HOUSE BILL REPORT
HB 2219
This analysis was prepared by non-partisan legislative staff for the use of legislative members in
their deliberations. This analysis is not a part of the legislation nor does it constitute a
statement of legislative intent.
As Reported by House Committee On:
Agriculture & Natural Resources
Title: An act relating to forest practices regulations applicable to small forest landowners.
Brief Description: Regarding forest practices regulations that apply to small forest landowners.
Sponsors: Representatives Orcutt, B. Sullivan, Kessler and Kretz.
Brief History:
Agriculture & Natural Resources: 2/22/07, 2/26/07 [DPS].
Brief Summary of Substitute Bill |
|
|
|
|
HOUSE COMMITTEE ON AGRICULTURE & NATURAL RESOURCES
Majority Report: The substitute bill be substituted therefor and the substitute bill do pass. Signed by 15 members: Representatives B. Sullivan, Chair; Blake, Vice Chair; Kretz, Ranking Minority Member; Warnick, Assistant Ranking Minority Member; Dickerson, Eickmeyer, Grant, Hailey, Kagi, Lantz, McCoy, Newhouse, Orcutt, Strow and VanDeWege.
Staff: Jason Callahan (786-7117).
Background:
The Forest Riparian Easement Program
The Forest Riparian Easement (FRE) Program is a program managed by the Department of
Natural Resources' (DNR) Small Forest Landowner Office (SFLO) to acquire 50-year
easements along riparian and other sensitive aquatic areas from small forest landowners that
are willing to sell or donate easements to the state. The DNR is authorized to purchase
easements from small forest landowners and hold the easements in the name of the state. The
easements are restrictive only, and allow all landowner activities except as necessary to
protect the riparian functions of the habitat for the term of the easement.
Easements entered into through the FRE Program are intended to represent 50 percent of the
value of the unharvested trees, plus participation compliance costs. Once an FRE contract is
executed, the DNR is required to reimburse the landowner for the actual costs involved with
the establishment of streamside buffers and timber marking.
The value of the easement is determined by the DNR based on the fair market value of the
timber volume covered by the easement. This calculation is made by the DNR after it
conducts a timber cruise of 100 percent of the proposed easement. The data gathered in the
timber cruise is then applied to a stumpage value table to calculate the fair market value.
Value is calculated only on qualifying timber. This is timber that is located within a
commercially reasonable harvest unit that cannot be harvested because of regulatory
limitations.
Exceptions to Riparian Buffers
Although the state's Forest Practice Rules generally have specific restrictions on the amount
of harvest allowed near streams and creeks, there is an exemption available from these
restrictions for certain landowners. Parcels that are 20 contiguous acres or less are exempt
from the modern riparian buffers rule, as long as the owner of the parcel does not own a
cumulative total of more than 80 acres. Instead, these landowners can opt to either follow the
Forest Practice Rules in place prior to 1999, or work with the DNR to establish an alternative
management plan for the riparian portion of the harvest area.
Summary of Substitute Bill:
The Forest Riparian Easement Program
The unharvested trees eligible for coverage in the FRE Program are specified to include trees
that were not harvested due to their location on unstable slopes, and are not limited to trees
left unharvested due to their location in a riparian buffer area. In addition, participation in the
FRE Program is expanded to include landowners who qualify for the 20-acre exemption to
the current Forest Practices Rules, but who chooses to abide by the standard Forest Practices
Rules as though no exception existed.
The SFLO is required to determine the compensation for all qualifying timber to be offered to
a landowner for an easement as soon as possible following the landowner's application for the
FRE Program. However, the determination is to serve only as an appraisal, and no duty to
present an actual offer is created until an appropriation exists to fund the offer. In order to
provide timely estimates, the SFLO is directed to use any funding provided to it from the
state's Capital Construction Budget to complete the compensation estimates and execute the
resulting FRE Program contracts for all pending applications during the 2007-2009 fiscal
biennium. In addition, the Forests Practices Board is directed to amend an existing
administrative rule that requires the SFLO to send a landowner a notice of compensation
within 60 days of a completed timber cruise.
The compensation that the DNR must reimburse FRE Program applicants is expressly made
to include the cost of hiring a geotechnologist to complete required studies or reports.
Substitute Bill Compared to Original Bill:
The original bill expanded the 20-acre exemption to the current Forest Practices Rules, did
not allow landowners eligible for the 20-acre exemption to participate in the FRE Program,
required all FRE Program compensation estimates to be completed within 60 days of
application, and did not require the SFLO or Forest Practices Board to take any specific
actions.
Appropriation: None.
Fiscal Note: Requested on February 13, 2007. New fiscal note requested on February 23, 2007
Effective Date of Substitute Bill: The bill takes effect 90 days after adjournment of session in which bill is passed.
Staff Summary of Public Testimony:
(In support) This is a clean-up bill addressing loose ends in the FRE Program. Language is
being simplified and clarified. A healthy and functioning FRE Program keeps small forest
landowners, and the land they own, in forestry, which benefits both people and critters.
The FRE Program currently does not do a good job of capturing the actual value of timber
that is left unharvested by a landowner because the compensation value is not determined
until sometime after the actual harvest occurs. This makes the landowner vulnerable to not
being compensated for trees that are lost due to wind storms or ice damage. The estimate of
compensation should be done before the money to enter into an easement contract is
available.
The current Forest Practices Rules are designed, in part, to protect fish habitat. One aspect of
that protection is limitations on timber harvest on unstable slopes. This limitation is in place
to protect streams from siltation, and if a landowner cannot harvest on a slope in order to
protect fish habitat, he or she should be eligible to participate in the FRE Program.
If the intent of the law is for a landowner to be reimbursed for the costs of gathering
information required of an FRE Program applicant, and that process requires an analysis
conducted by a geotechnologist, then the expense of hiring a geotechnologist should be a
reimbursable expense. Technical information is important, but can be expensive to obtain.
The intent of the current 20-acre exemption in the Forest Practices Rules is clarified by
adding the word "forested" to the description of the parcels covered by the exemption.
(With concerns) Conducting estimates for FRE Program applicants at the time of application
provides more certainty to the landowner, but the sooner the estimate is prepared and the
more detailed that it is, the more staffing commitment is required.
The current Forest Practices Rules have received assurances from the federal government that
the Endangered Species Act and the Clean Water Act are not being violated by forest
practices in the state. The federal government showed some skepticism about the 20-acre
exemption as the assurances process moved forward, and changing the language in that
exemption may destabilize the federal assurances granted to the entire suite of Forest
Practices Rules.
(Opposed) None.
Persons Testifying: (In support) Representative Orcutt, prime sponsor; and Ken Miller,
Washington Farm Forestry Association.
(With concerns) Leonard Young, Department of Natural Resources; and Melodie Selby,
Department of Natural Resources.