SENATE BILL REPORT

SB 6208


 


 

As Reported By Senate Committee On:

Government Operations & Elections, January 27, 2004

 

Title: An act relating to water-sewer district charges for temporary facilities.

 

Brief Description: Allowing water-sewer districts to set connection charges for future facilities.

 

Sponsors: Senators Roach, Kastama and McCaslin.


Brief History:

Committee Activity: Government Operations & Elections: 1/27/04 [DPS].

      


 

SENATE COMMITTEE ON GOVERNMENT OPERATIONS & ELECTIONS


Majority Report: That Substitute Senate Bill No. 6208 be substituted therefor, and the substitute bill do pass.

      Signed by Senators Roach, Chair; Stevens, Vice Chair; Berkey, Fairley, Horn, Kastama and McCaslin.

 

Staff: Diane Smith (786-7410)

 

Background: One of the powers granted to water-sewer districts is the power to fix rates and charges for the service they supply and to charge property owners who wish to connect to the district's system a connection charge in addition to the cost of connection. The connection charge is set by the water-sewer district commissioners so that the connecting property owners bear their equitable share of the cost of the system. The calculation of the connection charge must be a pro rata share of the sum of three cost centers, as follows: the cost of existing facilities; the cost of facilities planned, in an adopted comprehensive plan, to be constructed within the next ten years; and other costs the district must pay that are directly attributable to the improvements required by the property owners seeking to connect.

 

Summary of Substitute Bill: In the case of requiring the installation of permanent local facilities that the district is not planning to construct, the district is given an alternative. This alternative is to permit connection to its system by means of temporary facilities and to collect from the property owners seeking this connection by means of temporary facilities, a proportionate share of the cost of future local facilities needed to serve the property. The amount collected is held, together with interest, to be used for contribution towards the costs of construction of permanent local facilities by other developers. If these permanent facilities are not constructed within 15 years of the date of payment, the amount collected, including accrued interest, is returned to the property owner.

 

Substitute Bill Compared to Original Bill: The original bill was not considered.

 

Appropriation: None.

 

Fiscal Note: Not requested.

 

Effective Date: Ninety days after adjournment of session in which bill is passed.

 

Testimony For: This is the reverse of a late-comer's fee. It allows service for the first developer that needs to be connected in remote areas. That person pays for their own temporary connection to a water-sewer district's facilities and for a proportionate share of a future permanent facility. If no permanent facility is built by the district in the next 15 years, then the payment is returned to the lot with the temporary facility.

 

Testimony Against: None.

 

Testified: Phil Watkins, Bert Ross, Lakehaven Utility District (pro).