BILL REQ. #:  Z-0176.1 



_____________________________________________ 

SENATE BILL 5036
_____________________________________________
State of Washington59th Legislature2005 Regular Session

By Senators Fraser, Zarelli, Regala and Spanel; by request of Public Works Board

Read first time 01/10/2005.   Referred to Committee on Ways & Means.



     AN ACT Relating to authorization for projects recommended by the public works board; creating a new section; and declaring an emergency.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:

NEW SECTION.  Sec. 1   Pursuant to chapter 43.155 RCW, the following project loans recommended by the public works board are authorized to be made with funds appropriated from the public works assistance account:
     (1) Bainbridge Island--storm sewer project--construct a storm sewer waste management facility including bins for storage of asphalt, concrete, wood chips, rock, sand and gravel, and miscellaneous woody debris; and test remaining soil and remove contaminated soils from the Head of the Bay site . . . . . . . . . . . . $782,000
     (2) Bainbridge Island--sanitary sewer project--upgrade wastewater treatment plant by upgrading the following: Headworks, biosolids, oxidation ditch aeration basins, sludge holding basins, secondary clarification, and sludge pumping and effluent outfall . . . . . . . . . . . . $3,618,000
     (3) Battle Ground--sanitary sewer project--expand the capacity in the shared use facilities by performing the design engineering and construction for a parallel sewer line interceptor, 1 new transmission pump station, an influent pressure main, and treatment plant improvements to increase the capacity from 10.3 million gallons per day to 16 million gallons per day . . . . . . . . . . . . $10,000,000
     (4) Birchbay water and sewer district--sanitary sewer project--extend the existing sanitary sewer system constructing approximately 10,000 feet of gravity sewer mains, including manholes, side sewers to each lot, and other sewer appurtenances. The project will also include temporary erosion and sedimentation control measures and other public/private improvement restoration following sewer installation
. . . . . . . . . . . . $765,000
     (5) Blaine--sanitary sewer project--construct a wastewater pretreatment facility and a 700,000 gallon equalization storage facilities along and underneath Marine Drive to prevent raw sewage overflows into Drayton Harbor, construction of control structures required to operate and maintain facilities, and reconstruction of existing lift station number one . . . . . . . . . . . . $5,080,000
     (6) Brewster--sanitary sewer project--retrofit south lift station and dry well/wet well system will be converted to a submersible pump station, headworks structure will be enclosed, including electrical and ventilation systems, replacement of chlorine gas disinfection system with UV disinfection, construction of a plant water system, adding new effluent flow meter and automatic sampler, replacement of activated sludge pumps, retrofitting primary clarifier, installation of a new dewatering facility, electrical, and control features and appurtenances
. . . . . . . . . . . . $2,659,600
     (7) Carnation--sanitary sewer project--eliminate current septic tank/drainfield systems and replace them with a centralized sewer collection system that will connect directly to the treatment facility being built by King County, including approximately 26,000 feet of vacuum sewer collector pipes, 3,000 feet of force main, approximately 700 side sewers and the associated abandonment of septic tank/drainfield systems, relocation of 10,000 feet of water main, telemetry system for new sewer facilities, and a vacuum/pump station
. . . . . . . . . . . . $4,374,700
     (8) Castle Rock--sanitary sewer project--upgrade wastewater treatment plant by constructing a new treatment process, structures and equipment, new oxidation ditch, modernized headworks, disinfecting with ultraviolet, installation of a belt thickener, and press for solids and secondary clarifiers . . . . . . . . . . . . $655,000
     (9) Chinook water district--domestic water project--construct a new package water filter plant . . . . . . . . . . . . $1,425,000
     (10) College Place--domestic water project--construct a 1.5 million gallon water storage reservoir, install a booster station, approximately 7,100 feet of 16 inch water transmission mains, three pressure reducing valve stations, and a second booster station in the Regency Park package system, telemetry improvements, and associated appurtenances . . . . . . . . . . . . $2,975,000
     (11) Douglas county--storm sewer project--construction of a detention basin of approximately 35 acre feet, construction of an urban conveyance and water quality project that consists of construction of about 2,000 feet of closed conduit, 1,000 feet of open channel, and construction of a water quality treatment facility, and all appropriate appurtenances . . . . . . . . . . . . $2,835,600
     (12) Dupont--sanitary sewer project--replace approximately 6,600 feet of sanitary sewer line with manholes, 103 side sewers, and overlaying 4,200 feet of street. The city of DuPont will also purchase capacity from Pierce County allowing the transfer of flows for treatment to Pierce County . . . . . . . . . . . . $1,985,600
     (13) East Wenatchee water district--domestic water project--increase capacity and remedy leaking mains by replacing approximately one mile of 12 inch ductile iron transmission main . . . . . . . . . . . . $490,875
     (14) Eatonville--domestic water project--construct a membrane filtration system and use the existing disinfection system, install a booster pump station, additional well sources, basin modifications, and approximately 1,200 feet of transmission main to connect to the existing system . . . . . . . . . . . . $807,500
     (15) Edmonds--sanitary sewer project--lift station elimination and rehabilitation project includes elimination of lift station seven, demolish the facility and construct approximately 1,550 feet of gravity sewer line, and install a new line from current location of lift station seven to lift station eight. Replace lift station eight, including upsizing of the wet well and replacement of all mechanical and electrical equipment and replacement and upsizing of approximately 450 feet of force main . . . . . . . . . . . . $1,216,903
     (16) Enumclaw--sanitary sewer project--upgrade and expand the existing wastewater treatment plant by constructing a new headworks, install new extended aeration activated sludge basins, anaerobic/anoxic basins, and two additional secondary clarifiers. The city will also include construction of chemical facilities, enlarging laboratory area, sludge dewatering, and stabilization facilities and related appurtenances . . . . . . . . . . . . $9,750,000
     (17) Ephrata--sanitary sewer project--construction of approximately 2,400 feet of sanitary sewer main, 200 feet of side sewer pipe, eight manholes and appurtenances, and the rehabilitation of approximately one mile of access roadway in the port of Ephrata . . . . . . . . . . . . $289,000
     (18) Everett--sanitary sewer project--construct upgrades to the wastewater treatment plant that include: A headworks grit system, construction of two primary clarifiers, a new biofilter, new piping arrangements, modifications to the trickling filter pump station, installation of primary sludge grit removal equipment, sludge dispersion equipment, flow metering, new hypochlorite generation facilities, new scum collection and dewatering equipment, and minor upgrade of the north effluent pump station . . . . . . . . . . . . $10,000,000
     (19) Freeland water district--domestic water project--solve the source and storage needs by constructing a new reservoir, connection of the new well to the new reservoir, connection of the new reservoir to the system, rehabilitation of the existing well number one, and all appropriate appurtenances . . . . . . . . . . . . $308,030
     (20) Gig Harbor--sanitary sewer project--upgrade to the wastewater treatment plant to improve its efficiency and effectiveness. In addition, an outfall extension into Colvos Passage, including a diffuser will be constructed. Project will result in a higher quality effluent being discharged to Puget Sound . . . . . . . . . . . . $10,000,000
     (21) Goldendale--road project--reconstruct approximately 2,700 feet of East Collins Drive. This will include curb and gutters, storm drainage facilities, sewer line repair and replacement, water line replacement, and a 40 foot curb to curb road section consisting of two eleven foot travel lanes and two nine foot parking areas . . . . . . . . . . . . $827,316
     (22) Highland water district--domestic water project--construct a 0.5 million gallon steel water tank and foundation, appurtenances such as water lines and valves, access road, and other site improvements as needed . . . . . . . . . . . . $573,750
     (23) Ilwaco--sanitary sewer project--replace approximately 2,000 feet of sanitary sewer lines and 2,250 feet of storm sewer lines, including contributing laterals. In addition, installation of new manholes, catch basins, and other related improvements would be made as part of the project . . . . . . . . . . . . $774,000
     (24) Jefferson County public utility district 1--domestic water project--extend water system to service the entire Marrowstone Island. Replacing individual wells with a public water supply. This will include installation of approximately 150,000 feet of water mains with accoutrements, a new 300,000 gallon storage tank, and expansion of existing treatment facilities. This will ensure a consistent source of potable water for the residents . . . . . . . . . . . . $2,000,000
     (25) Jefferson County public utility district 1--sanitary sewer project--replace approximately 80 individual septic systems with a new community drainfield system, consisting of approximately 12 grinder pump stations, twin booster pump stations, two dosing tanks, and other components necessary to enable the system to function properly. Completion of this project will virtually eliminate the release of any untreated effluent into the wetland and Discovery Bay . . . . . . . . . . . . $948,924
     (26) Kennewick--domestic water project--upgrade the water treatment plant with installation of a new membrane filtration at the Columbia River plant and installation of an ultraviolet disinfection system at the Ranney collector number five. Other related improvements will be made to the system as part of the project. This project will bring the city into compliance with the department of health's ground water under the influence (GWI) requirements . . . . . . . . . . . . $10,000,000
     (27) King county water district No. 111--domestic water project--construct four water treatment facilities. Each facility will include chlorine generation systems, backwash recycling facilities, SCADA systems at each plant, and any other related activities necessary to complete the construction. This will enable the district to be in compliance with iron and manganese MCLs and eliminate the hazards associated with chlorine . . . . . . . . . . . . $1,255,428
     (28) King county water district No. 125--domestic water project--upgrade pressure zone 2 by installing two secondary source connections, including pressure-reducing valves, valves, piping, and appurtenances and approximately 150 feet of water main. The project will also include replacement of approximately 12,500 feet of undersized water main, including all valves, fittings, hydrants, and appurtenances and project area restoration as required . . . . . . . . . . . . $1,088,850
     (29) Lake Forest Park--sanitary sewer project--installation of a series of extensions to the city of Lake Forest Park's sanitary sewer system to provide service to residential areas currently not serviced. This will include construction of approximately 3.8 miles of sewer main extension including gravity sewer, pressure piping, service connections and side sewers, lift stations, grinder pump assemblies, surface restoration, temporary erosion and sedimentation control, and related work . . . . . . . . . . . . $4,656,000
     (30) Leavenworth--domestic water project--reconstruct old reservoir on existing site, including new structural walls, new roof, and related appurtenances. Project will also include installation of a SCADA monitoring/radio telemetry control system . . . . . . . . . . . . $1,400,000
     (31) LOTT wastewater alliance--sanitary sewer project--construct four secondary clarifier mechanisms, replacement of RAS pumps, secondary scum pumping improvements, and motorized actuators. Upgrades to equipment and mechanisms will enable LOTT to meet increasing loads at the Budd Inlet wastewater treatment plant and improve the effluent quality . . . . . . . . . . . . $4,278,404
     (32) Malaga water district--domestic water project--construct a new 52,000 gallon partially buried concrete reservoir and connecting piping and install security fencing around tank. This project will enable the district to ensure a continuous safe water supply to the homes and businesses in the area . . . . . . . . . . . . $161,500
     (33) Manchester water district--domestic water project--upgrade a wide range of the water system. Project will include installation of a SCADA system with all hardware, software, and backup equipment. Installation of a new flow meter at each wellhead and pump station. Distribution/transmission piping replacements and upgrades to the Mile Hill Road area, Yukon Harbor Drive and Southworth Drive. Installation of two interties in the South Street and Garfield Road area. Construction of two pressure-reducing stations located in the Beach Drive and Harper Hill areas . . . . . . . . . . . . $970,870
     (34) Mason county public utility district 1--domestic water project--source improvements and system rehabilitation to the newly acquired Arcadia Estates system. Project will include pump and controls for well number two, 24,000 gallon storage reservoir with draft fire hydrant, three booster pumps, two pressure tanks, pressure-reducing station, service meters, and three blow off assemblies. This will remove the red operating permit and ensure a safe and reliable source of potable water for the community . . . . . . . . . . . .
. . . . . . . . . . . . $95,950
     (35) Mason county public utility district 1--domestic water project--rehabilitate the source of supply at the newly acquired Twanoh Heights water system. This project will include rehabilitation of well number one, installation of two pumps, abandonment of well number two per department of ecology rules, service meters and air release valves. This project will allow the community to have a continuous, safe and reliable water source . . . . . . . . . . . . $172,900
     (36) Mason county public utility district 1--domestic water project--address system needs for the Madrona Beach water system by constructing a 11,500 gallon reservoir, booster station, site work/plumbing, service meters, and a source meter. This will enable the public utility district to comply with department of health requirements and remove a blue operating permit . . . . . . . . . . . . $171,000
     (37) Mason county public utility district 1--domestic water project--make improvements to the newly acquired Canal Beach water system. The improvements include drilling and testing a new well source, constructing a 20,000 gallon storage tank, piped system intertie, fire service line and hydrant, water services with new meters, and abandonment of existing well sources per department of ecology rules . . . . . . . . . . . . $171,712
     (38) Mason county public utility district 1--domestic water project--make improvements to the Minerva Terrace water system that will include drill and test well, integrate well into system, booster station with all appurtenances, 35,200 gallon reservoir, and a draft fire hydrant. This will enable the system to have the red operating permit to be lifted and comply with department of health rules . . . . . . . . . . . .
. . . . . . . . . . . . $217,550
     (39) Northeast Sammamish sewer/water district--domestic water project--construct a new water treatment plant, new 0.5 million gallon reservoir and pump station, new transmission water main, and new distribution main and associated minor improvements. The district will then be able to meet the federal arsenic level regulations and ensure a safe source of potable water for the community . . . . . . . . . . . . $4,154,970
     (40) Northshore utility district--sanitary sewer project--install approximately 2,445 feet of gravity sewer main, manholes, connection to the sanitary sewer system, and related restoration and appurtenances. In addition, the district will replace approximately 2,400 feet of asbestos concrete water mains. This will resolve the negative environmental and health impacts of the failing septic systems in the area . . . . . . . . . . . . $814,634
     (41) Northshore utility district--sanitary sewer project--install approximately 300 feet of gravity sewer main, manholes, connection to the sanitary sewer system, and related restoration and appurtenances. In addition, the district will replace approximately 300 feet of asbestos concrete water mains. This will resolve the negative environmental and health impacts of the failing septic systems in the area . . . . . . . . . . . . $113,334
     (42) Oak Harbor--domestic water project--replace existing water transmission mains being destroyed due to a highway project. The project includes construction of approximately 4,000 feet of transmission mains along Highway 20 just south of Deception Pass state park. Project will meet the city's foreseeable water requirements and provide sufficient capacity for the Naval Air Station--Whidbey . . . . . . . . . . . .
. . . . . . . . . . . . $834,700
     (43) Orchard Avenue irrigation district number 6--domestic water project--install approximately 19,100 feet of PVC pipe. Approximately 210 buried meter boxes, reconnect approximately 400 existing services, and all required valves and other fittings. Project will eliminate public health concern over potential lead contamination from lead joint pipe . . . . . . . . . . . . $1,066,800
     (44) Pierce County--road project--widen, reconstruct, and overlay the intersection of Canyon Road E and 176th Street E, which includes additional travel lanes in each direction and left and right turn lanes at the intersection, a new traffic signal system, traffic signal interconnect system, street lights, median, curb and gutter, concrete sidewalks, landscaping, undergrounding of utilities, storm drainage conveyance, storage, and treatment facilities. Project will increase carrying capacity and allow for economic development . . . . . . . . . . . . $2,942,000
     (45) Pullman--sanitary sewer project--construct a new variable volume digester at the wastewater treatment plant, with an approximate capacity of 350,000 gallons. The work includes site preparation and construction of the digester, necessary piping modifications, and modifications to the existing plant control system. Project will enable the city to meet the environmental protection agency's SRT requirements . . . . . . . . . . . . $1,912,000
     (46) Pullman--domestic water project--construct a well to replace well number 3. Included in the project will be the drilling of the replacement well, well pump, motor, controls, disinfection equipment, fluoride injection equipment, a swell and chemical storage house, connection of transmission lines, and other related miscellaneous items and site work . . . . . . . . . . . . $850,000
     (47) Ridgefield--sanitary sewer project--construct a new pump station, install approximately 3,000 feet of force main, which will discharge directly into the treatment plant, and construct approximately 3,000 feet of gravity interceptor sewer. This project will enable the city to open up service to an area that is currently not served and allow for economic development . . . . . . . . . . . . $1,718,000
     (48) Ritzville--domestic water project--increase the city's water capacity from 1,200 to 2,000 gallons per minute by drilling a new well. This will also include installing the necessary pump and connections to the storage tank and construct a well house to protect the equipment
. . . . . . . . . . . . $845,000
     (49) Ronald wastewater district--sanitary sewer project--sewer extension to unsewered areas includes installation of approximately 2,700 feet PVC sewer main and approximately 2,000 feet PVC sewers in three separate areas of the district. All associated appurtenances will also be instilled, such as manholes and side sewer stubs. Approximately 1,100 sewer trunk main will be repaired. The streets and other public improvements that are disturbed during construction will be restored to city of Shoreline's standards . . . . . . . . . . . . $1,021,700
     (50) Samish water district--sanitary sewer project--upgrade its system by replacing pumps and controls at six sewage pump stations, replace controls at one sewage pump station, upgrade SCADA, and replace inline valves on existing sewer force main. This will ensure that the system operates within regulations . . . . . . . . . . . . $1,083,000
     (51) Seattle--storm sewer project--increase capacity of the drainage system by installing approximately 1,760 feet of storm drain along South Trenton Street, 3rd Avenue South, and 4th Avenue South. Install 2,380 feet of storm drain along South Director Street and 7th Avenue South. The last part of the project will construct a new storm drain system on 8th Avenue South. These new drainage pipes will reduce flows to the combined sewer system and reduce the number of overflows
. . . . . . . . . . . . $3,400,000
     (52) Seattle--storm sewer project--upgrade two culverts in the lower reaches of Taylor Creek to remove fish barriers and construct a fish ladder to improve fish passage and control sediment transportation. Other related improvements will be made to the area as part of the project . . . . . . . . . . . . $450,500
     (53) Seattle--storm sewer project--construct two ponds that will include a 4 acre feet sediment collection pond, 2 acre feet decant pond, 750 feet of access road, 750 of decant piping, a gravel pump and its housing and controls, and 4,000 feet of landscaping around the new ponds. Additional related upgrades will be done to complete the project . . . . . . . . . . . . $1,832,600
     (54) Skyway water/sewer district--domestic water project--replace and upsize the supply meter from the city of Seattle system and replace approximately 6,350 feet of asbestos water supply line. In addition, four new pressure zones interties will be installed to improve flow between pressure zones within the water/sewer district . . . . . . . . . . . . $1,130,526
     (55) Spokane--domestic water project--replace about 3,500 feet of riveted steel water transmission mains with ductile iron pipe. In addition, project will include all valves, connections, blowoffs, air valves, railroad crossing, and pavement restoration and traffic control
. . . . . . . . . . . . $3,453,975
     (56) Spokane--domestic water project--construct a 2 million gallon elevated steel tank with an accompanying booster station. This will include all piping, valves, telemetry, instrumentation, excavation and site preparation including landscaping, paving, and fencing . . . . . . . . . . . .
. . . . . . . . . . . . $2,232,950
     (57) Spokane county--road project--construct a total of 8.3 miles of roadway from Havana Street to Forker Road and from Forker Road from Bigelow Gulch Road to Wellesley Road. The construction will provide for expanding the road to four traveled lanes plus eight foot shoulders to improve safety and traffic capacity. A center turn lane will be added at locations where vehicles routinely make left turns. Eight foot shoulders will be added to provide for safety of pedestrians and bicycles . . . . . . . . . . . . $10,000,000
     (58) Stanwood--domestic water project--construct a 1 million gallon elevated water tank, water main, appurtenances, and equipment necessary to connect the new water tank to the existing system. Project will also install telemetry and control systems compatible with existing system, construction of a Cedarhome booster pump station for filling the Cedarhome reservoir, and improvements to the sites such as grading, fencing, and landscaping . . . . . . . . . . . . $2,481,620
     (59) Stevens County--solid waste project--expand municipal solid waste site by construction of an 11 acre lateral expansion, environmentally protective landfill lining and leachate collection system and construction of ancillary facilities such as perimeter roads. Leachate facilities will consist of piping, collection and conveyance facilities . . . . . . . . . . . . $2,600,000
     (60) Union Gap--sanitary sewer project--construct approximately 3,400 feet of sewer interceptor and 1,800 feet of sewer laterals in conjunction with new roadways in the Valley Mall Boulevard area . . . . . . . . . . . .
. . . . . . . . . . . . $676,429
     (61) Washougal--sanitary sewer project--construct a redundant secondary clarifier adjacent to existing secondary clarifier, including piping connections to the existing clarifier distribution structure, scum pump station, and RAS/WAS pump room. Additional work will include RAS/WAS pump room modifications for installation of dedicated return and waste-activated sludge pumps, sidewalks, and site grading and all necessary electrical hardware and SCADA control modifications. Project will enable the city to meet their national pollution discharge elimination system permit requirements . . . . . . . . . . . . $794,000
     (62) West Richland--sanitary sewer project--increase capacity by constructing a one million gallons per day biolac wastewater treatment facility, approximately 2,700 feet of sanitary sewer pipe, lift station, miscellaneous roadway patching, and site restoration. If additional funds are available, improvements to the facilities outfall structure will be designed along with facilities for sludge handling from the sewer maintenance program. Project will enable the city to meet their national pollution discharge elimination system permit requirements . . . . . . . . . . . . $4,000,000
     (63) Witworth water district 2--domestic water project--The district will solve the area problems by installing approximately 27,090 of water lines together with valves and appurtenances, connection to the existing system, 15 hydrants, pavement repair, and other surface restoration. In addition, installation of a two million gallon steel reservoir and a 1,700 gallons per minute booster pump station and various piping, appurtenances, pumps, controls, security, electrical, and connection to existing system . . . . . . . . . . . . $2,502,300
     (64) Yakima--sanitary sewer project--The project will be done in two phases. Phase I will install approximately 6,640 feet of sewer main trunk line in River Road from North 16th Avenue to North 40th Avenue. Phase II will install 5,500 feet of sewer main trunk line in River Road from North 6th Avenue to North 16th Avenue if public works trust fund loan funds remain and private development proceeds. The project will help prevent further loss of major employers by providing the transportation and utility infrastructure necessary to maintain competitive operations . . . . . . . . . . . . $2,307,000

NEW SECTION.  Sec. 2   This act is necessary for the immediate preservation of the public peace, health, or safety, or support of the state government and its existing public institutions, and takes effect immediately.

--- END ---