BILL REQ. #: S-3862.2
State of Washington | 58th Legislature | 2004 Regular Session |
Read first time 01/19/2004. Referred to Committee on Parks, Fish & Wildlife.
AN ACT Relating to compliance with the hydraulic project approval requirements; amending RCW 77.15.300; and adding a new section to chapter 77.55 RCW.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
NEW SECTION. Sec. 1 A new section is added to chapter 77.55 RCW
to read as follows:
If any person or government agency fails to follow the requirements
of obtaining hydraulic project approval under this chapter or fails to
carry out any of the requirements or conditions of a hydraulic project
approval issued under this chapter, the department may issue a cease
and desist order to that person or government agency. The cease and
desist order must set forth the specific nature, extent, and time of
violation, the damage or potential damage, a notice that the violation
cease and desist, and, in appropriate cases, the specific corrective
action to be taken within a specified time. Within twenty days of
service of a cease and desist or other order or as provided by rule of
the department extending the time, the person may file a written
petition with the department appealing the order, and this petition
must be treated as an application for an adjudicative proceeding under
chapter 34.05 RCW. In the event of an appeal, a person or government
agency may seek interim relief from a cease and desist or other order
under this section as provided in chapter 34.05 RCW.
Sec. 2 RCW 77.15.300 and 2000 c 107 s 239 are each amended to
read as follows:
(1) Except as otherwise provided in this section, a person is
guilty of unlawfully undertaking hydraulic project activities if the
person constructs any form of hydraulic project or performs other work
on a hydraulic project and:
(a) Fails to have a hydraulic project approval required under
chapter 77.55 RCW for such construction or work; ((or))
(b) Violates any requirements or conditions of the hydraulic
project approval for such construction or work; or
(c) Violates any cease and desist or other order issued under
section 1 of this act if that order has been either served on the
person or posted at the site of the violation, except if the person
acts in accordance with any relief under chapter 34.05 RCW pursuant to
a timely appeal or timely relief from the department cease and desist
or other order.
(2) Unlawfully undertaking hydraulic project activities is a gross
misdemeanor.
(3) A person is not guilty of unlawfully undertaking hydraulic
project activities if the person is subject to a cease and desist or
other order issued under section 1 of this act unless the person
violates the cease and desist or other order. This section does not
apply to activities that are the subject of a cease and desist or other
order issued under section 1 of this act and the person does not
violate such an order.