FINAL BILL REPORT
ESHB 1020
C 196 L 06
Synopsis as Enacted
Brief Description: Regarding electrical transmission.
Sponsors: By House Committee on Technology, Energy & Communications (originally sponsored by Representatives Morris and B. Sullivan).
House Committee on Technology, Energy & Communications
Senate Committee on Water, Energy & Environment
Background:
Electrical Transmission
The region's electrical transmission grid is an interconnected network of transmission lines
that transfers bulk power between points of supply and demand. The main grid consists of
500 kilovolt, 345 kilovolt, and 230 kilovolt lines. These lines are usually mounted on large
metal towers that range in height from 70 to 170 feet, depending on the size, location, and
design of the tower. The towers typically require rights-of-way that are 90 to 165 feet wide.
Energy Policy Act of 2005
The national Energy Policy Act of 2005 (Act) was signed into law August 2005. Section
1221 of the Act authorizes the Secretary of the U.S. Department of Energy (Secretary) to
conduct a study within one year of passage, and triennially thereafter, of electric transmission
congestion. The Secretary will issue a report based on the study, which may designate any
geographic area experiencing electric energy transmission capacity constraints or congestion
that adversely affects consumers as a national interest energy electric transmission corridor.
In determining whether to designate a particular area as a national interest electric
transmission corridor, the Secretary may consider the following:
FERC's Backstop Authority
The Act authorizes the Federal Energy Regulatory Commission to issue permits for
construction or modification of electric transmission in a national interest transmission
corridor if:
EFSEC Licensing
The Energy Facility Site Evaluation Council (EFSEC) was created in 1970 to provide
one-stop licensing for large energy projects. The EFSEC's membership includes mandatory
representation from five state agencies and discretionary representation from four additional
state agencies. The EFSEC's membership may include representatives from the particular
city, county, or port district where potential projects may be located.
The EFSEC's jurisdiction includes the siting of large intrastate natural gas and petroleum
pipelines, electric power plants above 350 megawatts, new oil refineries, large expansions of
existing facilities, and underground natural gas storage fields. For electric power plants, the
EFSEC's jurisdiction extends to those associated facilities that include new transmission lines
that operate in excess of 200 kilovolts and are necessary to connect the plant to the Northwest
power grid.
The EFSEC siting process generally involves six steps: (1) a potential site study followed by
an application; (2) a State Environmental Policy Act review; (3) a review for consistency
with applicable local land use laws and plans; (4) a formal adjudication on all issues related
to the project; (5) certain air and water pollution discharge permitting reviews as delegated by
the U.S. Environmental Protection Agency; and (6) a recommendation to the Governor who
then decides whether to accept, reject, or remand the application. A certification agreement
approved by the Governor preempts any other state or local regulation concerning the
location, construction, and operational conditions of an energy facility. Under the EFSEC
process, the applicant is required to pay the costs of the EFSEC in processing an application.
County and City Growth Management
Under the Growth Management Act, certain counties and cities must develop comprehensive
land use plans outlining the coordinated land use policy of the county or city. The
comprehensive land use planning process includes adopting development regulations, such as
zoning ordinances, critical areas ordinances, and binding site plan ordinances.
Summary:
EFSEC Jurisdiction
The EFSEC jurisdiction is extended to include new electrical transmission lines that operate
in excess of 115 kilovolts that are necessary to connect a power plant to the region's power
grid and electrical transmission facilities in excess of 115 kilovolts in national interest
electric transmission corridors. When siting transmission facilities, EFSEC must not
consider the fuel source of the electricity to be carried on the facilities.
After "The EFSEC is designated as the state authority for purposes of siting transmission
facilities under the national Energy Policy Act of 2005 and any accompanying regulations
that may be adopted by the U.S. Secretary of Energy.", and "The EFSEC's authority regarding
transmission facilities is limited to those transmission facilities that are the subject of the
Energy Policy Act of 2005. When siting transmission facilities related to Energy Policy Act
of 2005, the EFSEC may consider interstate benefits to be achieved by the proposed
construction or modification of the facilities in the state." In addition, the EFSEC must
convey to the U.S. Secretary of Energy the views of interested parties in the state concerning
the appropriate limits on federal authority over transmission siting in the state.
Changes to the EFSEC Process
Various updates are made to the EFSEC process, including the consideration of local land
use plans and ordinances adopted under the Growth Management Act. Also, reimbursements
are authorized for the time a local government's member or designee services on the EFSEC
in reviewing a siting application.
Votes on Final Passage:
House 93 2
Senate 46 0 (Senate amended)
House 98 0
Senate 48 0 (Senate amended)
House 96 0 (House concurred)
Effective: June 7, 2006