BILL REQ. #: S-0818.1
State of Washington | 58th Legislature | 2003 Regular Session |
Read first time 02/14/2003. Referred to Committee on Judiciary.
AN ACT Relating to the timely payment by government on contract claims; amending RCW 39.76.011 and 39.76.020; and adding a new section to chapter 39.76 RCW.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
Sec. 1 RCW 39.76.011 and 1992 c 223 s 1 are each amended to read
as follows:
(1) Except as provided in RCW 39.76.020, every state agency,
county, city, town, school district, board, commission, or any other
public body shall pay interest at a rate of one and one-half percent
per month((, but at least one dollar per month,)) on amounts due on
written contracts for public works, personal services, goods and
services, equipment, and travel, whenever the public body fails to make
timely payment. Chapter 19.52 RCW does not apply to this section.
(2) For purposes of this section, payment shall be timely if:
(a) Except as provided otherwise in this subsection, a check or
warrant is mailed or is available on the date specified for the amount
specified in the applicable contract documents but not later than
thirty days of receipt of a properly completed invoice or receipt of
goods or services, whichever is later. If a contract is funded by
grant or federal money, the public body shall pay the prime contractor
for satisfactory performance within thirty calendar days of the date
the public body receives a payment request that complies with the
contract or within thirty calendar days of the date the public body
actually receives the grant or federal money, whichever is later.
(b) On written contracts for public works, when part or all of a
payment is going to be withheld for unsatisfactory performance or if
the payment request made does not comply with the requirements of the
contract, the public body shall notify the prime contractor in writing
within eight working days after receipt of the payment request stating
specifically why part or all of the payment is being withheld and what
remedial actions must be taken by the prime contractor to receive the
withheld amount.
(c) If the notification by the public body required by (b) of this
subsection does not comply with the notice contents required under (b)
of this subsection, the public body shall pay the interest under
subsection (1) of this section from the ninth working day after receipt
of the initial payment request until the contractor receives notice
that does comply with the notice contents required under (b) of this
subsection.
(d) If part or all of a payment is withheld under (b) of this
subsection, the public body shall pay the withheld amount within thirty
calendar days after the prime contractor satisfactorily completes the
remedial actions identified in the notice. If the withheld amount is
not paid within the thirty calendar days, the public body shall pay
interest under subsection (1) of this section from the thirty-first
calendar day until the date paid.
(e)(i) If the prime contractor on a public works contract, after
making a request for payment to the public body but before paying a
subcontractor for the subcontractor's performance covered by the
payment request, discovers that part or all of the payment otherwise
due to the subcontractor is subject to withholding from the
subcontractor under the subcontract for unsatisfactory performance, the
prime contractor may withhold the amount as allowed under the
subcontract. If the prime contractor withholds an amount under this
subsection, the prime contractor shall:
(A) Give the subcontractor notice of the remedial actions that must
be taken as soon as practicable after determining the cause for the
withholding but before the due date for the subcontractor payment;
(B) Give the contracting officer of the public body a copy of the
notice furnished to the subcontractor under (e)(i)(A) of this
subsection; and
(C) Pay the subcontractor within eight working days after the
subcontractor satisfactorily completes the remedial action identified
in the notice.
(ii) If the prime contractor does not comply with the notice and
payment requirements of (e)(i) of this subsection, the contractor shall
pay the subcontractor interest on the withheld amount from the eighth
working day at an interest rate that is equal to the amount set forth
in subsection (1) of this section.
(3) For the purposes of this section:
(a) A payment is considered to be made when mailed or personally
delivered to the party being paid.
(b) An invoice is considered to be received when it is date-stamped
or otherwise marked as delivered. If the invoice is not date-stamped
or otherwise marked as delivered, the date of the invoice is considered
to be the date when the invoice is received.
Sec. 2 RCW 39.76.020 and 1981 c 68 s 2 are each amended to read
as follows:
RCW 39.76.010 does not apply to the following:
(1) Interagency or intergovernmental transactions;
(2) Amounts payable to employees or prospective employees of state
agencies or local governmental units as reimbursement for expenses;
(3) Belated claims for any time of delinquency after July 31
following the second year of the fiscal biennium;
(4)(a) Claims subject to a good faith dispute, when before the date
of timely payment, notice of the dispute is:
(((a))) (i) Sent by certified mail;
(((b))) (ii) Personally delivered; or
(((c))) (iii) Sent in accordance with procedures in the contract;
(b) This subsection (4) is only applicable to the portion of the
claim that is being disputed in good faith. Any portion of the claim
that is not being disputed in good faith must be paid in a timely
manner and is subject to RCW 39.76.010 or 39.76.011 and section 3 of
this act.
(5) Delinquencies due to natural disasters, disruptions in postal
or delivery service, work stoppages due to labor disputes, power
failures, or any other cause resulting from circumstances clearly
beyond the control of the unit of local government or state agency;
(6) Contracts entered before July 26, 1981; and
(7) Payment from any retirement system listed in RCW 41.50.030 and
chapter 41.24 RCW.
NEW SECTION. Sec. 3 A new section is added to chapter 39.76 RCW
to read as follows:
Any person who prevails against a public body in any action brought
to collect interest due under this chapter, shall be awarded the
interest due, including interest on payments that were not withheld in
good faith under RCW 39.76.020(4), plus all costs, including reasonable
attorney fees, incurred in connection with the legal action. In
addition, it shall be within the discretion of the court to award the
person an amount not less than five dollars and not to exceed one
hundred dollars for each day that payments upon which interest accrued
were withheld.