Washington State House of Representatives Office of Program Research |
BILL ANALYSIS |
Technology, Energy & Communications Committee | |
HB 2156
This analysis was prepared by non-partisan legislative staff for the use of legislative members in
their deliberations. This analysis is not a part of the legislation nor does it constitute a
statement of legislative intent.
Brief Description: Regarding carbon dioxide mitigation.
Sponsors: Representative Morris.
Brief Summary of Bill |
|
Hearing Date: 2/13/07
Staff: Scott Richards (786-7156).
Background:
In 2004, the Legislature established a policy to mitigate carbon dioxide (CO2) emissions from
fossil-fueled thermal power plants with a generating capacity of 25 megawatts or more. These
thermal power plants are required to mitigation for 20 percent of the CO2 emissions produced by
the plant over a period of 30 years. This requirement applies to new power plants seeking site
certification through the Energy Facility Site Evaluation Council (EFSEC) or an order of
approval from the Department of Ecology (DOE) after July 1, 2004, and existing plants that
increase the production of CO2 emissions by 15 percent or more.
The CO2 from these thermal power plants may be mitigated: (1) by making a payment to an
independent qualified organization; (2) by direct purchase of permanent carbon credits; or (3) by
direct investment in CO2 mitigation projects. The EFSEC is to maintain a list of independent
qualified organizations.
Payment to a Third Party Option: The rate that must be paid per ton for those CO2 emissions
that must be mitigated is $1.60. This rate is subject to adjustment. Payment may be made in a
lump sum no later than 60 days prior to the start of construction or in partial payments over five
years. Partial payments are paid in equal annual amounts and are also subject to adjustment.
The EFSEC may adjust the per ton rate every two years and any increase or decrease may not
exceed 50 percent of the current rate. The DOE or local air pollution control authorities must
use the adjusted rate established by the EFSEC.
Carbon Credit Option: Credits must come from real, permanent, verifiable CO2 mitigation not
otherwise required or used for other CO2 mitigation projects.
Direct Investment Option: Mitigation projects must be approved by the EFSEC, the DOE, or a
local air pollution control authority and must be included in the site certification agreement or
the order of approval. Direct investments are limited in amount to no more than the cost of a
lump sum payment option. Implementation is monitored by an independent entity for applicants
under the jurisdiction of the EFSEC, and by the DOE or a local air pollution control authority for
applicants not under the jurisdiction of the EFSEC, except for carbon credits.
Mitigation projects under both the payment to a third party option and direct investment option
must: (1) provide a reasonable certainty that the performance requirements will be achieved; (2)
be implemented after July 1, 2004; (3) minimize the extent to which external events can reduce
the amount of CO2 offset; (4) accomplish CO2 reductions that would not otherwise take place;
and (5) provide for mitigation of an appropriate duration.
Summary of Bill:
Any load-serving utility that enters into a long-term financial commitment for baseload
generation located outside the borders of the state is required to mitigate 20 percent of the total
carbon dioxide (CO2) emissions produced by the fossil-fueled thermal electric power plant or
plants over the period of the commitment. A "load serving utility" means any consumer-owned
or investor-owned utility serving electricity to end use customers in the state. The load-serving
utility is required to develop a CO2 mitigation plan detailing how the utility plans to mitigate
CO2 emissions.
A "long-term financial commitment" means either: (1) a new ownership investment in baseload
generation; or (2) a new or renewed contract with a term of five or more years, which includes
procurement of baseload generation. "Baseload generation" means electricity generation from a
fossil-fueled power plant that is designed and intended to provide electricity at an annualized
plant capacity factor of at least 60 percent. For a load-serving utility, "total CO2 emissions"
means the amount of CO2 emitted by a fossil-fueled thermal electric power plant over the
duration of a long-term financial commitment.
Carbon Dioxide (CO2) Mitigation
In mitigating CO2 emissions, the load-serving utility may choose one or a combination of the
following CO2 mitigation options: (1) payment to a third party to provide mitigation; (2) direct
purchase of permanent carbon credits; or (3) investment in load-serving utility-controlled CO2
mitigation projects, including combined heat and power (cogeneration).
Payment to Third Party
If the load-serving utility chooses to pay a third party, the mitigation rate shall be $1.60 per
metric ton of CO2 mitigated. Payment may be made in a lump sum no later than 60 days prior to
the start of a long-term commitment. As an alternative to a one-time payment, the load-serving
utility may make partial payments over five years. Partial payments are paid in equal annual
amounts and are also subject to adjustment.
The EFSEC may by rule adjust the rate per ton biennially as long as any increase or decrease
does not exceed 50 percent of the current rate. In adjusting the mitigation rate, EFSEC must
consider the current market price of a ton of CO2.
Direct Investment
For load-serving utilities, direct investments must be implemented through mitigation projects
conducted directly by, or under the control of, the load-serving utility. For an investor-owned
utility, mitigation projects must be approved by the Washington Utilities and Transportation
Commission (WUTC). For a consumer-owned utility, a mitigation project must be approved by
the governing board of the utility. Direct investments are limited in amount to no more than the
cost of a lump sum payment option.
Mitigation projects must be fully in place within a reasonable time after the start of the long-term
financial commitment. The load-serving utility may not use more than 20 percent of the total
funds for the selection, monitoring, and evaluation of mitigation projects and the management
and enforcement of contracts.
For investor-owned utilities, the implementation of projects will be monitored by the WUTC.
For consumer-owned utilities, the implementation projects, will be monitored by the governing
board of the utility. No more than 20 percent of the funds may be used for selection, monitoring,
and evaluation of the mitigation project.
The WUTC shall develop rules to carry out its responsibilities.
Appropriation: None.
Fiscal Note: Requested on February 12, 2007.
Effective Date: The bill takes effect 90 days after adjournment of session in which bill is passed.