BILL REQ. #: S-0301.1
State of Washington | 63rd Legislature | 2013 Regular Session |
Read first time 01/25/13. Referred to Committee on Governmental Operations.
AN ACT Relating to modifying the criteria for public works assistance; amending RCW 43.155.070; and creating new sections.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
NEW SECTION. Sec. 1 The legislature finds that it is in the best
interest of the state to encourage the use of low-cost alternatives to
traditional construction methods, including the use of pipe bursting
technology for sewer, storm water, and water delivery infrastructure.
The legislature intends to encourage the use of these alternatives
through the public works assistance account by giving preference to
projects that utilize low-cost alternatives to traditional
construction.
NEW SECTION. Sec. 2 By December 31, 2013, the public works board
shall report to the legislature on the board's plans and progress in
implementing this act, including changes to administrative rules and
specific criteria developed by the board. By December 31, 2014, the
public works board shall report to the legislature regarding compliance
with this act, including the number of projects identified and given
preference for utilizing low-cost alternatives to construction and the
cost savings from those projects.
Sec. 3 RCW 43.155.070 and 2012 c 196 s 9 are each amended to read
as follows:
(1) To qualify for loans or pledges under this chapter the board
must determine that a local government meets all of the following
conditions:
(a) The city or county must be imposing a tax under chapter 82.46
RCW at a rate of at least one-quarter of one percent;
(b) The local government must have developed a capital facility
plan; and
(c) The local government must be using all local revenue sources
which are reasonably available for funding public works, taking into
consideration local employment and economic factors.
(2) Except where necessary to address a public health need or
substantial environmental degradation, a county, city, or town planning
under RCW 36.70A.040 must have adopted a comprehensive plan, including
a capital facilities plan element, and development regulations as
required by RCW 36.70A.040. This subsection does not require any
county, city, or town planning under RCW 36.70A.040 to adopt a
comprehensive plan or development regulations before requesting or
receiving a loan or loan guarantee under this chapter if such request
is made before the expiration of the time periods specified in RCW
36.70A.040. A county, city, or town planning under RCW 36.70A.040
which has not adopted a comprehensive plan and development regulations
within the time periods specified in RCW 36.70A.040 is not prohibited
from receiving a loan or loan guarantee under this chapter if the
comprehensive plan and development regulations are adopted as required
by RCW 36.70A.040 before submitting a request for a loan or loan
guarantee.
(3) In considering awarding loans for public facilities to special
districts requesting funding for a proposed facility located in a
county, city, or town planning under RCW 36.70A.040, the board must
consider whether the county, city, or town planning under RCW
36.70A.040 in whose planning jurisdiction the proposed facility is
located has adopted a comprehensive plan and development regulations as
required by RCW 36.70A.040.
(4) The board must develop a priority process for public works
projects as provided in this section. The intent of the priority
process is to maximize the value of public works projects accomplished
with assistance under this chapter. The board must attempt to
((assure)) ensure a geographical balance in assigning priorities to
projects. The board must consider at least the following factors in
assigning a priority to a project:
(a) Whether the local government receiving assistance has
experienced severe fiscal distress resulting from natural disaster or
emergency public works needs;
(b) Except as otherwise conditioned by RCW 43.155.110, whether the
entity receiving assistance is a Puget Sound partner, as defined in RCW
90.71.010;
(c) Whether the project is referenced in the action agenda
developed by the Puget Sound partnership under RCW 90.71.310;
(d) Whether the project is critical in nature and would affect the
health and safety of a great number of citizens;
(e) Whether the applicant's permitting process has been certified
as streamlined by the office of regulatory assistance;
(f) Whether the applicant has developed and adhered to guidelines
regarding its permitting process for those applying for development
permits consistent with section 1(2), chapter 231, Laws of 2007;
(g) The cost of the project compared to the size of the local
government and amount of loan money available;
(h) The number of communities served by or funding the project;
(i) Whether the project is located in an area of high unemployment,
compared to the average state unemployment;
(j) Whether the project is the acquisition, expansion, improvement,
or renovation by a local government of a public water system that is in
violation of health and safety standards, including the cost of
extending existing service to such a system;
(k) Except as otherwise conditioned by RCW 43.155.120, and
effective one calendar year following the development of model
evergreen community management plans and ordinances under RCW
35.105.050, whether the entity receiving assistance has been
recognized, and what gradation of recognition was received, in the
evergreen community recognition program created in RCW 35.105.030;
(l) The relative benefit of the project to the community,
considering the present level of economic activity in the community and
the existing local capacity to increase local economic activity in
communities that have low economic growth; ((and))
(m) Whether the project includes low-cost alternatives to
traditional construction techniques, including the use of pipe bursting
technology in a project requiring the replacement of sewer, storm
water, and water delivery infrastructure; and
(n) Other criteria that the board considers advisable.
(5) Existing debt or financial obligations of local governments may
not be refinanced under this chapter. Each local government applicant
must provide documentation of attempts to secure additional local or
other sources of funding for each public works project for which
financial assistance is sought under this chapter.
(6) Before November 1st of each even-numbered year, the board must
develop and submit to the appropriate fiscal committees of the senate
and house of representatives a description of the loans made under RCW
43.155.065, 43.155.068, and subsection (9) of this section during the
preceding fiscal year and a prioritized list of projects which are
recommended for funding by the legislature, including one copy to the
staff of each of the committees. The list must include, but not be
limited to, a description of each project and recommended financing,
the terms and conditions of the loan or financial guarantee, the local
government jurisdiction and unemployment rate, demonstration of the
jurisdiction's critical need for the project and documentation of local
funds being used to finance the public works project. The list must
also include measures of fiscal capacity for each jurisdiction
recommended for financial assistance, compared to authorized limits and
state averages, including local government sales taxes; real estate
excise taxes; property taxes; and charges for or taxes on sewerage,
water, garbage, and other utilities.
(7) The board may not sign contracts or otherwise financially
obligate funds from the public works assistance account before the
legislature has appropriated funds for a specific list of public works
projects. The legislature may remove projects from the list
recommended by the board. The legislature may not change the order of
the priorities recommended for funding by the board.
(8) Subsection (7) of this section does not apply to loans made
under RCW 43.155.065, 43.155.068, and subsection (9) of this section.
(9) Loans made for the purpose of capital facilities plans are
exempted from subsection (7) of this section.
(10) To qualify for loans or pledges for solid waste or recycling
facilities under this chapter, a city or county must demonstrate that
the solid waste or recycling facility is consistent with and necessary
to implement the comprehensive solid waste management plan adopted by
the city or county under chapter 70.95 RCW.
(11) After January 1, 2010, any project designed to address the
effects of storm water or wastewater on Puget Sound may be funded under
this section only if the project is not in conflict with the action
agenda developed by the Puget Sound partnership under RCW 90.71.310.