WSR 14-06-041 PERMANENT RULES DEPARTMENT OF LABOR AND INDUSTRIES [Filed February 26, 2014, 8:46 a.m., effective April 1, 2014] Effective Date of Rule: April 1, 2014.
Purpose: The purpose of this rule making is to increase the elevator fees by 13.1 percent. Labor and industries was given the authority by 3ESSB 5034, which passed the legislature in 2013, to increase the elevator fees by 13.1 percent. The elevator program's budget and projected revenue were evaluated and the fee increase is necessary to support the program's expenditures which includes the addition of six new full-time employees (five inspectors and one technical specialist) as requested by the department.
Citation of Existing Rules Affected by this Order: Amending WAC 296-96-00922 What are the fees associated with licensing?, 296-96-01005 When do I need and what are the steps in obtaining a permit?, 296-96-01010 What are the installation permit fees for conveyances, material lifts, and hoists and how are they calculated?, 296-96-01012 What are the permit fees for alterations to conveyances, material lifts, and hoists and how are they calculated?, 296-96-01025, What is the permit fee for personnel and material hoists?, 296-96-01027, Are initial installation permit fees refundable?, 296-96-01030, What is the process for installation and alteration plan approval?, 296-96-01035, Are there inspection fees?, 296-96-01040, What is the fee for testing and inspecting regular elevators used as temporary elevators to provide transportation for construction personnel, tools, and materials only?, 296-96-01045, What are the inspection requirements and fees for conveyances in private residences?, 296-96-01050, How do I get a supplemental inspection?, 296-96-01055, Are technical services available and what is the fee?, 296-96-01057, Does the department charge a fee to perform investigations and what is the fee?, 296-96-01060, Can I request an after hours inspection and what is the fee?, and 296-96-01065, What are the annual operating certificate fees?
Statutory Authority for Adoption: Chapter 70.87 RCW and chapter 4, Laws of 2013 (3ESSB 5034).
Adopted under notice filed as WSR 14-01-089 on December 17, 2013.
A final cost-benefit analysis is available by contacting Alicia Curry, P.O. Box 44400, Olympia, WA 98504-4400, phone (360) 902-6244, fax (360) 902-5292, e-mail Alicia.Curry@Lni.wa.gov.
Number of Sections Adopted in Order to Comply with Federal Statute: New 0, Amended 0, Repealed 0; Federal Rules or Standards: New 0, Amended 0, Repealed 0; or Recently Enacted State Statutes: New 0, Amended 0, Repealed 0.
Number of Sections Adopted at Request of a Nongovernmental Entity: New 0, Amended 0, Repealed 0.
Number of Sections Adopted on the Agency's Own Initiative: New 0, Amended 15, Repealed 0.
Number of Sections Adopted in Order to Clarify, Streamline, or Reform Agency Procedures: New 0, Amended 0, Repealed 0.
Number of Sections Adopted Using Negotiated Rule Making: New 0, Amended 0, Repealed 0; Pilot Rule Making: New 0, Amended 0, Repealed 0; or Other Alternative Rule Making: New 0, Amended 15, Repealed 0.
Date Adopted: February 26, 2014.
Joel Sacks
Director
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-00922 What are the fees associated with licensing?
The following are the department's elevator license fees:
AMENDATORY SECTION (Amending WSR 07-24-041, filed 11/30/07, effective 1/1/08)
WAC 296-96-01005 When do I need and what are the steps in obtaining a permit?
(1) See WAC 296-96-01000 for the permit process.
(2) Construction and alteration permits are valid for one year from the date of issue. However, permits may be renewed if you:
(a) Apply for a renewal permit before your current permit expires;
(b) The department approves your request for a renewal permit; and
(c) You pay a $((51.60)) 58.30 renewal fee to the department for each permit you renew;
(3) If your permit has expired you must reapply for a new permit.
(4) See WAC 296-96-01006 for work requiring a permit.
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01010 What are the installation permit fees for conveyances, material lifts, and hoists and how are they calculated?
Installation permit fees are based on the total cost of the conveyance and the labor to install the conveyance. The following permit fees apply to the construction or relocation of all conveyances and material lifts:
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01012 What are the permit fees for alterations to conveyances, material lifts, and hoists and how are they calculated?
Permit fees are based on the total cost of the equipment, materials and labor to perform the alteration. The following permit fees apply to the alteration of all conveyances and material lifts:
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01025 What is the permit fee for personnel and material hoists?
The fee for each personnel hoist or material hoist installation is. . . .$((228.40)) 258.30
See WAC 296-96-01035(2) for requirements for jumps.
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01027 Are initial installation permit fees refundable?
Your initial installation permit fees are refundable if the installation work has not been performed, minus a processing fee, unless your permits have expired. No refunds will be issued for expired permits. All requests for refunds must be submitted in writing to the elevator section and must identify the specific permits and the reasons for which the refunds are requested.
The processing fee for each refund is. . . .$((34.10)) 38.50
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01030 What is the process for installation and alteration plan approval?
Prior to the start of construction, the applicant must submit to the department for approval two copies of plans for new installations or major alterations. To be approved, the plan must comply with the latest adopted edition of the American Society of Mechanical Engineers (ASME), the National Electrical Code (NEC) and applicable Washington Administrative Codes (WAC). In addition, the plans must include all information necessary in determining whether each installation/alteration complies with all applicable codes. The permit holder must keep a copy of the approved plan on the job site until the department has witnessed all acceptance tests. Any alterations to the approved plan must be submitted to the department for approval before a final inspection will be conducted. The nonrefundable fees for reviewing your plans are:
For each installation/major alteration. . . .$((28.30)) 32.00
If more than two sets of plans are submitted, the fee for each additional set. . . .$((11.20)) 12.60
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01035 Are there inspection fees?
Yes. The initial inspection(s) of a conveyance or for the initial inspection of construction, alteration or relocation of a conveyance is included with your permit fee. Once the department has approved the initial installation of the conveyance you will be issued a temporary operating certificate that is valid for 30 days. Prior to the expiration of the 30-day temporary operating certificate the application for an annual operating certificate and the appropriate fees must be paid to the department. Once the department has received the appropriate fees and application the owner will be issued the first annual operating certificate. The owner or owners' representative will receive an invoice from the department for renewal. The owner is required to renew the annual operating certificate yearly.
The following inspections require an additional inspection fee:
(1) Reinspection. If a conveyance does not pass an initial inspection and an additional inspection is required, the fee for each reinspection of a conveyance is $((114.10)) 129.00 per conveyance plus $((55.40)) 62.60 per hour for each hour in addition to the first hour.
The department may waive reinspection fees.
(2) Inspecting increases in the height (jumping) of personnel and material hoists.
The fee for inspecting an increase in the height (jumping) of each personnel hoist or material hoist is $((114.10)) 129.00 plus $((56.90)) 64.30 per hour for each hour in addition to 2 hours. This fee is for inspections occurring during regular working hours.
The permit holder may be allowed to operate a hoist prior to the jump inspection if:
(a) The electrical limits will not allow the lift to operate above the previously inspected landing.
(b) The state elevator inspector is contacted, agrees and can schedule within 3 days.
(3) Variance inspections.
(a) The fee for an on-site variance inspection is $((171.20)) 193.60 per conveyance plus $((56.90)) 64.30 per hour for each hour in addition to 2 hours. This fee is for inspections occurring during regular working hours.
(b) The fee for a variance that does not require an on-site inspection is $((56.90)) 64.30 per conveyance. The individual requesting the variance must provide the department with pictures, documentation, or other information necessary for the department to review the variance. The department may conduct an on-site variance inspection to verify the information provided or if it determines that an inspection is necessary. If an on-site variance inspection is performed, the fees in (a) of this subsection will apply.
(4) "Red tag" status fee. The annual fee for a conveyance in "Red tag" status is $((28.30)) 32.00.
(5) Decommission inspection. The fee for performing a decommission inspection is $((56.90)) 64.30. Once the decommission inspection has been performed and approved, the conveyance will no longer require annual inspections until such time that the conveyance is brought back into service. Prior to operating the conveyance, a new inspection and annual operating permit must be obtained.
(6) Voluntary inspections by request. The owner or potential purchaser of a building within the department's jurisdiction may request a voluntary inspection of a conveyance. The fee for this inspection will be $((114.10)) 129.00 per conveyance and $((56.90)) 64.30 per hour for each hour in addition to 2 hours plus the standard per diem and mileage allowance granted to department inspectors. The owner/potential purchaser requesting the voluntary inspection will not be subject to any penalties based on the inspector's findings.
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01040 What is the fee for testing and inspecting regular elevators used as temporary elevators to provide transportation for construction personnel, tools, and materials only?
(1) The fee for the inspecting and testing of regular elevators used as temporary elevators is $((91.20)) 103.10, in addition to any other fees required in this chapter. This fee purchases a 30-day temporary use permit that may be renewed at the department's discretion.
(2) When this temporary use permit is purchased, a notice declaring that the equipment has not received final approval from the department must be conspicuously posted in the elevator.
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01045 What are the inspection requirements and fees for conveyances in private residences?
(1) Chapter 70.87 RCW requires the department to inspect all new, altered or relocated conveyances operated exclusively for single-family use in private residences. Prior to installation, a licensed elevator contractor must complete a permit application as described in WAC 296-96-01005 and pay the appropriate fee listed in WAC 296-96-01010.
(2) Chapter 70.87 RCW allows the department to inspect conveyances operated exclusively for single-family use in private residences when the department is investigating an accident or an alleged or apparent violation of the statute or these rules.
(3) No annual inspection and operating certificate is required for a private residence conveyance operated exclusively for single-family use unless the owner requests it. When an owner requests an inspection and an annual operating certificate, the following fee must be paid prior to an inspection:
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01050 How do I get a supplemental inspection?
Any person, firm, corporation or governmental agency can request a supplemental inspection from the department by paying a fee of $((68.40)) 77.30 per hour (including travel time) plus the standard per diem and mileage allowance granted to department inspectors. This fee is for inspections occurring during regular working hours.
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01055 Are technical services available and what is the fee?
You may request elevator field technical services from the department by paying a fee of $((68.40)) 77.30 per hour (including travel time) plus the standard per diem and mileage allowance granted to department inspectors. These field technical services may include code evaluation, code consultation, plan examination, code interpretation and clarification of technical data relating to the application of the department's conveyance rules. Field technical services do not include inspections.
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01057 Does the department charge a fee to perform investigations and what is the fee?
An elevator inspector may charge at a rate of $((68.40)) 77.30 per hour (including travel time) plus the standard per diem and mileage allowance granted to department inspectors. These services shall include accident investigation relating to any and all accidents. This fee would include an inspection as required during the accident investigation.
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01060 Can I request an after-hours inspection and what is the fee?
You may request an inspection outside of normal business hours, which are 7:00 a.m. to 5:00 p.m., if an inspector is available and the inspection is authorized by the department. The minimum fee for an after-hours inspection is $((85.40)) 96.50 and $((85.40)) 96.50 per hour for each hour in addition to the first hour plus the standard per diem and mileage allowance granted to department inspectors. This fee is in addition to any other fees required for your project.
AMENDATORY SECTION (Amending WSR 12-06-065, filed 3/6/12, effective 4/30/12)
WAC 296-96-01065 What are the annual operating certificate fees?
An annual operating certificate will be issued to you upon payment of the appropriate fee. The owner of record will be invoiced by the department. If a change of owner has occurred, it is the new owner's responsibility to ensure the department has the corrected information. Below is the fee structure table:
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||