Washington State House of Representatives Office of Program Research |
BILL ANALYSIS |
Local Government Committee | |
HB 2219
Brief Description: Expanding eligibility for urban industrial land banks.
Sponsors: Representatives Hunt, DeBolt, Williams and Alexander.
Brief Summary of Bill |
|
Hearing Date: 3/1/05
Staff: Thamas Osborn (786-7129).
Background:
Major Industrial Development Pilot Project.
In 1996 the Legislature enacted legislation as part of the Growth Management Act (GMA)
authorizing a pilot project under which areas for major industrial development could be
established outside urban growth areas (UGAs) for the purpose of expeditiously siting such
development. Among other provisions, the pilot project legislation: a) allowed only certain
counties to participate in the project, such participation being contingent on the satisfaction of
detailed criteria relating to population, geographic location, and unemployment statistics; b)
established criteria for siting these developments within designated banks of land; and c)
provided for amending GMA comprehensive plans to implement these provisions. The
provisions of the original pilot project have been amended several times to modify the
applicability criteria and termination dates.
Industrial Land Banks Definition.
"Industrial land bank" is defined to mean up to two master planned locations, each consisting of a
parcel or parcels of contiguous land, sufficiently large so as not to be readily available within the
UGA of a city, or otherwise meeting specified criteria. The definition specifies that the land
bank must be suitable for manufacturing, industrial, or commercial businesses and designated by
the county through the comprehensive planning process specifically for major industrial use.
Master Planned Locations Establishment Criteria.
Eligible counties may establish up to two master planned locations for major industrial activity
within an urban industrial land bank (land bank) located outside UGAs. Among other criteria for
establishing major industrial developments within designated land banks, eligible counties must
provide for new infrastructure, determine the feasibility of alternate sites, and satisfy specific
development regulation requirements. Additionally, when selecting locations for inclusion
within a land bank, counties must give priority to locations adjacent to, or in close proximity to, a
UGA.
Comprehensive Planning Process Locating Industrial Developments in Land Banks.
An eligible county must complete a comprehensive planning process before a master planned
location for a major industrial development may be included in an industrial land bank. The
planning process must ensure that the following criteria are met:
Development Regulations Authorization of Specific Major Industrial Developments.
An eligible county must adopt development regulations establishing the criteria that must be met
before the siting of a specific major industrial development within an approved industrial land
bank may be authorized. These criteria must ensure that:
The approval of specific proposals for siting specific major industrial developments requires no
further comprehensive plan amendment.
County Elibibility Criteria for the Creation of Master Planned Industrial Development.
The act allows only certain counties to be eligible for participation in the urban industrial land
bank designation process outlined in the provisions of the act. The eligible counties are
categorized into two groupings that are differentiated in accordance with the date of the
expiration of their authority to engage in the land bank development process. The expiration of
such authority for one group of counties is December 31, 2007. The expiration of such authority
for the other group of counties was December 31, 2002.
To be included in the group of counties whose authority expires on December 31, 2007, a county
must meet one of several sets of criteria that include detailed requirements related to population,
geographic location, and unemployment statistics. These eligibility criteria allow the inclusion of
counties that meet one of the following sets of conditions:
Summary of Bill:
A county that has "direct major rail line access" and which borders another county eligible for
participation in the urban industrial land bank designation process is also eligible to create urban
industrial land banks. A county meeting these criteria has until December 31, 2007
to engage in the process of creating master planned locations in an urban industrial land bank.
Appropriation: None.
Fiscal Note: Not requested.
Effective Date: The bill takes effect 90 days after adjournment of session in which bill is passed.