S-0892.1  _______________________________________________

 

                         SENATE BILL 5533

          _______________________________________________

 

State of Washington      55th Legislature     1997 Regular Session

 

By Senators Haugen and Jacobsen

 

Read first time 01/30/97.  Referred to Committee on Government Operations.

Readjusting certain public contract bid amounts for inflation.


    AN ACT Relating to revising certain competitive bid dollar amounts to account for inflation; and amending RCW 35.22.620 and 35.23.352.

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:

 

    Sec. 1.  RCW 35.22.620 and 1993 c 198 s 9 are each amended to read as follows:

    (1) As used in this section, the term "public works" means as defined in RCW 39.04.010.

    (2) A first class city may have public works performed by contract pursuant to public notice and call for competitive bids.  As limited by subsection (3) of this section, a first class city may have public works performed by city employees in any annual or biennial budget period equal to a dollar value not exceeding ten percent of the public works construction budget, including any amount in a supplemental public works construction budget, over the budget period.  The amount of public works that a first class city has a county perform for it under RCW 35.77.020 shall be included within this ten percent limitation.

    If a first class city has public works performed by public employees in any budget period that are in excess of this ten percent limitation, the amount in excess of the permitted amount shall be reduced from the otherwise permitted amount of public works that may be performed by public employees for that city in its next budget period.  Twenty percent of the motor vehicle fuel tax distributions to that city shall be withheld if two years after the year in which the excess amount of work occurred, the city has failed to so reduce the amount of public works that it has performed by public employees.  The amount so withheld shall be distributed to the city when it has demonstrated in its reports to the state auditor that the amount of public works it has performed by public employees has been so reduced.

    Whenever a first class city has had public works performed in any budget period up to the maximum permitted amount for that budget period, all remaining public works within that budget period shall be done by contract pursuant to public notice and call for competitive bids.

    The state auditor shall report to the state treasurer any first class city that exceeds this amount and the extent to which the city has or has not reduced the amount of public works it has performed by public employees in subsequent years.

    (3) In addition to the percentage limitation provided in subsection (2) of this section, a first class city with a population in excess of one hundred fifty thousand shall not have public employees perform a public works project in excess of ((fifty)) sixty thousand dollars if more than a single craft or trade is involved with the public works project, or a public works project in excess of ((twenty-five)) thirty thousand dollars if only a single craft or trade is involved with the public works project or the public works project is street signalization or street lighting.  In addition to the percentage limitation provided in subsection (2) of this section, a first class city with a population of one hundred fifty thousand or less shall not have public employees perform a public works project in excess of ((thirty-five)) forty thousand dollars if more than one craft or trade is involved with the public works project, or a public works project in excess of ((twenty)) twenty-five thousand dollars if only a single craft or trade is involved with the public works project or the public works project is street signalization or street lighting.  A public works project means a complete project.  The restrictions in this subsection do not permit the division of the project into units of work or classes of work to avoid the restriction on work that may be performed by day labor on a single project.

    (4) In addition to the accounting and record-keeping requirements contained in RCW 39.04.070, every first class city annually shall prepare a report for the state auditor indicating the total public works construction budget and supplemental public works construction budget for that year, the total construction costs of public works performed by public employees for that year, and the amount of public works that is performed by public employees above or below ten percent of the total construction budget.  However, if a city budgets on a biennial basis, this annual report shall indicate the amount of public works that is performed by public employees within the current biennial period that is above or below ten percent of the total biennial construction budget.

    After September 1, 1987, each first class city with a population of one hundred fifty thousand or less shall use the form required by RCW 43.09.205 to account and record costs of public works in excess of five thousand dollars that are not let by contract.

    (5) The cost of a separate public works project shall be the costs of materials, supplies, equipment, and labor on the construction of that project.  The value of the public works budget shall be the value of all the separate public works projects within the budget.

    (6) When any emergency shall require the immediate execution of such public work, upon the finding of the existence of such emergency by the authority having power to direct such public work to be done and duly entered of record, publication of description and estimate may be made within seven days after the commencement of the work.  Within two weeks of the finding that such an emergency existed, the city council shall adopt a resolution certifying the existence of this emergency situation.

    (7) In lieu of the procedures of subsections (2) and (6) of this section, a first class city may use a small works roster process and award contracts for public works projects with an estimated value of one hundred thousand dollars or less as provided in RCW 39.04.155.

    Whenever possible, the city shall invite at least one proposal from a minority or woman contractor who shall otherwise qualify under this section.

    (8) The allocation of public works projects to be performed by city employees shall not be subject to a collective bargaining agreement.

    (9) This section does not apply to performance-based contracts, as defined in RCW 39.35A.020(3), that are negotiated under chapter 39.35A RCW.

    (10) Nothing in this section shall prohibit any first class city from allowing for preferential purchase of products made from recycled materials or products that may be recycled or reused.

    (11) Beginning on July 1, 1999, and on July 1st of each succeeding odd-numbered year, the dollar limits specified in subsection (3) of this section shall be adjusted as follows:  The office of financial management shall calculate such limits by adjusting the previous biennium's limits by the appropriate federal inflationary index reflecting the rate of inflation for the previous biennium.  Such amounts shall be rounded to the nearest one hundred dollars.

 

    Sec. 2.  RCW 35.23.352 and 1996 c 18 s 2 are each amended to read as follows:

    (1) Any second class city or any town may construct any public works, as defined in RCW 39.04.010, by contract or day labor without calling for bids therefor whenever the estimated cost of the work or improvement, including cost of materials, supplies, and equipment will not exceed the sum of ((thirty)) thirty-five thousand dollars if more than one craft or trade is involved with the public works, or ((twenty)) twenty-five thousand dollars if a single craft or trade is involved with the public works or the public works project is street signalization or street lighting.  A public works project means a complete project.  The restrictions in this subsection do not permit the division of the project into units of work or classes of work to avoid the restriction on work that may be performed by day labor on a single project.

    Whenever the cost of the public work or improvement, including materials, supplies and equipment, will exceed these figures, the same shall be done by contract.  All such contracts shall be let at public bidding upon publication of notice calling for sealed bids upon the work.  The notice shall be published in the official newspaper, or a newspaper of general circulation most likely to bring responsive bids, at least thirteen days prior to the last date upon which bids will be received.  The notice shall generally state the nature of the work to be done that plans and specifications therefor shall then be on file in the city or town hall for public inspections, and require that bids be sealed and filed with the council or commission within the time specified therein.  Each bid shall be accompanied by a bid proposal deposit in the form of a cashier's check, postal money order, or surety bond to the council or commission for a sum of not less than five percent of the amount of the bid, and no bid shall be considered unless accompanied by such bid proposal deposit.  The council or commission of the city or town shall let the contract to the lowest responsible bidder or shall have power by resolution to reject any or all bids and to make further calls for bids in the same manner as the original call.

    When the contract is let then all bid proposal deposits shall be returned to the bidders except that of the successful bidder which shall be retained until a contract is entered into and a bond to perform the work furnished, with surety satisfactory to the council or commission, in accordance with RCW 39.08.030.  If the bidder fails to enter into the contract in accordance with his or her bid and furnish a bond within ten days from the date at which he or she is notified that he or she is the successful bidder, the check or postal money order and the amount thereof shall be forfeited to the council or commission or the council or commission shall recover the amount of the surety bond.  A low bidder who claims error and fails to enter into a contract is prohibited from bidding on the same project if a second or subsequent call for bids is made for the project.

    If no bid is received on the first call the council or commission may readvertise and make a second call, or may enter into a contract without any further call or may purchase the supplies, material or equipment and perform the work or improvement by day labor.

    (2) The allocation of public works projects to be performed by city or town employees shall not be subject to a collective bargaining agreement.

    (3) In lieu of the procedures of subsection (1) of this section, a second class city or a town may use the small works roster process provided in RCW 39.04.155 to award public works contracts with an estimated value of one hundred thousand dollars or less.

    Whenever possible, the city or town shall invite at least one proposal from a minority or woman contractor who shall otherwise qualify under this section.

    (4) The form required by RCW 43.09.205 shall be to account and record costs of public works in excess of five thousand dollars that are not let by contract.

    (5) The cost of a separate public works project shall be the costs of the materials, equipment, supplies, and labor on that construction project.

    (6) Any purchase of supplies, material, or equipment, except for public work or improvement, where the cost thereof exceeds seven thousand five hundred dollars shall be made upon call for bids.

    (7) Bids shall be called annually and at a time and in the manner prescribed by ordinance for the publication in a newspaper of general circulation in the city or town of all notices or newspaper publications required by law.  The contract shall be awarded to the lowest responsible bidder.

    (8) For advertisement and formal sealed bidding to be dispensed with as to purchases between seven thousand five hundred and fifteen thousand dollars, the council or commission must authorize by resolution, use of the uniform procedure provided in RCW 39.04.190.

    (9) These requirements for purchasing may be waived by resolution of the city or town council or commission which declared that the purchase is clearly and legitimately limited to a single source or supply within the near vicinity, or the materials, supplies, equipment, or services are subject to special market conditions, and recites why this situation exists.  Such actions are subject to RCW 39.30.020.

    (10) This section does not apply to performance-based contracts, as defined in RCW 39.35A.020(3), that are negotiated under chapter 39.35A RCW.

    (11) Nothing in this section shall prohibit any second class city or any town from allowing for preferential purchase of products made from recycled materials or products that may be recycled or reused.

    (12) Beginning on July 1, 1999, and on July 1st of each succeeding odd-numbered year, the dollar limits specified in subsection (1) of this section shall be adjusted as follows:  The office of financial management shall calculate such limits by adjusting the previous biennium's limits by the appropriate federal inflationary index reflecting the rate of inflation for the previous biennium.  Such amounts shall be rounded to the nearest one hundred dollars.

 


                            --- END ---