HB 1766 - DIGEST

 

                      (DIGEST AS ENACTED)

 

     Provides that the dollar bid threshold requiring general contractors to list the names of all subcontractors as part of the bid is raised from in excess of $100,000 to $1 million more.

     Declares that the general contractor only has to list subcontractors that contract directly with the general contractor for specific areas of work and may not list more than one subcontractor for each category of work.  The specific areas of work are defined as heating, ventilation and air conditioning, plumbing, and electrical work.

     Provides that failure to submit names of subcontractors, or for the bidder to name itself to perform such work, or the naming of two or more subcontractors to perform the same work will render the bid void.