HB 2785 - DIGEST |
Provides if any person or government agency fails to follow the requirements of obtaining hydraulic project approval under chapter 77.55 RCW, or fails to carry out any of the requirements or conditions of a hydraulic project approval issued under chapter 77.55 RCW, the department may issue an order to that person or government agency. The order may require the person or government agency to stop work on any or all of the activities subject to the hydraulic project approval, to correct or to restore the nonconforming site, or to both stop work and to correct or to restore the nonconforming site. |