Washington State

House of Representatives

Office of Program Research

BILL

ANALYSIS

Environment Committee

HB 1571

This analysis was prepared by non-partisan legislative staff for the use of legislative members in their deliberations. This analysis is not a part of the legislation nor does it constitute a statement of legislative intent.

Brief Description: Concerning paint stewardship.

Sponsors: Representatives Peterson, Goodman, Fitzgibbon, McBride, Pollet, Robinson, Stanford, S. Hunt and Riccelli.

Brief Summary of Bill

  • Requires producers of architectural paint to participate in a stewardship program approved by the Department of Ecology to manage the end-of-life disposition of leftover paint.

  • Prohibits retailers from selling the architectural paint of producers who do not participate in an approved stewardship program.

Hearing Date: 2/5/15

Staff: Jacob Lipson (786-7196).

Background:

Households and businesses use paints for a variety of purposes, including as a way to add color or preservative qualities to the interior and exterior of buildings. Paint may be characterized as either oil-based paint (also called solvent-based paint) or latex-based paint (also called acrylic or water-based paint), depending on the type of liquid solvent that contains the paint's dissolved coloring pigments. Options for the management of leftover architectural paints may include reuse, recycling, use as an energy source, or disposal through solid waste management streams.

Under waste management regulations in Washington, the collection and disposal requirements associated with leftover paint depend on the size of the entity generating the leftover waste. Households and certain small-quantity generators that generate less than 220 pounds of dangerous wastes per month are exempt from managing their leftover architectural paints as dangerous wastes. The dangerous wastes generated by households and small quantity generators are referred to as moderate risk wastes (MRW).

Household hazardous waste (HHW) and MRW facilities are collection sites that provide for the disposal of dangerous wastes from households, small businesses, or government generators. The HHW or MRW facilities, and similar mobile collection services, are operated under the solid waste management plans developed by local governments and are financed by rates charged for solid waste collection services. The HHW and MRW facilities may provide one option for small quantity generators and households to dispose of their leftover architectural paints, although not all HHW or MRW collection locations and services accept either or both types of paint.

Where HHW or MRW paint collection services are not available, one permissible disposal option for leftover paint, where available, are voluntary collections coordinated by paint retailers or mobile facilities. A second additional permissible disposal option is to dry and solidify latex-based paint prior to disposal via local solid waste management collection streams.

Businesses that generate volumes of dangerous waste that exceed exempt levels must manage their leftover oil-based paints like other dangerous wastes by meeting certain storage and handling requirements, and by recycling or disposal at a facility specially permitted to handle dangerous wastes. Business generators of nonexempt volumes of dangerous waste may also need to manage leftover latex-based paints as dangerous wastes, depending on the contents of the latex paint.

Other Relevant Program Context.

The Pollution Control Hearings Board (PCHB) is an appeals board with jurisdiction to hear appeals of certain decisions, orders, and penalties made by the Department of Ecology (Department) and several other state agencies. Parties aggrieved by a PCHB decision may obtain subsequent judicial review.

The Utilities and Transportation Commission (UTC) supervises and regulates private solid waste companies, including reviewing and approving their rates and fees. Cities and towns also sometimes provide solid waste collection services.

The Public Records Act requires state and local government agencies to make all public records available for public inspection and copying unless the records fall within a statutory exemption.

Summary of Bill:

Manufacturer and Retailer Responsibilities.

Producers of interior or exterior architectural paint sold in containers of five gallons or less are required to participate in an approved stewardship plan and fund a paint stewardship organization. Producers that do not participate in an approved stewardship plan may not sell architectural paint in or into Washington.

Retailers may not sell the paint of producers who do not participate in an approved stewardship plan and fund a stewardship organization. Retailers must verify that a producer is listed on the Department website as a compliant producer prior to selling that producer's paint to consumers. Paint retailers may elect to serve as paint collection sites for the stewardship program, but are not required to do so. Architectural paint sold to consumers must be accompanied by information about the end-of-life paint management options offered by the stewardship program.

Paint Stewardship Program.

A stewardship organization representing producers is required to submit a stewardship program plan to the Department by January 15, 2016. A stewardship organization must implement the program by July 1, 2016 or within three months of the plan's approval by the Department, whichever comes later.

The plan the stewardship organization submits to the Department must include a description of the operations and management of the stewardship program, including:

The stewardship program must collect leftover oil-based and latex-based architectural paints from households and small quantity generators, as well as latex-based paint from regulated generators. Under the stewardship program, architectural paints must be managed using both environmentally and economically sound practices and must prioritize the following waste management options in descending order: paint reduction, reuse, recycling, energy recovery, and disposal. The stewardship program must also include a process for handling the canisters that contain the leftover paint, with an emphasis on recycling the canisters.

The stewardship program must develop and distribute informational materials to collection sites and educational materials to consumers.

Paint Collection Requirements for Stewardship Programs.

A stewardship program plan must provide reasonably convenient and available statewide collection. Programs must also utilize existing public and private solid waste services and facilities. The program must fairly compensate service providers for their costs. The stewardship organization must renegotiate collection site contracts every two years, unless both parties agree otherwise. Curbside collection services may be used in lieu of paint collection facilities by the stewardship program, so long as doing so provides at least equivalent convenience and access. The program must use geographic modeling to ensure that distribution of collection sites in rural and urban areas meets certain criteria, including the requiring that collection service be provided within 15 miles of 90 percent of the state's population. The stewardship program's collection system must use public and private waste collection services, as well as existing paint retail stores as collection sites, if it is cost-effective and mutually agreeable to do so. Retail sites are not required to participate as collection sites. Collection sites must be identified in the plan submitted for approval by the Department and must be operational within the first year of the program.

Program Funding.

The funding of a stewardship program must be based on a uniform assessment levied on each can of architectural paint sold by producers to retailers and distributors. Paint producers must cover all administrative and operational costs of the program. The per-can assessment on producers must be added to the price of the paint sold at retail, but may not be described as a Department recycling fee. The program may not add an additional fee at the time of leftover paint collection; however, curbside collection services may charge an additional fee to cover their additional collection costs as provided by a contract with a city or the UTC. The assessment must be sufficient to recover, but not exceed, the stewardship program's costs. The per-can assessment proposed in a stewardship organization's plan must be reviewed by an independent auditor, who must then recommend an amount to the Department for approval. Surplus funds from the assessment must either be put back into program services or used to reduce the amount of the assessment in future years.

An account is created in the State Treasury to accept the receipts owed to the Department by stewardship organizations and may only be used for administering and enforcing the program.

Program Oversight and Compliance Mechanisms.

The Department is responsible for reviewing the plan submitted by the stewardship organization within 120 days of receipt and must approve the plan if it meets statutory requirements. Proposed stewardship plans and plan amendments must be made available for at least 30 days of public comment.

The Department must also supervise the stewardship organization's implementation of the paint assessment, approve the amount of the paint assessment, and review the annual reports of stewardship organizations to ensure compliance with program requirements. The Department must maintain a list of paint producers who are compliant with stewardship program participation requirements on its website. The Department's costs in administering and enforcing the stewardship program must be paid in an annual fee by the stewardship organization or organizations. If there are multiple stewardship programs, they must equally divide the Department’s fee.

A civil penalty of up to $1,000 per violation per day may be imposed by the Department for violations of the act or up to $10,000 per violation per day for known, intentional, or negligent violations. Penalties imposed by the Department are appealable to the PCHB.

Reporting Requirements and Other Provisions.

Beginning in 2016, stewardship organizations must submit an annual report by October 15. The report, made publicly available online, must include descriptions of the program's paint management methods, the volumes of different types of paint collected by the program, and various costs associated with implementing the program, including an independent financial audit of the program.

Proprietary information submitted to the Department is exempt from disclosure under the Public Records Act, although information that does not directly or indirectly identify an individual producer or stewardship organization may be disclosed. Valuable commercial information submitted to the Department may not be disclosed without advanced notice to the submitter. If the submitter obtains a superior court order protecting the records within 10 days of the notice, the Department may not release them. A superior court must protect the records if disclosure would result in private loss, including unfair competitive disadvantage.

Producers and stewardship organizations are granted immunity from state antitrust laws in establishing the stewardship program and in establishing the paint assessment.

The Paint Stewardship Program laws are deemed void if a federal paint recycling program is established.

The Department may adopt rules to implement, administer, and enforce the program.

Appropriation: None.

Fiscal Note: Available.

Effective Date: This bill takes effect 90 days after adjournment of the session in which the bill is passed, except for section 17, relating to the jurisdiction of the pollution control hearings board, which takes effect June 30, 2019.