FINAL BILL REPORT
SHB 1037
C 325 L 07
Synopsis as Enacted
Brief Description: Regarding electrical transmission.
Sponsors: By House Committee on Technology, Energy & Communications (originally sponsored by Representatives Morris, Hudgins, Moeller and B. Sullivan).
House Committee on Technology, Energy & Communications
Senate Committee on Water, Energy & Telecommunications
Background:
Energy Facility Site Evaluation Council.
The Energy Facility Site Evaluation Council (EFSEC) is the one-stop permitting and
certificating authority for the siting of major energy facilities in Washington. The EFSEC's
jurisdiction does not extend to general electrical transmission lines. It does, however, have
jurisdiction over (1) new transmission lines that operate in excess of 115 kilovolts that are
necessary to connect a power plant to the region's power grid, and (2) electrical transmission
facilities in "national interest electric transmission corridors" as designated by the U.S.
Secretary of Energy.
Federal Electrical Transmission Study.
In August 2006, the Department of Energy issued the first National Electric Transmission
Congestion Study (Study), which identified three classes of congestion: (1) areas where
near-term action is needed, called "critical congestion areas;" (2) areas where additional
analysis and information appear to be needed, called "congestion areas of concern;" and (3)
areas where congestion would become a problem if new generation were to be developed
without considering new transmission, called "conditional congestion areas."
Summary:
Electric Transmission Facilities Opt-in Provisions.
A person may choose to use the EFSEC siting process when developing electric transmission
facilities of at least 115,000 volts, and the facilities are located in a completely new corridor
in more than one jurisdiction that has promulgated land use plans or zoning ordinances.
A person may choose to use the EFSEC siting process when developing electric transmission
facilities in excess of 115,000 volts, and the facilities are located outside of a national interest
electric transmission corridor and are not new corridors.
Electrical Transmission Facilities Preapplication Process.
A person considering applying for a site certification agreement for any transmission facility
may initiate a preapplication process. The preapplication process is initiated by written
correspondence from the preapplicant to the EFSEC, and includes the process adopted by the
EFSEC for consulting with the preapplicant and with cities, towns, and counties prior to
accepting applications for transmission facilities.
The EFSEC must consider and may recommend certification of electrical transmission
facilities in corridors by affected cities, towns, or counties where:
In the absence of a corridor designation as part of land use plans and zoning maps,
preapplicants are required to negotiate for a reasonable time with affected cities, towns, and
counties to attempt to reach agreement about a corridor plan. If no corridor plan is agreed to
by the applicant and cities, towns, and counties, the applicant shall propose a recommended
corridor and electrical transmission facilities to be included within the proposed corridor.
The EFSEC must develop and adopt rules to govern the process. Preapplicants are required to
pay the EFSEC a fee of $10,000 to be applied to the cost of the process.
National Interest Electric Transmission Corridors.
The EFSEC jurisdiction over national interest electric transmission corridors applies to
electric transmission lines of at least 115,000 volts.
A legislative finding that transmission lines at or below 115,000 volts have historically been
regulated by local government is repealed.
Definition.
The definition for "site" is amended to include alternative energy resource and electrical
transmission facility.
Votes on Final Passage:
House 88 3
Senate 48 0 (Senate amended)
House 98 0 (House concurred)
Effective: July 22, 2007