H-1298.1 _______________________________________________
HOUSE BILL 1590
_______________________________________________
State of Washington 54th Legislature 1995 Regular Session
By Representatives Mielke, Crouse and Huff
Read first time 01/31/95. Referred to Committee on Energy & Utilities.
AN ACT Relating to energy financing voter approval; amending RCW 80.52.030, 80.52.040, 80.52.050, and 80.52.060; creating a new section; and decodifying RCW 80.52.020.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
NEW SECTION. Sec. 1. Many government-owned electrical utilities, including those operated by first class cities and public utility districts, have traditionally relied upon a federal marketing agency as their primary, if not exclusive, source of electrical energy. Recent changes affecting the operation of federally owned hydroelectric projects for the protection of anadromous fish, and the prospect that additional constraints might be placed upon the management of such federal facilities, have diminished the stability of the cost of power supplied by such federal marketing agency. In response to the concern engendered by the increasing cost of electricity generated at federally owned hydroelectric projects, many government-owned electrical utilities have either begun to seek, or are currently pursuing, the acquisition of their own electrical energy generation plants or facilities. Some of these acquisitions may entail the involvement of other parties. Default on bonds issued to finance the WPPSS nuclear plants demonstrates that the faith and credit of the political subdivisions of the state should not be extended unadvisedly. Therefore, the legislature finds and declares that government-owned electrical utilities must receive the authorization of their electors for the issuance of any bonds required to finance the acquisition or development of electrical energy generation plants or facilities when the ownership of such plants or facilities will be undivided between the government-owned utility and another party or parties.
Sec. 2. RCW 80.52.030 and 1981 2nd ex.s. c 6 s 3 are each amended to read as follows:
The definitions set forth in this section apply throughout this chapter unless the context clearly requires otherwise.
(1) "Public agency" means a public utility district, joint operating agency, city, county, or any other state governmental agency, entity, or political subdivision.
(2) "Major public energy project" means a plant or installation capable, or intended to be capable, of generating electricity in an amount greater than two hundred fifty megawatts. Where two or more such plants are located within the same geographic site, each plant shall be considered a major public energy project. An addition to an existing facility is not deemed to be a major energy project unless the addition itself is capable, or intended to be capable, of generating electricity in an amount greater than two hundred fifty megawatts. A project which is under construction on July 1, 1982, shall not be considered a major public energy project unless the official agency budget or estimate for total construction costs for the project as of July 1, 1982, is more than two hundred percent of the first official estimate of total construction costs as specified in the senate energy and utilities committee WPPSS inquiry report, volume one, January 12, 1981, and unless, as of July 1, 1982, the projected remaining cost of construction for that project exceeds two hundred million dollars.
(3) "Public energy project" means a plant or installation capable, or intended to be capable, of generating electricity including a major public energy project.
(4) "Cost
of construction" means the total cost of planning and building a ((major))
public energy project and placing it into operation, including, but not limited
to, planning cost, direct construction cost, licensing cost, cost of fuel inventory
for the first year's operation, interest, and all other costs incurred prior to
the first day of full operation, whether or not incurred prior to July 1, 1982.
(((4))) (5)
"Cost of acquisition" means the total cost of acquiring a ((major))
public energy project from another party, including, but not limited to,
principal and interest costs.
(((5))) (6)
"Bond" means a revenue bond, a general obligation bond, or any other
indebtedness issued by a public agency or its assignee.
(((6))) (7)
"Applicant" means a public agency, or the assignee of a public
agency, requesting the secretary of state to conduct an election pursuant to
this chapter.
(((7))) (8)
"Cost-effective" means that a project or resource is forecast:
(a) To be reliable and available within the time it is needed; and
(b) To meet or reduce the electric power demand of the intended consumers at an estimated incremental system cost no greater than that of the least-cost similarly reliable and available alternative project or resource, or any combination thereof.
(((8))) (9)
"System cost" means an estimate of all direct costs of a project or
resource over its effective life, including, if applicable, the costs of
distribution to the consumer, and, among other factors, waste disposal costs, end-of-cycle
costs, and fuel costs (including projected increases), and such quantifiable
environmental costs and benefits as are directly attributable to the project or
resource.
Sec. 3. RCW 80.52.040 and 1981 2nd ex.s. c 6 s 4 are each amended to read as follows:
No public agency or assignee of a public agency may issue or sell bonds to finance the cost of construction or the cost of acquisition of (1) A major public energy project, or any portion thereof; or (2) a public energy project to be acquired or developed pursuant to RCW 54.44.020, unless it has first obtained authority for the expenditure of the funds to be raised by the sale of such bonds for that project at an election conducted in the manner provided in this chapter.
Sec. 4. RCW 80.52.050 and 1982 c 88 s 1 are each amended to read as follows:
The election required under RCW 80.52.040 shall be conducted in the manner provided in this section.
(1)(a) If the applicant is a public utility district, joint operating agency, city, or county, the election shall be among the voters of the public utility district, city, or county, or among the voters of the local governmental entities comprising the membership of the joint operating agency.
(b) If the applicant is any public agency other than those described in subsection (1)(a) of this section, or is an assignee of a joint operating agency and not itself a joint operating agency, the election shall be conducted state-wide in the manner provided in Title 29 RCW for state-wide elections.
(2) The election shall be held at the next state-wide general election occurring more than ninety days after submission of a request by an applicant to the secretary of state unless a special election is requested by the applicant as provided in this section.
(3) If no state-wide election can be held under subsection (2) of this section within one hundred twenty days of the submission to the secretary of state of a request by an applicant for financing authority under this chapter, the applicant may request that a special election be held if such election is necessary to avoid significant delay in construction or acquisition of the energy project. Within ten days of receipt of such a request for a special election, the secretary of state shall designate a date for the election pursuant to RCW 29.13.010 and certify the date to the county auditor of each county in which an election is to be held under this section.
(4) Prior to an
election under this section, the applicant shall submit to the secretary of
state a cost-effectiveness study, prepared by an independent consultant
approved by the state finance committee, pertaining to the ((major))
public energy project under consideration. The study shall be available for
public review and comment for thirty days. At the end of the thirty-day
period, the applicant shall prepare a final draft of the study which includes
the public comment, if any.
(5) The secretary of state shall certify the ballot issue for the election to be held under this section to the county auditor of each county in which an election is to be held. The certification shall include the statement of the proposition as provided in RCW 80.52.060. The costs of the election shall be relieved by the applicant in the manner provided by RCW 29.13.045. In addition, the applicant shall reimburse the secretary of state for the applicant's share of the costs related to the preparation and distribution of the voters' pamphlet required by subsection (6) of this section and such other costs as are attributable to any election held pursuant to this section.
(6) Prior to an
election under this section, the secretary of state shall provide an
opportunity for supporters and opponents of the requested financing authority
to present their respective views in a voters' pamphlet which shall be
distributed to the voters of the local governmental entities participating in
the election. Upon submission of an applicant's request for an election
pursuant to this section, the applicant shall provide the secretary of state
with the following information regarding each ((major)) public energy
project for which the applicant seeks financing authority at such election,
which information shall be included in the voters' pamphlet:
(a) The name, location,
and type of ((major)) public energy project, expressed in common terms;
(b) The dollar amount and type of bonds being requested;
(c) If the bond issuance is intended to finance the acquisition of all or a portion of the project, the anticipated total cost of the acquisition of the project;
(d) If the bond issuance is intended to finance the planning or construction of all or a portion of the project, the anticipated total cost of construction of the project;
(e) The projected average rate increase for consumers of the electricity to be generated by the project. The rate increase shall be that which will be necessary to repay the total indebtedness incurred for the project, including estimated interest;
(f) A summary of the final cost-effectiveness study conducted under subsection (4) of this section;
(g) The anticipated functional life of the project;
(h) The anticipated decommissioning costs of the project; and
(i) If a special election is requested by the applicant, the reasons for requesting a special election.
Sec. 5. RCW 80.52.060 and 1981 2nd ex.s. c 6 s 6 are each amended to read as follows:
The proposition for
each ((major)) public energy project listed upon a ballot pursuant to
this chapter shall be in the form provided in this section.
(1) If the funds are intended to finance the planning or construction of all or a portion of the project, the proposition shall read substantially as follows:
"Shall (name of applicant) be authorized to spend (dollar amount of financing authority requested) to construct the (name of the project) (type of project) located at (location) , the anticipated total construction cost of which is (anticipated cost of construction) ?"
(2) If the financing authority is intended to finance the acquisition of all or a portion of the project from another party, the proposition shall read substantially as follows:
"Shall (name of applicant) be authorized to spend (dollar amount of financing authority requested) to acquire the (name of project) (type of project) located at (location) , the anticipated total acquisition cost of which is (anticipated cost of acquisition) ?"
NEW SECTION. Sec. 6. RCW 80.52.020 is decodified.
--- END ---