Legislation enacted in 1995, required counties and cities planning under the Growth Management Act (GMA) to establish an integrated and consolidated development permit process. The permit process must include a determination of completeness of the project application within 28 days of submission. A project permit application is determined to be complete when it meets the local procedural submission requirements even if additional information is needed, because of subsequent project modifications.
Within 14 days of receiving requested additional information, the local government must notify the applicant whether the application is deemed complete. The determination of completeness does not preclude a request for additional information if new information is required or substantial project changes occur. A project permit application is deemed complete if the GMA jurisdiction does not provide a written determination to the applicant that the application is incomplete within the required time period.
Local project permit applications shall be deemed complete following three reviews or requests for additional information by the local government, unless there is a clear violation of substantive and procedural requirements demonstrated by the reviewing entity.