HOUSE BILL REPORT
SB 6408
BYSenators Patterson, Bender, Thorsness, Hansen and Talmadge; by request of Governor
Adopting the supplemental transportation budget.
House Committe on Transportation
House Staff:Robin Rettew (786-7306); Brad Lovaas (786-7307)
AS PASSED HOUSE MARCH 2, 1990
BACKGROUND:
The 1989 Legislature adopted a $2.0 billion budget for the 1989-91 biennium for all transportation agencies. This was a "no tax" increase budget.
SUMMARY:
The Governor's 1990 transportation supplemental budget adds $151.5 million, bringing the 1989-91 biennium total to $2.2 billion, an increase of 7.3 percent. This budget assumes passage of the comprehensive 1990 revenue bill. Major enhancements include:
1) $12.4 million for a new county arterial preservation program;
2) $6.9 million for increased funding for the county rural arterial program;
3) $41.3 million for the Transportation Improvement Board which has been unfunded since it was created in 1988;
4) $50.0 million for the regular Category C program at the Department of Transportation;
5) $5.0 million for special Category C projects including the First Avenue South Bridge, SR 18 between Auburn and I-90, and the North-South corridor in Spokane;
6) $3.1 million for removal of toll booths and preliminary engineering for the Spokane River Bridge and redemption of outstanding bonds;
7) $4.1 million for the new high capacity transit program including $3.4 million for high capacity planning grants, $.2 million for high capacity administration, $.2 million for freight rail administration, and $.2 million for Amtrak studies;
8) $1.5 million for acquisition of a fourth passenger only vessel, completion of passenger only terminal construction, and preliminary design work at the Sidney terminal;
9) $4.1 million for passenger only operating funds, continuation of the Sidney terminal lease, and completion of the payroll project;
10) $24 million for a new State Patrol headquarters facility (contingent on bond bill/bond bill not introduced);
11) $.5 million for completion of the county auditor automation project (CAAP) at the Department of Licensing;
12) $1.9 million reduction of transportation funds to complete cost accounting study fund shifts; and
13) $.4 million for strategic planning for information services at the Department of Licensing.
Appropriation: $148.5 million
Fiscal Note: Not Requested.
Effective Date:The bill contains an emergency clause and takes effect immediately.
VOTE ON FINAL PASSAGE:
Yeas 94; Nays 3 - 3/2