HB 1499 -
By Representative Eddy
ADOPTED 03/05/2009
Strike everything after the enacting clause and insert the following:
"NEW SECTION. Sec. 1 A new section is added to chapter 80.04 RCW
to read as follows:
(1) If a public agency is planning a project that may require a
utility facility operator to relocate its utility facilities in or
along the right-of-way, the public agency shall notify each affected
utility facility operator as soon as is practicable and include the
affected utility facility operator in a preliminary design meeting
during the design phase. The notice must provide information
concerning: (a) The proposed project design; and (b) proposed dates of
any required utility facility relocations.
(2) During the preliminary design meeting, public agencies and
affected utility facility operators shall review the impact of any
proposed utility facility relocation and make reasonable efforts to
avoid or minimize:
(a) Factors which could cause delay of the project;
(b) Relocation of existing utility facilities and associated costs;
and
(c) Costs to public agencies.
(3) This section does not preempt specific provisions in existing
franchises, permits, or contracts between public agencies and utility
facility operators.
(4) This section does not apply to the relocation of utility
facilities in the event of an unforeseen emergency that creates an
immediate threat to the public safety, health, or welfare.
(5) The definitions in this subsection apply throughout this
section unless the context clearly requires otherwise.
(a) "Public agency" means the state, county, city, or any political
subdivision of the state, which maintains ownership or control of the
right-of-way.
(b) "Utility facility" means any privately, publicly, or
cooperatively owned equipment, facilities, or system for producing,
transmitting, or distributing communications, cable television, power,
electricity, gas, hazardous liquids, water, steam, or waste."
Correct the title.
EFFECT: Strikes the provisions of the underlying bill. Requires
public agencies to notify an affected utility as soon as practicable if
a project in the right-of-way may require relocation of utility
facilities. Requires public agencies to include an affected utility in
a preliminary design meeting. Provides that public agencies and
affected utilities must make reasonable efforts to avoid or minimize:
(1) Factors that could cause delay of the project; (2) relocation of
utility facilities and associated costs; and (3) costs to public
agencies.
Specifies that these notice provisions do not apply to the
relocation of utility facilities in the event of an emergency, nor do
they preempt existing agreements between public agencies and utilities.