2056-S.E AMS GO S2802.1
ESHB 2056 - S COMM AMD
By Committee on Government Operations & Elections
ADOPTED 04/11/2003
Strike everything after the enacting clause and insert the following:
"NEW SECTION. Sec. 1. A new section is added to chapter 39.04 RCW to read as follows:
When a municipality receives a written protest from a bidder for a public works project which is the subject of competitive bids, the municipality shall not execute a contract for the project with anyone other than the protesting bidder without first providing at least two full business days' written notice of the municipality's intent to execute a contract for the project; provided that the protesting bidder submits notice in writing of its protest no later than two full business days following bid opening. Intermediate Saturdays, Sundays, and legal holidays are not counted in determining the minimum two-day notice period.
NEW SECTION. Sec. 2. A new section is added to chapter 39.04 RCW to read as follows:
A low bidder on a public works project who claims error and fails to enter into a contract is prohibited from bidding on the same project if a second or subsequent call for bids is made for the project.
Sec. 3. RCW 39.10.061 and 2002 c 46 s 2 are each amended to read as follows:
(1) Notwithstanding any other provision of law, and after complying with RCW 39.10.030, a public body may utilize the general contractor/construction manager procedure of public works contracting for public works projects authorized under subsection (2) of this section. For the purposes of this section, "general contractor/construction manager" means a firm with which a public body has selected and negotiated a maximum allowable construction cost to be guaranteed by the firm, after competitive selection through formal advertisement and competitive bids, to provide services during the design phase that may include life-cycle cost design considerations, value engineering, scheduling, cost estimating, constructability, alternative construction options for cost savings, and sequencing of work, and to act as the construction manager and general contractor during the construction phase.
(2) Except those school districts proposing projects that are considered and approved by the school district project review board, public bodies authorized under this section may utilize the general contractor/construction manager procedure for public works projects valued over ten million dollars where:
(a) Implementation of the project involves complex scheduling requirements; or
(b) The project involves construction at an existing facility which must continue to operate during construction; or
(c) The involvement of the general contractor/construction manager during the design stage is critical to the success of the project.
(3) Public bodies should select general contractor/construction managers early in the life of public works projects, and in most situations no later than the completion of schematic design.
(4) Contracts for the services of a general contractor/construction manager under this section shall be awarded through a competitive process requiring the public solicitation of proposals for general contractor/construction manager services. The public solicitation of proposals shall include: A description of the project, including programmatic, performance, and technical requirements and specifications when available; the reasons for using the general contractor/construction manager procedure; a description of the qualifications to be required of the proposer, including submission of the proposer's accident prevention program; a description of the process the public body will use to evaluate qualifications and proposals, including evaluation factors and the relative weight of factors; the form of the contract to be awarded; the estimated maximum allowable construction cost; and the bid instructions to be used by the general contractor/construction manager finalists. Evaluation factors shall include, but not be limited to: Ability of professional personnel, past performance in negotiated and complex projects, and ability to meet time and budget requirements; the scope of work the general contractor/construction manager proposes to self-perform and its ability to perform it; location; recent, current, and projected work loads of the firm; and the concept of their proposal. A public body shall establish a committee to evaluate the proposals. After the committee has selected the most qualified finalists, these finalists shall submit final proposals, including sealed bids for the percent fee, which is the percentage amount to be earned by the general contractor/construction manager as overhead and profit, on the estimated maximum allowable construction cost and the fixed amount for the detailed specified general conditions work. The public body shall select the firm submitting the highest scored final proposal using the evaluation factors and the relative weight of factors published in the public solicitation of proposals.
(5) The maximum allowable construction cost may be negotiated between the public body and the selected firm after the scope of the project is adequately determined to establish a guaranteed contract cost for which the general contractor/construction manager will provide a performance and payment bond. The guaranteed contract cost includes the fixed amount for the detailed specified general conditions work, the negotiated maximum allowable construction cost, the percent fee on the negotiated maximum allowable construction cost, and sales tax. If the public body is unable to negotiate a satisfactory maximum allowable construction cost with the firm selected that the public body determines to be fair, reasonable, and within the available funds, negotiations with that firm shall be formally terminated and the public body shall negotiate with the next highest scored firm and continue until an agreement is reached or the process is terminated. If the maximum allowable construction cost varies more than fifteen percent from the bid estimated maximum allowable construction cost due to requested and approved changes in the scope by the public body, the percent fee shall be renegotiated.
(6) All subcontract work shall be competitively bid with public bid openings. When critical to the successful completion of a subcontractor bid package and after publication of notice of intent to determine bidder eligibility in a legal newspaper of general circulation published in or as near as possible to that part of the county in which the public work will be done at least twenty days before requesting qualifications from interested subcontract bidders, the owner and general contractor/construction manager may determine subcontractor bidding eligibility using the following evaluation criteria:
(a) Adequate financial resources or the ability to secure such resources;
(b) History of successful completion of a contract of similar type and scope;
(c) Project management and project supervision personnel with experience on similar projects and the availability of such personnel for the project;
(d) Current and projected workload and the impact the project will have on the subcontractor's current and projected workload;
(e) Ability to accurately estimate the subcontract bid package scope of work;
(f) Ability to meet subcontract bid package shop drawing and other coordination procedures;
(g) Eligibility to receive an award under applicable laws and regulations; and
(h) Ability to meet subcontract bid package scheduling requirements.
The owner and general contractor/construction manager shall weigh the evaluation criteria and determine a minimum acceptable score to be considered an eligible subcontract bidder.
After publication of notice of intent to determine bidder eligibility, subcontractors requesting eligibility shall be provided the evaluation criteria and weighting to be used by the owner and general contractor/construction manager to determine eligible subcontract bidders. After the owner and general contractor/construction manager determine eligible subcontract bidders, subcontractors requesting eligibility shall be provided the results and scoring of the subcontract bidder eligibility determination.
Subcontract bid packages shall be awarded to the responsible bidder submitting the low responsive bid. The requirements of RCW 39.30.060 apply to each subcontract bid package. All subcontractors who bid work over three hundred thousand dollars shall post a bid bond and all subcontractors who are awarded a contract over three hundred thousand dollars shall provide a performance and payment bond for their contract amount. All other subcontractors shall provide a performance and payment bond if required by the general contractor/construction manager. If a general contractor/construction manager receives a written protest from a subcontractor bidder, the general contractor/construction manager shall not execute a contract for the subcontract bid package with anyone other than the protesting bidder without first providing at least two full business days' written notice of the general contractor/construction manager's intent to execute a contract for the subcontract bid package. Intermediate Saturdays, Sundays, and legal holidays are not counted in determining the minimum two-day notice period. A low bidder who claims error and fails to enter into a contract is prohibited from bidding on the same project if a second or subsequent call for bids is made for the project. Except as provided for under subsection (7) of this section, bidding on subcontract work by the general contractor/construction manager or its subsidiaries is prohibited. The general contractor/construction manager may negotiate with the low-responsive bidder in accordance with RCW 39.10.080 or, if unsuccessful in such negotiations, rebid.
(7) The general contractor/construction manager, or its subsidiaries, may bid on subcontract work if:
(a) The work within the subcontract bid package is customarily performed by the general contractor/construction manager;
(b) The bid opening is managed by the public body; and
(c) Notification of the general contractor/construction manager's intention to bid is included in the public solicitation of bids for the bid package.
In no event may the value of subcontract work performed by the general contractor/construction manager exceed thirty percent of the negotiated maximum allowable construction cost.
(8) A public body may include an incentive clause in any contract awarded under this section for savings of either time or cost or both from that originally negotiated. No incentives granted may exceed five percent of the maximum allowable construction cost. If the project is completed for less than the agreed upon maximum allowable construction cost, any savings not otherwise negotiated as part of an incentive clause shall accrue to the public body. If the project is completed for more than the agreed upon maximum allowable construction cost, excepting increases due to any contract change orders approved by the public body, the additional cost shall be the responsibility of the general contractor/construction manager."
ESHB 2056 - S COMM AMD
By Committee on Government Operations & Elections
ADOPTED 04/11/2003
On page 1, line 1 of the title, after "bidding;" strike the remainder of the title and insert "amending RCW 39.10.061; and adding new sections to chapter 39.04 RCW."
--- END ---
<