts from the proposal, if it can be done) and to help the agency decide whether an EIS is required.
Instructions for applicants:
This environmental checklist asks you to describe some basic information about your proposal. Governmental agencies use this checklist to determine whether the environmental impacts of your proposal are significant, requiring preparation of an EIS. Answer the questions briefly, with the most precise information known, or give the best description you can.
You must answer each question accurately and carefully, to the best of your knowledge. In most cases, you should be able to answer the questions from your own observations or project plans without the need to hire experts. If you really do not know the answer, or if a question does not apply to your proposal, write "do not know" or "does not apply." Complete answers to the questions now may avoid unnecessary delays later.
Some questions ask about governmental regulations, such as zoning, shoreline, and landmark designations. Answer these questions if you can. If you have problems, the governmental agencies can assist you.
The checklist questions apply to all parts of your proposal, even if you plan to do them over a period of time or on different parcels of land. Attach any additional information that will help describe your proposal or its environmental effects. The agency to which you submit this checklist may ask you to explain your answers or provide additional information reasonably related to determining if there may be significant adverse impact.
Use of checklist for nonproject proposals:
For nonproject proposals complete this checklist and the supplemental sheet for nonproject actions (Part D). The lead agency may exclude any question for the environmental elements (Part B) which they determine do not contribute meaningfully to the analysis of the proposal.
For nonproject actions, the references in the checklist to the words "project," "applicant," and "property or site" should be read as "proposal," "proposer," and "affected geographic area," respectively.
A. BACKGROUND
1. Name of proposed project, if applicable:
2. Name of applicant:
3. Address and phone number of applicant and contact person:
4. Date checklist prepared:
5. Agency requesting checklist:
6. Proposed timing or schedule (including phasing, if applicable):
7. Do you have any plans for future additions, expansion, or further activity related to or connected with this proposal? If yes, explain.
8. List any environmental information you know about that has been prepared, or will be prepared, directly related to this proposal.
9. Do you know whether applications are pending for governmental approvals of other proposals directly affecting the property covered by your proposal? If yes, explain.
10. List any government approvals or permits that will be needed for your proposal, if known.
11. Give brief, complete description of your proposal, including the proposed uses and the size of the project and site. There are several questions later in this checklist that ask you to describe certain aspects of your proposal. You do not need to repeat those answers on this page. (Lead agencies may modify this form to include additional specific information on project description.)
12. Location of the proposal. Give sufficient information for a person to understand the precise location of your proposed project, including a street address, if any, and section, township, and range, if known. If a proposal would occur over a range of area, provide the range or boundaries of the site(s). Provide a legal description, site plan, vicinity map, and topographic map, if reasonably available. While you should submit any plans required by the agency, you are not required to duplicate maps or detailed plans submitted with any permit applications related to this checklist.
((TO BE COMPLETED BY APPLICANT
EVALUATION FOR
AGENCY USE
ONLY
B. ENVIRONMENTAL ELEMENTS
1. Earth
a.
General description of the site (circle one): Flat, rolling, hilly, steep slopes, mountainous, other......
b.
What is the steepest slope on the site (approximate percent slope)?
c.
What general types of soils are found on the site (for example, clay, sand, gravel, peat, muck)? If you know the classification of agricultural soils, specify them and note any prime farmland.
d.
Are there surface indications or history of unstable soils in the immediate vicinity? If so, describe.
e.
Describe the purpose, type, and approximate quantities of any filling or grading proposed. Indicate source of fill.
f.
Could erosion occur as a result of clearing, construction, or use? If so, generally describe.
g.
About what percent of the site will be covered with impervious surfaces after project construction (for example, asphalt or buildings)?
h.
Proposed measures to reduce or control erosion, or other impacts to the earth, if any:
2. Air
a.
What types of emissions to the air would result from the proposal (i.e., dust, automobile, odors, industrial wood smoke) during construction and when the project is completed? If any, generally describe and give approximate quantities if known.
b.
Are there any offsite sources of emissions or odor that may affect your proposal? If so, generally describe.
c.
Proposed measures to reduce or control emissions or other impacts to air, if any:
3. Water
a.
Surface:
 
1) Is there any surface water body on or in the immediate vicinity of the site (including year-round and seasonal streams, saltwater, lakes, ponds, wetlands)? If yes, describe type and provide names. If appropriate, state what stream or river it flows into.
 
2) Will the project require any work over, in, or adjacent to (within 200 feet) the described waters? If yes, please describe and attach available plans.
 
3) Estimate the amount of fill and dredge material that would be placed in or removed from surface water or wetlands and indicate the area of the site that would be affected. Indicate the source of fill material.
 
4) Will the proposal require surface water withdrawals or diversions? Give general description, purpose, and approximate quantities if known.
 
5) Does the proposal lie within a 100-year flood plain? If so, note location on the site plan.
 
6) Does the proposal involve any discharges of waste materials to surface waters? If so, describe the type of waste and anticipated volume of discharge.
b.
Ground:
 
1) Will groundwater be withdrawn, or will water be discharged to groundwater? Give general description, purpose, and approximate quantities if known.
 
2) Describe waste material that will be discharged into the ground from septic tanks or other sources, if any (for example: Domestic sewage; industrial, containing the following chemicals...; agricultural; etc.). Describe the general size of the system, the number of such systems, the number of houses to be served (if applicable), or the number of animals or humans the system(s) are expected to serve.
c.
Water runoff (including storm water):
 
1) Describe the source of runoff (including storm water) and method of collection and disposal, if any (include quantities, if known). Where will this water flow? Will this water flow into other waters? If so, describe.
 
2) Could waste materials enter ground or surface waters? If so, generally describe.
d.
Proposed measures to reduce or control surface, ground, and runoff water impacts, if any:
4. Plants
a.
Check or circle types of vegetation found on the site:
 
Deciduous tree: Alder, maple, aspen, other
 
Evergreen tree: Fir, cedar, pine, other
 
Shrubs
 
Grass
 
Pasture
 
Crop or grain
 
Wet soil plants: Cattail, buttercup, bullrush, skunk cabbage, other
 
Water plants: Water lily, eelgrass, milfoil, other
 
Other types of vegetation
b.
What kind and amount of vegetation will be removed or altered?
c.
List threatened or endangered species known to be on or near the site.
d.
Proposed landscaping, use of native plants, or other measures to preserve or enhance vegetation on the site, if any:
5. Animals
a.
Circle any birds and animals which have been observed on or near the site or are known to be on or near the site:
 
 
Birds: Hawk, heron, eagle, songbirds,
other: . . . .
 
 
Mammals: Deer, bear, elk, beaver,
other: . . . .
 
 
Fish: Bass, salmon, trout, herring, shellfish,
other: . . . .
b.
List any threatened or endangered species known to be on or near the site.
c.
Is the site part of a migration route? If so, explain.
d.
Proposed measures to preserve or enhance wildlife, if any:
6. Energy and natural resources
a.
What kinds of energy (electric, natural gas, oil, wood stove, solar) will be used to meet the completed project's energy needs? Describe whether it will be used for heating, manufacturing, etc.
b.
Would your project affect the potential use of solar energy by adjacent properties? If so, generally describe.
c.
What kinds of energy conservation features are included in the plans of this proposal? List other proposed measures to reduce or control energy impacts, if any:
7. Environmental health
a.
Are there any environmental health hazards, including exposure to toxic chemicals, risk of fire and explosion, spill, or hazardous waste, that could occur as a result of this proposal? If so, describe.
 
1) Describe special emergency services that might be required.
 
2) Proposed measures to reduce or control environmental health hazards, if any:
b.
Noise
 
1) What types of noise exist in the area which may affect your project (for example: traffic, equipment, operation, other)?
 
2) What types and levels of noise would be created by or associated with the project on a short-term or a long-term basis (for example: traffic, construction, operation, other)? Indicate what hours noise would come from the site.
 
3) Proposed measures to reduce or control noise impacts, if any:
8. Land and shoreline use
a.
What is the current use of the site and adjacent properties?
b.
Has the site been used for agriculture? If so, describe.
c.
Describe any structures on the site.
d.
Will any structures be demolished? If so, what?
e.
What is the current zoning classification of the site?
f.
What is the current comprehensive plan designation of the site?
g.
If applicable, what is the current shoreline master program designation of the site?
h.
Has any part of the site been classified as an "environmentally sensitive" area? If so, specify.
i.
Approximately how many people would reside or work in the completed project?
j.
Approximately how many people would the completed project?
k.
Proposed measures to avoid or reduce displacement impacts, if any:
l.
Proposed measures to ensure the proposal is compatible with existing and projected land uses and plans, if any:
9. Housing
a.
Approximately how many units would be provided, if any? Indicate whether high, middle, or low-income housing.
b.
Approximately how many units, if any, would be eliminated? Indicate whether high, middle, or low-income housing.
c.
Proposed measures to reduce or control housing impacts, if any:
10. Aesthetics
a.
What is the tallest height of any proposed structure(s), not including antennas; what is the principal exterior building material(s) proposed?
b.
What views in the immediate vicinity would be altered or obstructed?
c.
Proposed measures to reduce or control aesthetic impacts, if any:
11. Light and glare
a.
What type of light or glare will the proposal produce? What time of day would it mainly occur?
b.
Could light or glare from the finished project be a safety hazard or interfere with views?
c.
What existing offsite sources of light or glare may affect your proposal?
d.
Proposed measures to reduce or control light and glare impacts, if any:
12. Recreation
a.
What designated and informal recreational opportunities are in the immediate vicinity?
b.
Would the proposed project displace any existing recreational uses? If so, describe.
c.
Proposed measures to reduce or control impacts on recreation, including recreation opportunities to be provided by the project or applicant, if any:
13. Historic and cultural preservation
a.
Are there any places or objects listed on, or proposed for, national, state, or local preservation registers known to be on or next to the site? If so, generally describe.
b.
Generally describe any landmarks or evidence of historic, archaeological, scientific, or cultural importance known to be on or next to the site.
c.
Proposed measures to reduce or control impacts, if any:
14. Transportation
a.
Identify public streets and highways serving the site, and describe proposed access to the existing street system. Show on site plans, if any.
b.
Is site currently served by public transit? If not, what is the approximate distance to the nearest transit stop?
c.
How many parking spaces would the completed project have? How many would the project eliminate?
d.
Will the proposal require any new roads or streets, or improvements to existing roads or streets, not including driveways? If so, generally describe (indicate whether public or private).
e.
Will the project use (or occur in the immediate vicinity of) water, rail, or air transportation? If so, generally describe.
f.
How many vehicular trips per day would be generated by the completed project? If known, indicate when peak volumes would occur.
g.
Proposed measures to reduce or control transportation impacts, if any:
15. Public services
a.
Would the project result in an increased need for public services (for example: Fire protection, police protection, health care, schools, other)? If so, generally describe.
b.
Proposed measures to reduce or control direct impacts on public services, if any.
16. Utilities
a.
Circle utilities currently available at the site: Electricity, natural gas, water, refuse service, telephone, sanitary sewer, septic system, other.
b.
Describe the utilities that are proposed for the project, the utility providing the service, and the general construction activities on the site or in the immediate vicinity which might be needed.
C.
SIGNATURE
The above answers are true and complete to the best of my knowledge. I understand that the lead agency is relying on them to make its decision.
 
 
Signature:
. . . . 
 
 
Date Submitted:
. . . . 
D.
SUPPLEMENTAL SHEET FOR NONPROJECT ACTIONS
 
(do not use this sheet for project actions)
 
Because these questions are very general, it may be helpful to read them in conjunction with the list of the elements of the environment.
 
When answering these questions, be aware of the extent the proposal, or the types of activities likely to result from the proposal, would affect the item at a greater intensity or at a faster rate than if the proposal were not implemented. Respond briefly and in general terms.
1.
How would the proposal be likely to increase discharge to water; emissions to air; production, storage, or release of toxic or hazardous substances; or production of noise?
 
Proposed measures to avoid or reduce such increases are:
2.
How would the proposal be likely to affect plants, animals, fish, or marine life?
 
Proposed measures to protect or conserve plants, animals, fish, or marine life are:
3.
How would the proposal be likely to deplete energy or natural resources?
 
Proposed measures to protect or conserve energy and natural resources are:
4.
How would the proposal be likely to use or affect environmentally sensitive areas or areas designated (or eligible or under study) for governmental protection; such as parks, wilderness, wild and scenic rivers, threatened or endangered species habitat, historic or cultural sites, wetlands, flood plains, or prime farmlands?
 
Proposed measures to protect such resources or to avoid or reduce impacts are:
5.
How would the proposal be likely to affect land and shoreline use, including whether it would allow or encourage land or shoreline uses incompatible with existing plans?
 
Proposed measures to avoid or reduce shoreline and land use impacts are:
6.
How would the proposal be likely to increase demands on transportation or public services and utilities?
 
Proposed measures to reduce or respond to such demand(s) are:
7.
Identify, if possible, whether the proposal may conflict with local, state, or federal laws or requirements for the protection of the environment.))
B. ENVIRONMENTAL ELEMENTS
1. Earth
a. General description of the site (circle one): Flat, rolling, hilly, steep slopes, mountainous, other......
b. What is the steepest slope on the site (approximate percent slope)?
c. What general types of soils are found on the site (for example, clay, sand, gravel, peat, muck)? If you know the classification of agricultural soils, specify them and note any agricultural land of long-term commercial significance and whether the proposal results in removing any of these soils.
d. Are there surface indications or history of unstable soils in the immediate vicinity? If so, describe.
e. Describe the purpose, type, total area, and approximate quantities of any filling or grading proposed. Indicate source of fill.
f. Could erosion occur as a result of clearing, construction, or use? If so, generally describe.
g. About what percent of the site will be covered with impervious surfaces after project construction (for example, asphalt or buildings)?
h. Proposed measures to reduce or control erosion, or other impacts to the earth, if any:
2. Air
a. What types of emissions to the air would result from the proposal during construction, operation, and maintenance when the project is completed? If any, generally describe and give approximate quantities if known.
b. Are there any offsite sources of emissions or odor that may affect your proposal? If so, generally describe.
c. Proposed measures to reduce or control emissions or other impacts to air, if any:
3. Water
a. Surface:
1) Is there any surface water body on or in the immediate vicinity of the site (including year-round and seasonal streams, saltwater, lakes, ponds, wetlands)? If yes, describe type and provide names. If appropriate, state what stream or river it flows into.
2) Will the project require any work over, in, or adjacent to (within 200 feet) the described waters? If yes, please describe and attach available plans.
3) Estimate the amount of fill and dredge material that would be placed in or removed from surface water or wetlands and indicate the area of the site that would be affected. Indicate the source of fill material.
4) Will the proposal require surface water withdrawals or diversions? Give general description, purpose, and approximate quantities if known.
5) Does the proposal lie within a 100-year flood plain? If so, note location on the site plan.
6) Does the proposal involve any discharges of waste materials to surface waters? If so, describe the type of waste and anticipated volume of discharge.
b. Ground:
1) Will groundwater be withdrawn from a well for drinking water or other purposes? If so, give a general description of the well, proposed uses and approximate quantities withdrawn from the well? Will water be discharged to groundwater? Give general description, purpose, and approximate quantities if known.
2) Describe waste material that will be discharged into the ground from septic tanks or other sources, if any (for example: Domestic sewage; industrial, containing the following chemicals...; agricultural; etc.). Describe the general size of the system, the number of such systems, the number of houses to be served (if applicable), or the number of animals or humans the system(s) are expected to serve.
c. Water runoff (including storm water):
1) Describe the source of runoff (including storm water) and method of collection and disposal, if any (include quantities, if known). Where will this water flow? Will this water flow into other waters? If so, describe.
2) Could waste materials enter ground or surface waters? If so, generally describe.
3) Does the proposal alter or otherwise affect drainage patterns in the vicinity of the site? If so, describe.
d. Proposed measures to reduce or control surface, ground, runoff water, and drainage pattern impacts, if any:
4. Plants
a. Check the types of vegetation found on the site:
— Deciduous tree: Alder, maple, aspen, other
— Evergreen tree: Fir, cedar, pine, other
— Shrubs
— Grass
— Pasture
— Crop or grain
— Orchards, vineyards or other permanent crops.
— Wet soil plants: Cattail, buttercup, bullrush, skunk cabbage, other
— Water plants: Water lily, eelgrass, milfoil, other
— Other types of vegetation
b. What kind and amount of vegetation will be removed or altered?
c. List threatened or endangered species known to be on or near the site.
d. Proposed landscaping, use of native plants, or other measures to preserve or enhance vegetation on the site, if any:
e. List all noxious weeds and invasive species known to be on or near the site.
5. Animals
a. List any birds and other animals which have been observed on or near the site or are known to be on or near the site. Examples include:
Birds: Hawk, heron, eagle, songbirds, other:
Mammals: Deer, bear, elk, beaver, other:
Fish: Bass, salmon, trout, herring, shellfish, other:
b. List any threatened or endangered species known to be on or near the site.
c. Is the site part of a migration route? If so, explain.
d. Proposed measures to preserve or enhance wildlife, if any:
e. List any invasive animal species known to be on or near the site.
6. Energy and natural resources
a. What kinds of energy (electric, natural gas, oil, wood stove, solar) will be used to meet the completed project's energy needs? Describe whether it will be used for heating, manufacturing, etc.
b. Would your project affect the potential use of solar energy by adjacent properties? If so, generally describe.
c. What kinds of energy conservation features are included in the plans of this proposal? List other proposed measures to reduce or control energy impacts, if any:
7. Environmental health
a. Are there any environmental health hazards, including exposure to toxic chemicals, risk of fire and explosion, spill, or hazardous waste, that could occur as a result of this proposal? If so, describe.
1) Describe any known or possible contamination at the site from present or past uses.
2) Describe existing hazardous chemicals/conditions that might affect project development and design. This includes underground hazardous liquid and gas transmission pipelines located within the project area and in the vicinity.
3) Describe any toxic or hazardous chemicals that might be stored, used, or produced during the project's development or construction, or at any time during the operating life of the project.
4) Describe special emergency services that might be required.
5) Proposed measures to reduce or control environmental health hazards, if any:
b. Noise
1) What types of noise exist in the area which may affect your project (for example: traffic, equipment, operation, other)?
2) What types and levels of noise would be created by or associated with the project on a short-term or a long-term basis (for example: traffic, construction, operation, other)? Indicate what hours noise would come from the site.
3) Proposed measures to reduce or control noise impacts, if any:
8. Land and shoreline use
a. What is the current use of the site and adjacent properties? Will the proposal affect current land uses on nearby or adjacent properties? If so, describe.
b. Has the project site been used as working farmlands or working forest lands? If so, describe. How much agricultural or forest land of long-term commercial significance will be converted to other uses as a result of the proposal, if any? If resource lands have not been designated, how many acres in farmland or forest land tax status will be converted to nonfarm or nonforest use?
1) Will the proposal affect or be affected by surrounding working farm or forest land normal business operations, such as oversize equipment access, the application of pesticides, tilling, and harvesting? If so, how:
c. Describe any structures on the site.
d. Will any structures be demolished? If so, what?
e. What is the current zoning classification of the site?
f. What is the current comprehensive plan designation of the site?
g. If applicable, what is the current shoreline master program designation of the site?
h. Has any part of the site been classified critical area by the city or county? If so, specify.
i. Approximately how many people would reside or work in the completed project?
j. Approximately how many people would the completed project displace?
k. Proposed measures to avoid or reduce displacement impacts, if any:
l. Proposed measures to ensure the proposal is compatible with existing and projected land uses and plans, if any:
m. Proposed measures to ensure the proposal is compatible with nearby agricultural and forest lands of long-term commercial significance, if any:
9. Housing
a. Approximately how many units would be provided, if any? Indicate whether high, middle, or low-income housing.
b. Approximately how many units, if any, would be eliminated? Indicate whether high, middle, or low-income housing.
c. Proposed measures to reduce or control housing impacts, if any:
10. Aesthetics
a. What is the tallest height of any proposed structure(s), not including antennas; what is the principal exterior building material(s) proposed?
b. What views in the immediate vicinity would be altered or obstructed?
c. Proposed measures to reduce or control aesthetic impacts, if any:
11. Light and glare
a. What type of light or glare will the proposal produce? What time of day would it mainly occur?
b. Could light or glare from the finished project be a safety hazard or interfere with views?
c. What existing offsite sources of light or glare may affect your proposal?
d. Proposed measures to reduce or control light and glare impacts, if any:
12. Recreation
a. What designated and informal recreational opportunities are in the immediate vicinity?
b. Would the proposed project displace any existing recreational uses? If so, describe.
c. Proposed measures to reduce or control impacts on recreation, including recreation opportunities to be provided by the project or applicant, if any:
13. Historic and cultural preservation
a. Are there any buildings or structures over 45 years old listed in or eligible for listing in national, state, or local preservation registers located on or near the site? If so, specifically describe.
b. Are there any landmarks, features, or other evidence of Indian or historic use or occupation. This may include human burials or old cemeteries. Is there any material evidence, artifacts, or areas of cultural importance on or near the site? Please list any professional studies conducted at the site to identify such resources.
c. Describe the methods used to assess the potential impacts to cultural resources on or near the project site. Examples include consultation with tribes and the department of archeology and historic preservation, archaeological surveys, historic maps, GIS data, etc.
d. Proposed measures to avoid, minimize, or compensate for disturbance to resources. Please include plans for the above and any permits that may be required.
14. Transportation
a. Identify public streets and highways serving the site or affected geographic area, and describe proposed access to the existing street system. Show on site plans, if any.
b. Is site currently or affected geographic area served by public transit? If so, generally describe. If not, what is the approximate distance to the nearest transit stop?
c. How many additional parking spaces would the completed project or nonproject proposal have? How many would the project or proposal eliminate?
d. Will the proposal require any new or improvements to existing roads, streets, pedestrian, bicycle or state transportation facilities, not including driveways? If so, generally describe (indicate whether public or private).
e. Will the project or proposal use (or occur in the immediate vicinity of) water, rail, or air transportation? If so, generally describe.
f. How many vehicular trips per day would be generated by the completed project or proposal? If known, indicate when peak volumes would occur and what percentage of the volume would be trucks. What data or transportation models were used to make these estimates?
g. Will the proposal interfere, affect or be affected by the movement of agricultural and forest products on roads or streets in the area? If so, generally describe.
h. Proposed measures to reduce or control transportation impacts, if any:
15. Public services
a. Would the project result in an increased need for public services (for example: Fire protection, police protection, public transit health care, schools, other)? If so, generally describe.
b. Proposed measures to reduce or control direct impacts on public services, if any.
16. Utilities
a. Circle utilities currently available at the site: Electricity, natural gas, water, refuse service, telephone, sanitary sewer, septic system, other.
b. Describe the utilities that are proposed for the project, the utility providing the service, and the general construction activities on the site or in the immediate vicinity which might be needed.
C. SIGNATURE
The above answers are true and complete to the best of my knowledge. I understand that the lead agency is relying on them to make its decision.
Signature: . . . . . . . . . . . .
Date Submitted: . . . . . . . . . .
D. SUPPLEMENTAL SHEET FOR NONPROJECT ACTIONS
(do not use this sheet for project actions)
Because these questions are very general, it may be helpful to read them in conjunction with the list of the elements of the environment.
When answering these questions, be aware of the extent the proposal, or the types of activities likely to result from the proposal, would affect the item at a greater intensity or at a faster rate than if the proposal were not implemented. Respond briefly and in general terms.
1. How would the proposal be likely to increase discharge to water; emissions to air; production, storage, or release of toxic or hazardous substances; or production of noise?
Proposed measures to avoid or reduce such increases are:
2. How would the proposal be likely to affect plants, animals, fish, or marine life?
Proposed measures to protect or conserve plants, animals, fish, or marine life are:
3. How would the proposal be likely to deplete energy or natural resources?
Proposed measures to protect or conserve energy and natural resources are:
4. How would the proposal be likely to use or affect environmentally sensitive areas or areas designated (or eligible or under study) for governmental protection; such as parks, wilderness, wild and scenic rivers, threatened or endangered species habitat, historic or cultural sites, wetlands, flood plains, or prime farmlands?
Proposed measures to protect such resources or to avoid or reduce impacts are:
5. How would the proposal be likely to affect land and shoreline use, including whether it would allow or encourage land or shoreline uses incompatible with existing plans?
Proposed measures to avoid or reduce shoreline and land use impacts are:
6. How would the proposal be likely to increase demands on transportation or public services and utilities?
Proposed measures to reduce or respond to such demand(s) are:
7. Identify, if possible, whether the proposal may conflict with local, state, or federal laws or requirements for the protection of the environment.
REPEALER
The following section of the Washington Administrative Code is repealed:
WAC 197-11-840
Department of game.
REPEALER
The following chapter of the Washington Administrative Code is repealed:
WAC 173-806-010
Authority.
WAC 173-806-020
Purpose of this part and adoption by reference.
WAC 173-806-030
Additional definitions.
WAC 173-806-040
Designation of responsible official.
WAC 173-806-050
Lead agency determination and responsibilities.
WAC 173-806-053
Transfer of lead agency status to a state agency.
WAC 173-806-058
Additional timing considerations.
WAC 173-806-065
Purpose of this part and adoption by reference.
WAC 173-806-070
Flexible thresholds for categorical exemptions.
WAC 173-806-080
Use of exemptions.
WAC 173-806-090
Environmental checklist.
WAC 173-806-100
Mitigated DNS.
WAC 173-806-110
Purpose of this part and adoption by reference.
WAC 173-806-120
Preparation of EIS—Additional considerations.
WAC 173-806-125
Additional elements to be covered in an EIS.
WAC 173-806-128
Adoption by reference.
WAC 173-806-130
Public notice.
WAC 173-806-132
Public notice.
WAC 173-806-140
Designation of official to perform consulted agency responsibilities for the city/county.
WAC 173-806-150
Purpose of this part and adoption by reference.
WAC 173-806-155
Purpose of this part and adoption by reference.
WAC 173-806-160
Substantive authority.
WAC 173-806-170
Appeals.
WAC 173-806-173
Notice/statute of limitations.
WAC 173-806-175
Purpose of this part and adoption by reference.
WAC 173-806-180
Adoption by reference.
WAC 173-806-185
Purpose of this part and adoption by reference.
WAC 173-806-190
Critical areas.
WAC 173-806-200
Fees.
WAC 173-806-205
Effective date.
WAC 173-806-220
Severability.
WAC 173-806-230
Adoption by reference.
REPEALER
The following chapter of the Washington Administrative Code is repealed:
WAC 197-06-010
Purpose.
WAC 197-06-020
Definitions.
WAC 197-06-030
Public records available.
WAC 197-06-040
Membership, officers, quorum, administrative offices, function.
WAC 197-06-050
Meetings.
WAC 197-06-060
Public records officer.
WAC 197-06-070
Office hours.
WAC 197-06-080
Requests for public records.
WAC 197-06-090
Copying.
WAC 197-06-100
Exemptions.
WAC 197-06-110
Review of denials of public records requests.
WAC 197-06-120
Protection of public records.
WAC 197-06-130
Records index.
WAC 197-06-140
Communications.
WAC 197-06-150
Adoption of form.
WAC 197-06-990
Form—Council on environmental policy—Request for public records.