Washington State House of Representatives Office of Program Research |
BILL ANALYSIS |
Local Government Committee | |
ESSB 5285
Brief Description: Updating the water quality joint development act to provide local government flexibility.
Sponsors: Senate Committee on Water, Energy & Environment (originally sponsored by Senators Poulsen, Morton, Rockefeller, Honeyford, Kline, Mulliken and Oke).
Brief Summary of Engrossed Substitute Bill |
|
|
|
Hearing Date: 3/30/05
Staff: CeCe Clynch (786-7168).
Background:
Water Quality Joint Development Act
The Water Quality Joint Development Act (Act) was enacted in 1986 with the stated purpose "to
provide public bodies an additional means by which to provide for financing, development, and
operation of water pollution control facilities." The Legislature intended "that public bodies be
authorized to provide service from such facilities by means of service agreements with public or
private parties."
"Water pollution control facilities" are defined as facilities or systems, whether owned or
operated by a public body or for a public body, for the control, collection, and treatment of
sanitary sewage, storm water, residential wastes, commercial wastes, industrial wastes, and
agricultural wastes. Facilities covered under this Act do not include dams or water supply
systems.
Under the Act, local governments may contract with a public or private service provider to
design, finance, construct, own, operate, or maintain these facilities. Agreements may be for a
term not to exceed 40 years or the life of the facility, whichever is longer, and are renewable.
Payment obligations assumed by a public body pursuant to such a service agreement may be paid
from taxes, user fees, or other revenues pledged to the payment of these obligations.
Service agreements must comply with numerous procedural requirements set forth in the Act,
including requirements with respect to notice, requests for proposal (RFP), criteria by which
RFPs are to be judged, performance bonds and other security, public hearings, and appeals. A
service provider is required to demonstrate in its RFP that a public body's annual costs will be
lower under its proposal than they would be if the public body financed, constructed, owned,
operated, and maintained the facilities. The DOE must review and approve service agreements
before finalization to ensure compliance with water pollution laws.
Alternative Public Works Contracting Procedures
In 1994, the Legislature recognized that while the traditional process of awarding public works
contracts in lump sum to the lowest responsible bidder is a fair and objective method, there are
circumstances when alternative public works contracting procedures may best serve the public
interest. Large public bodies, including state agencies, the two major research universities, and
cities, counties, ports, hospital districts, school districts, and public utility districts of a certain
size, were authorized to utilize the design-build and the general contractor/construction manager
contracting procedures for public works contracting.
The design-build procedure contemplates a contract between a public body and another party in
which the party agrees to both design and build the facility, portion of the facility, or other item
specified in the contract. The general contractor/construction manager procedure includes a
general contractor/construction manager which the public body selects and with which the public
body has negotiated a maximum allowable construction cost to be guaranteed by the firm to
provide services during the design phase that include cost design considerations, value
engineering, scheduling, cost estimating, constructability, alternative construction options,
sequencing of work, and acting as the construction manager and general contractor during the
construction phase.
Unlike the Water Quality Joint Development Act, the provisions found in Chapter 39.10 RCW
are not limited to water pollution control facilities but may be utilized with respect to many
different public works. Another notable difference is that the alternative public works
contracting procedures set forth in Chapter 39.10 RCW are in almost all cases limited to
contracts signed before July 1, 2007 and all but one of the sections in Chapter 39.10 are repealed
effective July 1, 2007.
Summary of Bill:
The Water Quality Joint Development Act is revised in the following ways:
A similar provision is added to the Alternative Public Works Contracting Procedures allowing a
large public body to use those procedures or the ones found under the Water Quality Joint
Development Act in connection with procuring services related to water pollution control
facilities.
In the context of the powers and authority conferred on the DOE, language is added indicating:
(1) that the DOE may enter into contracts with municipalities and public corporations for the
purpose of assisting with the financing of design, as well as construction, of water pollution
control facilities; and, (2) that the DOE has such authority regardless of the particular
procurement laws which are utilized by the municipality or public corporation.
Finally, the repealer at the end of the chapter dealing with Alternative Public Works Contracting
Procedures is amended to reflect that changes were made in the 2003 as well as the 2005
legislative session.
Appropriation: None.
Fiscal Note: Requested on March 22, 2005.
Effective Date: The bill takes effect 90 days after adjournment of session in which bill is passed.