HOUSE BILL REPORT
HB 1404
As Reported by House Committee On:
Natural Resources, Ecology & Parks
Title: An act relating to forest practices.
Brief Description: Requiring certain local governments to regulate forest practices.
Sponsors: Representatives B. Sullivan, Hinkle, Kretz, Upthegrove and Buck.
Brief History:
Natural Resources, Ecology & Parks: 2/10/05, 2/22/05 [DPS].
Brief Summary of Substitute Bill |
|
|
HOUSE COMMITTEE ON NATURAL RESOURCES, ECOLOGY & PARKS
Majority Report: The substitute bill be substituted therefor and the substitute bill do pass. Signed by 7 members: Representatives B. Sullivan, Chair; Upthegrove, Vice Chair; Buck, Ranking Minority Member; Blake, Dickerson, Eickmeyer and Williams.
Minority Report: Do not pass. Signed by 3 members: Representatives Kretz, Assistant Ranking Minority Member; DeBolt and Orcutt.
Staff: Jason Callahan (786-7117).
Background:
Classes of forest practices
Prior to conducting a harvest or most other silvicultural treatments on forest land, a forest
landowner must apply to the Department of Natural Resources (DNR) for approval for the
proposed forest practice. The application process and application fee required varies
depending on what class of forest practice is proposed. A forest practice can fall into one of
four classes:
The role of local governments in forest practices approvals
Counties and cities have the authority to approve or disapprove certain class IV forest
practices applications. In order to assume approval authority, the county or city must adopt
ordinances that establish minimum standards for class IV forest practices, establish the
necessary administrative provisions, and set procedures for the collection of fees. All cities
and counties are required to adopt the necessary ordinances for class IV forest practices
approval by December 31, 2005.
The authority to approve or disapprove class IV forest practices applications does not pass
from the DNR to the city or county until the DNR has granted final approval of the city or
county's ordinances. In conducting a review of the local government's proposed ordinances,
the DNR is required to consult with the Department of Ecology, and may disapprove the
ordinance wholly, or in part. Local governments that believe a disapproval of their
ordinances was improper may appeal the DNR's decision to the Forest Practices Appeal
Board.
Counties and cities that adopt the necessary ordinances to obtain control over class IV forest
practices approvals, and have those ordinances approved by the DNR, are eligible for
technical assistance from the DNR until January 1, 2006.
Summary of Substitute Bill:
The process for transferring authority to approve or disapprove forest practices applications is
repealed. A new mechanism with new dates is established. Some counties and cities are
required to adopt forest practices approval ordinances by the end of 2007, while the other
counties and cities retain the discretion to not assume the responsibility for approving forest
practices. The requirements on local governments vary depending on whether a county plans
under the Growth Management Act (GMA), although the path for transferring jurisdiction
remains constant across all counties.
Mandatory vs. discretionary
Some counties and cities are required to adopt and enforce ordinances or regulations for the
approval of forest practices applications, while the assumption of this responsibility is
optional for other local governments. The trigger for determining if a county or city is
required to adopt these ordinances is the number of forest practices applications that have
been submitted within the county for the time period between January 1, 2000 and December
31, 2002.
If more than 25 class IV applications had been filed to the DNR between those dates for
properties within a specific county, then that county, and the cities within it, are required to
adopt forest practices approval ordinances. If the number is less than 25, then the transfer of
jurisdiction for approvals is optional for the county and its cities.
In determining the number of class IV applications filed within a county, only certain
applications are counted. Those counted are limited to applications for class IV practices on
lands platted in 1960 or later, lands that have been converted to a non-forestry use, lands that
will not be replanted because of a likelihood of conversion to a non-forestry use, and lands
within an urban growth area.
GMA counties vs. Non-GMA counties
Although the 25-application trigger for mandatory assumption of jurisdiction over forest
practices approvals is consistent for all counties, the requirements for counties differ
depending on a particular county's participation under the GMA.
Counties not planning under the GMA, and the cities within them, only are required to
assume the jurisdiction for approving class IV forest practices on lands platted later than
1959, lands that are not to be reforested because of the likelihood of future urban
development, and lands that are already in the process of being converted to a non-forestry
use.
Counties that do plan under the GMA, and their cities, are required to adopt ordinances
covering class IV forest practices applications on the same lands that non-GMA counties
must address, as well as ordinances for the approval or all four class types of forest practices
when those applications are submitted for land located within an urban growth area.
The only land that GMA-planning counties and cities are not required to assume the
jurisdiction over are ownerships of 20 contiguous acres or more. However, the 20-acre
exception only applies if the owner of the property submits a written statement to the county
and the DNR that he or she does not intend to convert the property to a non-forestry use for
the coming decade. The owner' s written statement must be accompanied by both a written
forest management plan that is acceptable to the DNR, and documentation that the land is
enrolled, for the purposes of property taxes, as forest land of long-term significance.
Pre-requisites for a transfer of jurisdiction
The ordinances adopted by the counties and cities must require appropriate approvals for all
phases of forest land conversion and procedures for the collection of all administrative and
permit fees. Development regulations must also be adopted that protect public resources
from material damage and requires appropriate approvals for all phases of forest land
conversion, and the local jurisdiction must ensure consistency between its comprehensive
plan and the new development regulations.
A county or city can not assume the jurisdiction for forest practices approvals without
bringing their critical areas and development regulations in compliance with the current
requirements and notifying both the DNR and the Department of Ecology at least 60 days
before adoption of the necessary ordinances. However, neither department must approve of
the ordinances before the jurisdictional transfer occurs.
Role of the DNR
Exclusive jurisdiction over forest practices approvals remains with the DNR until a county or
city satisfies all requirements for the jurisdictional transfer, even after the date by which all
counties must have the appropriate ordinances adopted. The DNR is also required to provide
technical assistance to the cities and counties during and after the process of ordinance
adoption.
Substitute Bill Compared to Original Bill:
The substitute bill specifies that cities and counties that have already adopted ordinances for
forest practices are not required to re-adopt those ordinances, and that forest practices being
regulated by a local government are subject to the regulations of that local government and
are not subject to the Forest Practice Rules.
Appropriation: None.
Fiscal Note: Available.
Effective Date of Substitute Bill: The bill takes effect 90 days after adjournment of session in which bill is passed.
Testimony For: (In support of original bill) There are concerns with the current 2005 date
and processes for transferring class IV approvals to local governments, although it is still
believed that the local governments should take over permitting when land is not going to be
reforested. The adoption of ordinances did not work out as it was envisioned, and this bill
will make clear that an appropriate standard must be set by the county.
This bill is good for the citizen who wants to conduct a forest practice, as well as being good
for the environment. The streamlined process will mean that a developer will not need to get
all of the permits from the county or city, only to then have to get a forest practices approval
from the DNR. Consolidating all permitting at the local level makes sense since forest
practices in urbanizing areas is interwoven with urban planning.
(With concerns to original bill) Counties may not have enough money to take on the extra
requirements, so there should be an option to maintain DNR approvals if the county so
chooses.
Testimony Against: None.
Persons Testifying: (In support of original bill) Representative B. Sullivan, prime sponsor;
Eric Johnson and Paul Parker, Washington State Association of Counties; Leonard Young,
Washington Department of Natural Resources; and Leonard Bauer, Department of
Community, Trade and Economic Development.