FINAL BILL REPORT
SHB 2402
C 205 L 06
Synopsis as Enacted
Brief Description: Providing for expedited processing of energy facilities and alternative energy resources.
Sponsors: By House Committee on Technology, Energy & Communications (originally sponsored by Representatives Morris, Hudgins and B. Sullivan).
House Committee on Technology, Energy & Communications
Senate Committee on Water, Energy & Environment
Background:
Energy Facility Site Evaluation Council
The Energy Facility Site Evaluation Council (EFSEC) was created in 1970 to provide one-stop licensing for large energy projects. The EFSEC's membership includes mandatory
representation from five state agencies and discretionary representation from four additional
state agencies. The EFSEC's membership may include representatives from the particular
city, county, or port district where potential projects may be located. "In reviewing facility
siting applications, the EFSEC must determine whether or not a proposed site is consistent
and in compliance with county or regional land use plans or zoning ordinances."
The EFSEC's jurisdiction includes the siting of large intrastate natural gas and petroleum
pipelines, electric power plants above 350 megawatts, new oil refineries, large expansions of
existing facilities, and underground natural gas storage fields. For electric power plants, the
EFSEC's jurisdiction extends to those associated facilities that include new transmission lines
that operate in excess of 200 kilovolts and are necessary to connect the plant to the Northwest
power grid.
Alternative Energy Resource Facilities
Developers of energy facilities that exclusively use alternative energy resources, regardless of
the size of the facility's generation capacity, may choose to use the EFSEC process to site the
facility. "Alternative energy resources" include wind, solar, geothermal, landfill gas, wave or
tidal, untreated wood, and field residues.
Expedited Processing
A siting application may be expeditiously processed if the following criteria are not
significant enough to warrant the EFSEC's full review: (1) the environmental impact of the
proposed energy facility; (2) the area potentially affected: (3) the cost and magnitude of the
proposed energy facility; and (4) the degree to which the proposed energy facility represents a
change in use of the proposed site. The expedited process does not apply to alternative
energy resource facilities. Under the EFSEC process, the applicant is required to pay the
costs of the EFSEC in processing an application.
Summary:
Expanding Expedited Processing to Alternative Energy Resource Facilities
Al alternative energy resource facility may apply for expedited processing of its siting
application.
Modifying Expedited Processing
The EFSEC may grant an applicant expedited processing of any siting application for
certification upon finding that (1) the environmental impact of the proposed energy facility is
not significant or will be mitigated to a nonsignificant level under the State Environmental
Policy Act, and (2) the project is found to be consistent and in compliance with city, county
or regional land use plans or zoning ordinances. Once the applicant has been awarded
expedited processing the EFSEC is not required to commission an independent study to
further measure the consequences of the proposed energy facility or alternative energy
resource facility on the environment.
Municipal Land Use Plans and Ordinances
City land use plans and zoning ordinances, as well as such county and regional plans and
ordinances, must be considered by the EFSEC in reviewing an application, whether or not
expedited processing is used.
Votes on Final Passage:
House 93 3
Senate 45 0 (Senate amended)
House 97 0 (House concurred)
Effective: June 7, 2006