H-1367              _______________________________________________

 

                                                   HOUSE BILL NO. 1787

                        _______________________________________________

 

State of Washington                               51st Legislature                              1989 Regular Session

 

By Representatives H. Sommers, Schoon and Jacobsen

 

 

Read first time 2/3/89 and referred to Committee on Capital Facilities & Financing.

 

 


AN ACT Adopting the capital budget; making appropriations and authorizing expenditures for capital improvements; authorizing certain projects; and declaring an emergency.

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:

 

          NEW SECTION.  Sec. 1.     A capital budget is hereby adopted and, subject to the provisions set forth in this act, the several dollar amounts hereinafter  specified, or so much thereof as shall be sufficient to accomplish the purposes designated, are hereby appropriated and authorized to be incurred for capital projects during the period ending June 30, 1991, out of the several funds specified in this act.

 

          NEW SECTION.  Sec. 2.     As used in this  act, the following phrases have the following meanings:

          "Common School Constr Fund" means Common School Construction Fund;

          "Cap Bldg Constr Acct" means Capitol Building Construction Account;

          "St Bldg Constr Acct" means State Building Construction Account;

          "St Fac Renew Acct" means State Facilities Renewal Account;

          "Fish Cap Proj Acct" means Fisheries Capital Projects Account;

          "ORA" means Outdoor Recreation Account;

          "Sal Enhmt Constr Acct" means Salmon Enhancement Construction Account;

          "For Dev Acct" means Forest Development Account;

          "Res Mgmt Cost Acct" means Resource Management Cost Account;

          "LIRA, DSHS Fac" means Local Improvements Revolving Account‑-Department of Social and Health Services Facilities;

          "DSHS Constr Acct" means State Social and Health Services Construction Account;

          "CEP & RI Acct" means Charitable, Educational, Penal, and Reformatory Institutions Account;

          "WSU Bldg Acct" means Washington State University Building Account;

          "St H Ed Constr Acct" means State Higher Education Construction Account;

          "EWU Cap Proj Acct" means Eastern Washington University Capital Projects Account;

          "TESC Cap Proj Acct" means The Evergreen State College Capital Projects Account;

          "CWU Cap Proj Acct" means Central Washington University Capital Projects Account;

          "UW Bldg Acct" means University of Washington Building Account;

          "WWU Cap Proj Acct" means Western Washington University Capital Projects Account;

          "Cap Purch & Dev Acct" means Capitol Purchase and Development Account;

          "Hndcp Fac Constr Acct" means Handicapped Facilities Construction Account;

          "LIRA, Waste Disp Fac" means State and Local Improvement Revolving Account‑-Waste Disposal Facilities;

          "State Emerg Water Proj Rev" means Emergency Water Project Revolving Account‑-State;

          "LIRA, Waste Fac 1980" means State and Local Improvement Revolving Account‑-Waste Disposal Facilities 1980;

          "LIRA, Water Sup Fac" means State and Local Improvement Revolving Account‑-Water Supply Facilities;

          "LIRA" means State and Local Improvement Revolving Account;

          "LIRA, Public Rec Fac" means State and Local Improvement Revolving Account‑-Public Recreation Facilities;

          "H Ed Constr Acct" means Higher Education Construction Account 1979;

          "H Ed Reimb S/T Bonds Acct" means Higher Education Reimbursable Short-Term Bonds Account;

          "Unemp Comp Admin Acct" means Unemployment Compensation Administration Account;

          "Game Spec Wildlife Acct" means Game Special Wildlife Account;

          "Local Jail Imp & Constr Acct" means Local Jail Improvement and Construction Account;

          "ORV" means off road vehicle;

          "ESS Rail Assis Acct" means essential rail assistance account;

          "ESS Rail Bank Acct" means essential rail bank account;

          "East Cap Devel Acct" means east campus development account;

          The words "capital improvements" or "capital projects" used in this act mean acquisition of sites, easements, rights of way, or improvements thereon and appurtenances thereto, construction and initial equipment, reconstruction, demolition, or major alterations of new or presently owned capital assets.  For purposes of this act, "provided solely" means the specified amount may be spent only for the specified purpose.  Unless otherwise specifically authorized in this act, any portion of an amount provided solely for a specified purpose which is unnecessary to fulfill the specified purpose shall revert.

          "Revert" or "lapse" means the amount shall return to an unappropriated status.

                                                                              PART I

                                                               GENERAL GOVERNMENT

 

!af98,100@lb

 

          NEW SECTION.  Sec. 3.     FOR THE SECRETARY OF STATE

 

          Design and construct regional branch archive facility (90-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc3,005,000

 

@lb !tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc49,000!tc7,069,000!tc10,123,000

 

 

 

          NEW SECTION.  Sec. 4.     FOR THE SECRETARY OF STATE

 

          Acquisition and installation of moveable archive vault #2 shelving (90-2-002)

 

@lb !tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc152,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc152,000

 

 

 

          NEW SECTION.  Sec. 5.     FOR THE OFFICE OF FINANCIAL MANAGEMENT

 

          Local jail facilities (88-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLocal Jail Imp & Con Acct!tj1!tc150,615

St Bldg Constr Acct!tj1!tc1,060,789

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,827,596!tj1!tc5,039,000

 

 

 

          NEW SECTION.  Sec. 6.     FOR THE OFFICE OF FINANCIAL MANAGEMENT

 

          Branch campuses: Planning (90-5-001)

 

          The office of financial management shall contract with the higher education coordinating board, in cooperation with the public higher education institutions and the office of financial management, to plan for the orderly development of branch campuses through the year 2010.  The plan shall be submitted to the office of financial management and the legislature by January 1, 1990, and should contain, but not be limited to, the following items:

          (1) Distribution of projected enrollments between sectors of higher education and between main campus and branch campus sites through the year 2010;

          (2) Recommendations of specific sites for each branch campus taking into consideration long-term enrollment needs, access to the public, and program offerings;

          (3) Estimates of site acquisition and development costs necessary to accommodate estimated enrollments and program offerings at each branch campus.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,000,000

 

 

 

          NEW SECTION.  Sec. 7.     FOR THE OFFICE OF FINANCIAL MANAGEMENT

 

          Branch campuses:  Site acquisition and development (90-5-002)

 

          The appropriation in this section shall be used for the acquisition and construction of higher education branch campuses.  No funds in this appropriation shall be spent prior to legislative adoption of a branch campus plan, as outlined in section 104 of this act.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc45,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc100,000,000!tc145,000,000

 

 

 

          NEW SECTION.  Sec. 8.     FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Campus HVAC repairs (86-1-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj1!tc145,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc105,000!tj1!tc250,000

 

 

 

          NEW SECTION.  Sec. 9.     FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Temple of Justice Renovation (86-1-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc800,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc14,560,000!tj1!tc15,360,000

 

 

 

          NEW SECTION.  Sec. 10.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Capitol Lake Preservation (86-2-024)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj1!tc640,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc654,000!tj1!tc1,294,000

 

 

 

          NEW SECTION.  Sec. 11.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Northern State-Life Safety Repair (88-1-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc150,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc175,000!tj1!tc325,000

 

 

 

          NEW SECTION.  Sec. 12.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Campus repairs-Inadequate building systems (88-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj1!tc400,000

St Bldg Constr Acct!tj1!tc1,100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc5,867,000!tj1!tc7,367,000

 

 

 

          NEW SECTION.  Sec. 13.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          John A. Cherberg Building remodel (88-2-040)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc3,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc800,000!tj1!tc3,800,000

 

 

 

          NEW SECTION.  Sec. 14.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Highway-License Building Renovation (88-5-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Purch & Devel Acct!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc300,000!tj1!tc500,000

 

 

 

          NEW SECTION.  Sec. 15.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Emergency repairs (90-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj2!tc250,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc500,000!tc750,000

 

 

 

          NEW SECTION.  Sec. 16.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Small repairs and improvements (90-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj2!tc450,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc900,000!tc1,350,000

 

 

 

          NEW SECTION.  Sec. 17.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Campus asbestos program (90-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc210,000!tc410,000

 

 

 

          NEW SECTION.  Sec. 18.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Minor works:  Northern state repairs (90-1-012)

 

          (1) The appropriation in this section from the CEP & RI Account shall be used solely for developing a long range plan for the use of the Northern State Hospital facility.  The plan shall be developed cooperatively with the department of social and health services and in consultation with the affected local communities.  The study shall be submitted to the office of financial management and the legislature by January 1, 1990.

          (2) The remainder of the appropriation shall be used for asbestos abatement in residence facilities in current use.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc100,000

St Bldg Constr Acct!tj2!tc960,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,060,000

 

 

 

          NEW SECTION.  Sec. 19.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Boiler plant structural repairs (90-1-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc730,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc730,000

 

 

 

          NEW SECTION.  Sec. 20.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Asbestos inventory and inspection program (90-01-023)

 

          The appropriation in this section is subject to the following conditions and limitations:

          The department shall:

          (1) Develop guidelines for asbestos surveys in all state-owned buildings.

          (2) Review and approve state agency asbestos survey policies and procedures.

          (3) Establish and maintain a central file of asbestos surveys of state-owned buildings.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc200,000

 

 

          NEW SECTION.  Sec. 21.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Minor works:  Sidewalk and street repairs (90-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj2!tc500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc200,000!tc700,000

 

 

 

          NEW SECTION.  Sec. 22.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Minor works:  Building exterior repairs and renovation (90-2-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj2!tc1,426,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,340,000!tc2,766,000

 

 

 

          NEW SECTION.  Sec. 23.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Minor works:  Elevator/escalator repair (90-2-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc614,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,400,000!tc2,014,000

 

 

 

          NEW SECTION.  Sec. 24.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Minor works:  Electrical repairs (90-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj2!tc797,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc901,000!tc1,698,000

 

 

 

          NEW SECTION.  Sec. 25.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Minor works:  Mechanical system repairs (90-2-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc2,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc2,341,000!tc4,431,020

 

 

 

          NEW SECTION.  Sec. 26.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Minor works:  Interior building repair (90-2-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixMotor transport Acct!tj2!tc262,000

St Bldg Constr Acct!tj2!tc1,125,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,329,000!tc2,716,000

 

 

 

          NEW SECTION.  Sec. 27.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Highways-Licenses Building renovation (90-2-015)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj2!tc3,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc10,656,680!tc13,656,680

 

 

 

          NEW SECTION.  Sec. 28.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Capitol Lake repairs and preservation (90-3-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj2!tc1,813,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,813,000

 

 

 

          NEW SECTION.  Sec. 29.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Facilities management system (90-4-018)

 

          The appropriation in this section is subject to the following conditions and limitations:

          The department shall establish and maintain a central inventory of all state-owned land and facilities.  The data elements of the inventory shall be developed in cooperation with the office of financial management.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc200,000

 

 

 

          NEW SECTION.  Sec. 30.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Construction of archives storage building (90-4-024)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc2,015,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc2,015,000

 

 

 

          NEW SECTION.  Sec. 31.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          East campus development (90-5-003)

 

          Design and construct a natural resources building and parking facility on a site directly east of the old Thurston County courthouse.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixEast Cap Devel Acct!tj2!tc73,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc73,000,000

 

 

 

          NEW SECTION.  Sec. 32.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Dawley property acquisition (90-5-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,311,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,311,000

 

 

 

          NEW SECTION.  Sec. 33.    FOR THE DEPARTMENT OF GENERAL ADMINISTRATION

 

          Preplans and surveys (90-5-022)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCap Bldg Constr Acct!tj2!tc143,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc143,000

 

 

 

          NEW SECTION.  Sec. 34.    FOR THE MILITARY DEPARTMENT

 

          Tacoma Armory rehabilitation phase 3 (86-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,200,000!tj1!tc2,300,000

 

 

 

          NEW SECTION.  Sec. 35.    FOR THE MILITARY DEPARTMENT

 

          Constr watercraft supt training complex (86-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral fund‑-Federal!tj2!tc6,885,000

St Bldg Constr Acct!tj2!tc2,200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,640,000!tc5,500,000!tc16,225,000

 

 

 

          NEW SECTION.  Sec. 36.    FOR THE MILITARY DEPARTMENT

 

          Minor works:  Support fed service agreement (86-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral fund‑-Federal!tj2!tc3,189,000

St Bldg Constr Acct!tj2!tc1,063,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc8,884,000!tc13,136,000

 

 

 

          NEW SECTION.  Sec. 37.    FOR THE MILITARY DEPARTMENT

 

          Minor works (86-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc85,000!tc425,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,179,000!tc1,100,000!tc3,789,000

 

 

 

          NEW SECTION.  Sec. 38.    FOR THE MILITARY DEPARTMENT

 

          Small repairs and improvements (86-2-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc375,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc812,000!tc1,150,000!tc2,337,000

 

 

 

          NEW SECTION.  Sec. 39.    FOR THE MILITARY DEPARTMENT

 

          Construct Kent Armory (86-3-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral fund‑-Federal!tj2!tc600,000

St Bldg Constr Acct!tj1!tc375,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,114,000!tj1!tc4,089,000

 

 

 

          NEW SECTION.  Sec. 40.    FOR THE MILITARY DEPARTMENT

 

          Life/Safety code compliance (88-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc800,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,600,000!tc2,400,000

 

 

 

          NEW SECTION.  Sec. 41.    FOR THE MILITARY DEPARTMENT

 

          Repair/replace leaking underground tanks (88-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc134,000!tc345,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc153,000!tc430,000!tc1,062,000

 

 

 

          NEW SECTION.  Sec. 42.    FOR THE MILITARY DEPARTMENT

 

          Roof renovation (88-3-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc125,000!tc700,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc575,000!tc900,000!tc2,300,000

 

 

 

          NEW SECTION.  Sec. 43.    FOR THE MILITARY DEPARTMENT

 

          Exterior painting of facilities (88-3-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc258,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc258,000!tc500,000!tc1,016,000

 

 

 

          NEW SECTION.  Sec. 44.    FOR THE MILITARY DEPARTMENT

 

          Facility HVAC renovation (88-4-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc280,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc434,000!tc714,000

 

 

 

          NEW SECTION.  Sec. 45.    FOR THE MILITARY DEPARTMENT

 

          Energy conservation projects (88-4-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc125,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc951,000!tj1!tc1,076,000

 

 

 

          NEW SECTION.  Sec. 46.    FOR THE MILITARY DEPARTMENT

 

          Project preplanning (88-5-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc198,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc174,000!tc341,000!tc713,000

@la

                                                                          (End of part)

 

!np

                                                                              PART 2

                                                                                  

HUMAN RESOURCES

 

!af98,200 @lb

 

          NEW SECTION.  Sec. 47.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Capitalize development loan fund (88-2-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,200,000!tc7,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc6,870,000!tc10,000,000!tc26,070,000

 

 

 

          NEW SECTION.  Sec. 48.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Endangered landmark buildings (88-2-009)

 

          This appropriation is provided solely to establish a permanent fund, known as the endangered landmarks preservation fund, to be used by the department to purchase and hold for brief periods landmark buildings which might otherwise be lost or altered, and to resell those buildings with the proceeds for sale deposited in the fund.

          This appropriation is provided contingent on an equal amount being provided from nonstate sources on a project by project basis.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc600,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc600,000

 

 

 

          NEW SECTION.  Sec. 49.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Grays Harbor dredging (88-3-006)

 

          The appropriation in this section is provided solely for the state's share of costs for Grays Harbor dredging, dike construction, bridge relocation, and related expenses.

          (1) This money is contingent on $40,000,000 from the United States army corps of engineers and $10,000,000 from local government funds being provided for the project.

          (2) The port of Grays Harbor shall make the best possible effort to acquire additional project funding from sources other than those in subsection (1) of this section.  Any money, up to $10,000,000 provided from sources other than those in subsection (1) of this section, shall be used to reimburse or replace state building construction fund money.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc10,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc10,000,000

 

 

 

          NEW SECTION.  Sec. 50.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Capitalize housing trust fund (88-5-015)

 

          The appropriation in this section is subject to the following conditions and limitations:

          (1) No expenditures from this appropriation may be made until the department has completed the state-wide housing data study and the legislature has reviewed the results.

          (2) The appropriation shall be used solely for capital costs associated with the purposes of the housing trust fund under RCW 43.185.050.  These moneys shall be used for loans or grants for capital projects state-wide that will provide housing for persons or families with special housing needs and with incomes at or below fifty percent of the median family income for the county or standard metropolitan statistical area where the project is located.  At least thirty percent of the moneys used for loans or grants shall go to projects located in rural areas.

          (3) The department shall to the maximum extent feasible use the appropriation to leverage other funds for capital costs associated with the purposes of the housing trust fund under chapter 43.185 RCW.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,000,000!tc15,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc20,000,000!tc37,000,000

 

 

 

          NEW SECTION.  Sec. 51.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Tacoma Union Station (88-5-016)

 

          The appropriation in this section, in addition to funds appropriated for the 1987-89 biennium for this project, is subject to the following conditions and limitations:

          (1) $1,000,000 is provided solely to prevent further deterioration of the Tacoma Union Station building.  This may include, but is not limited to, providing a fire detection system, removing safety hazards, and programming necessary to implement these works.

          (2) A maximum of $500,000 may be used for planning regarding future use of the Tacoma Union Station property to promote state economic development.

          (3) The money in subsections (1) and (2) of this section is provided contingent upon a written legal agreement between the city of Tacoma and the state that (a) requires state approval of future uses and disposition of the Tacoma Union Station property and (b) gives the state the right of first refusal to assume the city of Tacoma's option to purchase the Tacoma Union Station property currently owned by the Burlington Northern company.

          (4) $500,000 is provided solely for architectural plans and construction specifications for a state museum on the Union Station property.

          (5) $400,000 is provided solely for purchase of the Union Station property.  The appropriation in this subsection is contingent on a like amount being provided for this purpose from nonstate sources.

          (6) $2,000,000 is provided solely for restoration of the rotunda of the Union Station building.  The appropriation in this subsection is contingent on the city's agreement to exercise its option to purchase Union Station and the city's agreement to grant to the state the right of first refusal to assume the city's option to purchase the property should the city decide to withdraw from the project.

          (7) The money in subsections (4), (5), and (6) of this section is provided contingent upon a written legal agreement between the city of Tacoma and the state that:

          (a) The city obtain the state's approval for all decisions with respect to:

          (i) Determining final ownership of Union Station itself;

          (ii) Identifying appropriate uses for the site; and

          (iii) Selecting consultants retained by the city under its contract with the state;

          (b) The city consult with the state and, unless prohibited from doing so by terms of the United States general services administration lease, follow the state's recommendations in other significant decisions concerning the development of the Union Station properties, including but not limited to:

          (i) Planning the development and redevelopment of the site to accommodate appropriate uses;

          (ii) Obtaining financing for acquisition, development, or redevelopment of the property; and

          (iii) Acquiring, leasing, subleasing, and/or reselling the property;

          (c) If the city finds that it is not possible to follow the state's recommendations, the city will advise the state and allow the state a reasonable opportunity to comment; and

          (d) The city shall obtain a public access easement from the United States general services administration or any other owner or lessee that will allow public access through the rotunda to any future state facility.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc3,900,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc500,000!tj1!tc4,400,000

 

 

 

          NEW SECTION.  Sec. 52.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          San Juan County Courthouse (88-5-017)

 

          This appropriation is contingent on the provision of an equal amount of money from nonstate sources.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc100,000

 

 

 

          NEW SECTION.  Sec. 53.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Columbia County Courthouse (89-4-004)

 

          The appropriation in this section is subject to the following conditions and limitations:

          (1) $400,000 is appropriated to repair and restore the Columbia county courthouse.

          (2) The appropriation in this section shall be matched by $700,000 in private donations and local funds from Columbia county.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc400,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc400,000

 

 

          NEW SECTION.  Sec. 54.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Spokane public facilities (89-5-005)

 

          The appropriation in this section is subject to the following conditions and limitations:  The money appropriated in this section is provided solely for the purposes of RCW 36.100.030 and 36.100.060.  Money appropriated in this section may be spent only if the Spokane public facilities district has been created.  If all bonds needed to construct a Spokane trade, sports and convention facility have not been authorized by December 31, 1991, the district shall within thirty days thereafter repay the amount appropriated in this section, together with all interest earnings, to the state building construction account.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,000,000

 

 

 

          NEW SECTION.  Sec. 55.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Construct fire service training center station (90-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc2,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc15,740!tj1!tc2,015,740

 

 

 

          NEW SECTION.  Sec. 56.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Public works trust fund (90-2-001)

 

          The appropriations in this section are provided solely for public works projects recommended by the public works board and approved by the legislature under chapter 43.155 RCW.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixPub Works Asst Acct!tj1!tc43,284,704!tc64,987,112

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc7/1/87!tcThereafter

 

!tc18,038,142!tc168,562,493!tc294,872,451

 

 

 

          NEW SECTION.  Sec. 57.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Emergency management building minor renovation (90-2-003)

 

          This appropriation shall be used solely to provide handicapped access and improve insulation.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc80,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc80,000

 

 

 

          NEW SECTION.  Sec. 58.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Fire service training center minor works (90-2-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc441,887

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc441,887

 

 

 

          NEW SECTION.  Sec. 59.    FOR THE DEPARTMENT OF COMMUNITY DEVELOPMENT

 

          Seattle Asian Cultural Center‑-Design and construction (90-5-006)

 

          This appropriation is subject to the following conditions and limitations:

          (1) This appropriation shall be used for construction cost only.

          (2) This appropriation is contingent upon an equal amount being provided by nonstate sources.

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc759,300

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc759,300

 

 

 

          NEW SECTION.  Sec. 60.    FOR THE DEPARTMENT OF LABOR AND INDUSTRIES

 

          Property acquisition, design and construct office facility (90-5-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixAccident Fund!tj2!tc31,500,000

Medical Aid Fund!tj2!tc31,500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc63,000,000

 

 

 

          NEW SECTION.  Sec. 61.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Lakeland Village:  Construct habilitation center (79-1-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixDSHS Constr Acct!tj1!tc375,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc6,040,662!tj1!tc6,415,662

 

 

 

          NEW SECTION.  Sec. 62.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Rainier School:  Renovate Evergreen Center (79-1-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc4,400,000

DSHS Constr Acct!tj1!tc75,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,058,824!tj1!tc5,533,824

 

 

 

          NEW SECTION.  Sec. 63.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Referendum #37 (79-3-001)

 

          In addition to previously approved projects, $29,000 shall be used to construct an addition to a training center in Skamania county to serve up to ten more developmentally disabled children under four years old, which requires a final application submittal by December 31, 1989, and approval by March 31, 1990.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixHandicap Fac Constr Acct!tj1!tc461,951

Improve‑-DSHS Fac Acct!tj1!tc23,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,825,588!tj1!tc3,311,039

 

 

 

          NEW SECTION.  Sec. 64.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          State mental health residences (79-3-002)

 

          This appropriation, in addition to funds appropriated in the 1987-89 biennium for this project, is subject to the following conditions and limitations:  A maximum of $40,000 of the funds provided may be spent for renovation or other costs necessary to establish a self-supporting day care center for children of state employees at Eastern State Hospital.  A maximum of $170,000 of the funds provided in this section is provided solely for participation by the department of social and health services in a project to construct a multipurpose child care center at the Everett community college.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixImprov‑-DSHS Fac Acct!tj1!tc218,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc985,677!tj1!tc1,204,177

 

 

 

          NEW SECTION.  Sec. 65.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Western State Hospital:  Complete artwork (79-4-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixDSHS Constr Acct!tj1!tc40,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc108,045!tj1!tc148,045

 

 

 

          NEW SECTION.  Sec. 66.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Construct public health lab (81-3-110)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixDSHS Constr Acct!tj1!tc12,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc631,490!tj1!tc643,990

 

 

 

          NEW SECTION.  Sec. 67.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Western State Hospital:  Fire safety (83-1-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixDSHS Constr Acct!tj1!tc25,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc189,203!tj1!tc214,203

 

 

 

          NEW SECTION.  Sec. 68.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Eastern State Hospital:  Renovate wards, phase 1 (83-2-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixDSHS Constr Acct!tj1!tc169,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,106,000!tj1!tc3,275,000

 

 

 

          NEW SECTION.  Sec. 69.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Western State Hospital:  Renovate wards, phase 2 (83-2-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixDSHS Constr Acct!tj1!tc3,500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc10,398,000!tj1!tc13,898,000

 

 

 

          NEW SECTION.  Sec. 70.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Mission Creek:  Renovate main buildings (86-1-202)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Fac Renew Acct!tj1!tc123,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,924,999!tj1!tc2,047,999

 

 

 

          NEW SECTION.  Sec. 71.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Fircrest Schools:  Construct food service (86-1-403)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixDSHS Constr Acct!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,896,302!tj1!tc4,096,302

 

 

 

          NEW SECTION.  Sec. 72.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Referendum 27 and 38 (86-2-099)

 

          The appropriations in this section are subject to the following conditions and limitations:

          (1) Up to sixteen full-time equivalent staff per year may be funded from the reappropriation of Referendum 38 for the purpose of reviewing local water improvement accounts.

          (2) The appropriation is provided solely for drought related municipal and industrial water supply projects.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA Water Supp Fac!tj1!tc25,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc20,134,000!tj1!tc45,134,000

 

 

 

          NEW SECTION.  Sec. 73.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Western State Hospital:  Renovate wards, phase 3 (88-1-307)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc585,900

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc585,900

 

 

 

          NEW SECTION.  Sec. 74.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          CSTC‑-Renovate residences to high school (88-1-318)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc860,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc87,000!tj1!tc947,000

 

 

 

          NEW SECTION.  Sec. 75.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          ITA residential facilities (88-2-340)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc950,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc50,000!tj1!tc1,000,000

 

 

 

          NEW SECTION.  Sec. 76.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Western State Hospital:  Sanitary sewer (88-2-400)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,050,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,829,000!tj1!tc4,879,000

 

 

 

          NEW SECTION.  Sec. 77.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor capital renewal:  Fire safety (90-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc600,000

St Bldg Constr Acct!tj1!tc1,120,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc25,000!tc1,200,000!tc2,945,000

 

 

 

          NEW SECTION.  Sec. 78.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor capital renewal:  Hazardous substance (90-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc500,000

St Bldg Constr Acct!tj1!tc645,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc332,000!tc1,392,500!tc2,869,500

 

 

 

          NEW SECTION.  Sec. 79.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Emergency capital repairs (90-1-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc250,000

St Bldg Constr Acct!tj1!tc294,000

St Fac Renew Acct!tj1!tc135,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc815,502!tc500,000!tc1,994,502

 

 

 

          NEW SECTION.  Sec. 80.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Echo Glen:  Renovate eleven living units (90-1-210)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc2,964,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc2,964,000

 

 

 

          NEW SECTION.  Sec. 81.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Western State Hospital:  Ward renovations, phase 4 (90-1-312)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc5,189,400

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc5,189,400

 

 

 

          NEW SECTION.  Sec. 82.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Eastern State Hospital:  Ward renovations, phase 2 (90-1-339)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc4,510,400

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc4,510,400

 

 

 

          NEW SECTION.  Sec. 83.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor capital renewal:  Utilities and facilities (90-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc750,000

St Bldg Constr Acct!tj1!tc780,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc278,000!tc2,100,000!tc3,908,000

 

 

 

          NEW SECTION.  Sec. 84.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor capital renewal:  Roads and grounds (90-2-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc500,000

St Bldg Constr Acct!tj1!tc510,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc112,200!tc1,200,000!tc2,322,200

 

 

 

          NEW SECTION.  Sec. 85.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor capital renewal:  Roofs (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc140,000!tc700,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,000,000!tc2,000,000!tc3,840,000

 

 

 

          NEW SECTION.  Sec. 86.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Small repairs and improvements  (90-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc190,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc415,000!tc605,000

 

 

 

          NEW SECTION.  Sec. 87.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor projects:  Bureau of Alcohol and Substance Abuse (90-2-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc442,400

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc100,000!tc542,400

 

 

 

          NEW SECTION.  Sec. 88.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor projects:  Juvenile rehabilitation division (90-2-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc270,100

St Bldg Constr Acct!tj1!tc331,000

St Fac Renew Acct!tj1!tc1,020,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,014,000!tc300,000!tc3,935,100

 

 

 

          NEW SECTION.  Sec. 89.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor projects:  Mental health division (90-2-030)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc600,000

St Fac Renew Acct!tj1!tc292,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,058,799!tc700,000!tc2,650,799

 

 

 

          NEW SECTION.  Sec. 90.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor projects:  Mental health division (2) (90-2-032)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc75,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc250,000!tc325,000

 

 

 

          NEW SECTION.  Sec. 91.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor projects:  Developmental disabilities division (90-2-040)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc21,200

St Bldg Constr Acct!tj1!tc694,000!tc517,600

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,063,955!tc550,000!tc2,846,755

 

 

 

          NEW SECTION.  Sec. 92.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Minor projects:  Health division (90-2-050)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc358,900

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc100,000!tc358,900

 

 

 

          NEW SECTION.  Sec. 93.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Lakeland Village:  Steam plant replacement (90-2-425)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc4,063,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc4,063,000

 

 

 

          NEW SECTION.  Sec. 94.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Resource conservation (90-4-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc220,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc85,000!tj1!tc305,000

 

 

 

          NEW SECTION.  Sec. 95.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Preplanning (90-4-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc215,400

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc329,500!tc544,900

 

 

 

          NEW SECTION.  Sec. 96.    FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

 

          Food bank facility:  Fircrest (90-5-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc788,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc788,000

 

 

 

          NEW SECTION.  Sec. 97.    FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Food services renovation (88-1-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc282,700

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc282,700

 

 

 

          NEW SECTION.  Sec. 98.    FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Soldiers Home‑-Preplan a thirty bed Alzheimer's unit (88-5-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc33,700

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,908,700!tc1,942,400

 

 

 

          NEW SECTION.  Sec. 99.    FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Preplanning for one hundred bed nursing care unit (88-5-022)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc129,400

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc7,487,600!tc7,617,000

 

 

 

          NEW SECTION.  Sec. 100.              FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Minor projects‑-Asbestos (90-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc300,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc300,000

 

 

 

          NEW SECTION.  Sec. 101.              FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Minor projects‑-Roads and walkways (90-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc100,000

 

 

 

          NEW SECTION.  Sec. 102.              FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Air quality, Building 9 (90-1-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc313,200

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc313,200

 

 

 

          NEW SECTION.  Sec. 103.              FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Small projects (90-1-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc39,800

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc39,800

 

 

 

          NEW SECTION.  Sec. 104.              FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Minor projects‑-Building remodel (90-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc256,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc256,000

 

 

 

          NEW SECTION.  Sec. 105.              FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Minor projects‑-Utilities and energy projects (90-4-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc544,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc544,000

 

 

 

          NEW SECTION.  Sec. 106.              FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Minor projects‑-Building study (90-5-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc35,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc35,000

 

 

 

          NEW SECTION.  Sec. 107.              FOR THE DEPARTMENT OF VETERANS' AFFAIRS

 

          Steam distribution system (92-2-024)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc22,200

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc895,700!tc917,900

 

 

 

          NEW SECTION.  Sec. 108.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Washington Corrections Center enlarge, remodel six hundred beds (83-3-029)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc32,961

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,338,053!tj1!tc1,371,014

 

 

 

          NEW SECTION.  Sec. 109.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Washington State Reformatory facility improvements (83-3-048)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc5,300,000!tc8,600,000

DSHS Constr Acct!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc9,533,303!tc16,000,000!tc39,633,303

 

 

 

          NEW SECTION.  Sec. 110.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Washington State Penitentiary improve security, facilities, utilities (83-3-052)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc400,000!tc5,898,000

DSHS Constr Acct!tj1!tc1,650,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc6,267,413!tc2,476,000!tc16,691,413

 

 

 

          NEW SECTION.  Sec. 111.              FOR THE DEPARTMENT OF CORRECTIONS

 

          McNeil Island Corrections Center renovation of utilities (86-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc4,377,000!tc1,261,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,647,000!tc4,674,000!tc13,959,000

 

 

 

          NEW SECTION.  Sec. 112.              FOR THE DEPARTMENT OF CORRECTIONS

 

          McNeil Island Corrections Center repairs to transportation system (86-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,033,831!tc3,522,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,259,169!tc7,081,000!tc13,896,000

 

 

 

          NEW SECTION.  Sec. 113.              FOR THE DEPARTMENT OF CORRECTIONS

 

          McNeil Island Corrections Center building fire/safety (86-1-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,000,000!tc2,183,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,165,000!tc967,000!tc8,315,000

 

 

 

          NEW SECTION.  Sec. 114.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide minor projects (86-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc160,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc4,019,000!tj1!tc4,179,000

 

 

 

          NEW SECTION.  Sec. 115.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide small repairs and improvements (86-2-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc33,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc512,500!tj1!tc546,000

 

 

 

          NEW SECTION.  Sec. 116.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Life safety code compliance (88-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc270,000

 

 

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,270,000!tj1!tc1,540,000

 

 

 

          NEW SECTION.  Sec. 117.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide wastewater system improvements (88-1-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc418,000!tc605,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc290,000!tj1!tc1,313,000

 

 

 

          NEW SECTION.  Sec. 118.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide water system improvements (88-1-018)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc50,000!tc939,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc372,000!tj1!tc1,361,000

 

 

 

          NEW SECTION.  Sec. 119.              FOR THE DEPARTMENT OF CORRECTIONS

 

          McNeil Island Corrections Center implement master plan (88-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc4,377,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc621,000!tc28,000,000!tc32,998,000

 

 

 

          NEW SECTION.  Sec. 120.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Tacoma work release relocation (88-2-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc4,355,450

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc106,550!tj1!tc4,462,000

 

 

 

          NEW SECTION.  Sec. 121.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Eastern Washington prerelease, site preparation (88-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc947,145

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc63,855!tj1!tc1,011,000

 

 

 

          NEW SECTION.  Sec. 122.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Washington Corrections Center for Women implement master plan (88-2-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc600,687!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc14,313!tc5,800,000!tc7,415,000

 

 

 

          NEW SECTION.  Sec. 123.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Washington Corrections Center reroof building (88-3-019)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc65,000!tj1!tc1,065,000

 

 

 

          NEW SECTION.  Sec. 124.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide asbestos removal/encapsulation (90-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc2,500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc5,000,000!tc7,500,000

 

 

 

          NEW SECTION.  Sec. 125.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Hazardous materials management (90-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc879,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc604,000!tc1,483,000

 

 

 

          NEW SECTION.  Sec. 126.              FOR THE DEPARTMENT OF CORRECTIONS

 

          WCC and WCCW perimeter security upgrade (90-1-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,652,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc3,277,000!tc4,929,000

 

 

 

          NEW SECTION.  Sec. 127.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide minor projects (90-1-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc1,000,000

St Bldg Constr Acct!tj2!tc4,349,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc8,000,000!tc13,349,000

 

 

 

          NEW SECTION.  Sec. 128.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide small repairs and improvements (90-1-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc756,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc756,000

 

 

 

          NEW SECTION.  Sec. 129.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide emergency repairs projects (90-1-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc750,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,500,000!tc2,250,000

 

 

 

          NEW SECTION.  Sec. 130.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Washington Corrections Center Reception Center upgrade (90-2-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc26,000

St Bldg Constr Acct!tj2!tc236,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc14,400,000!tc14,662,000

 

 

 

          NEW SECTION.  Sec. 131.              FOR THE DEPARTMENT OF CORRECTIONS

 

          WSP‑-Expand medium security complex (MSC) industries building (90-2-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,213,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,213,000

 

 

 

          NEW SECTION.  Sec. 132.              FOR THE DEPARTMENT OF CORRECTIONS

 

          State-wide roof repair (90-3-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,500,000

 

 

 

          NEW SECTION.  Sec. 133.              FOR THE DEPARTMENT OF CORRECTIONS

 

          Community corrections preplanning for construction‑-Work release (90-4-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCEP & RI Acct!tj2!tc218,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc7,790,000!tc8,008,000

 

 

 

          NEW SECTION.  Sec. 134.              FOR THE DEPARTMENT OF EMPLOYMENT SECURITY

 

          Port Angeles‑-Job Service Center (90-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixUnemploy Comp Admin‑-State!tj2!tc900,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc900,000

 

 

 

          NEW SECTION.  Sec. 135.              FOR THE DEPARTMENT OF EMPLOYMENT SECURITY

 

          Bremerton Job Service Center (92-5-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixUnemploy Comp Admin‑-State!tj2!tc761,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc761,000

@la

                                                                          (End of part)

 

!np

                                                                              PART 3

                                                                                  

NATURAL RESOURCES

 

!af98,300 @lb

 

          NEW SECTION.  Sec. 136.              FOR THE WASHINGTON STATE ENERGY OFFICE

 

          Energy conservation projects (90-4-001)

 

          The appropriation in this section is subject to the following conditions and limitations:

          The department shall contract with the following agencies for the amounts specified to undertake energy conservation projects.  Each contract shall require the agencies listed below to deposit into the energy conservation account an amount equal to the contract amount.  The payback period shall be determined by the department, but shall not exceed six years.

          (1) No more than $1,033,000 shall be expended for energy conservation projects for Military Department facilities;

          (2) No more than $361,600 shall be expended for energy conservation projects for the department of social and health services;

          (3) No more than $552,000 shall be expended for energy conservation projects for The Evergreen State College.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,946,600

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc2,199,000!tc4,145,600

 

 

 

          NEW SECTION.  Sec. 137.              FOR THE DEPARTMENT OF ECOLOGY

 

          Referendum 26‑-Waste disposal facilities; special program, state-wide (74-5-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA‑-Waste Disp Fac!tj1!tc15,742,506!tc6,100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc210,524,884!tc21,220,965!tc253,588,355

 

 

 

          NEW SECTION.  Sec. 138.              FOR THE DEPARTMENT OF ECOLOGY

 

          Referendum 27 and 38‑-Water supply facilities; special program, state-wide (74-5-006)

 

          The appropriation in this section is subject to the following conditions and limitations:

          (1) A maximum of $75,000 of this reappropriation may be expended for modification of the gate on the Lake Osoyoos international water control structure authorized by chapter 76, Laws of 1982.

          (2) Funds previously appropriated for the East Selah reregulating reservoir shall be reallocated for purposes of early implementation of the Yakima river basin water enhancement project in order to financially assist irrigators in making up 80,000 acre feet of water per year lost because of a 1980 court decision.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA Water Sup Fac!tj1!tc28,188,656!tc6,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc67,915,027!tc56,509,393!tc158,613,076

 

 

 

          NEW SECTION.  Sec. 139.              FOR THE DEPARTMENT OF ECOLOGY

 

          State emergency water project revolving account; special program, state-wide (76-5-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Emer Water Proj Rev!tj1!tc3,724,782!tc3,923,199

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,411,242!tc6,633,165!tc15,692,388

 

 

 

          NEW SECTION.  Sec. 140.              FOR THE DEPARTMENT OF ECOLOGY

 

          Padilla Bay Research Reserve‑-Land acquisition/special program (80-2-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral Fund‑-Federal!tj1!tc112,362

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,201,177!tj1!tc1,313,539

 

 

 

          NEW SECTION.  Sec. 141.              FOR THE DEPARTMENT OF ECOLOGY

 

          Referendum 39‑-Waste disposal facilities, 1980; special program, state-wide (82-5-005)

 

          The appropriation in this section is subject to the following conditions and limitations:  A maximum of $1,500,000 of the appropriation may be expended for planning assistance to any ground water management areas created pursuant to chapter 453, Laws of 1985.  Such assistance shall be allocated in a manner consistent with chapter 3, Laws of 1986.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA Waste Fac‑-1980!tj1!tc123,049,668!tc15,200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc312,372,992!tc153,615,411!tc604,238,071

 

 

 

          NEW SECTION.  Sec. 142.              FOR THE DEPARTMENT OF ECOLOGY

 

          Water quality account; special programs, state-wide (86-5-007)

 

          The appropriation in this section is subject to the following conditions and limitations:

          (1) In developing rules to administer chapter 3, Laws of 1986 and in awarding grants, extended grant payments, or loans from the water quality account, the department shall include, but not be limited to the following:

          (a) For facilities that discharge directly into marine waters, the department shall:

          (i) Give first priority to secondary wastewater treatment facilities that are mandated by both federal and state law;

          (ii) Give second priority to projects which reduce combined sewer overflows; and

          (iii) Encourage economies that are derived from any simultaneous projects which achieve both (i) and (ii) of this subsection.

          (b) In determining the appropriate level of state assistance for eligible facilities and activities, the department shall consider:

          (i) The need to provide additional assistance for eligible activities undertaken by local public bodies which lack taxing or revenue generating authority; and

          (ii) The need to provide additional assistance for eligible facilities undertaken by local public bodies that would suffer severe financial hardship in the absence of such additional assistance.

          (c) The department shall place such funds as may be necessary from the water quality account into a state revolving loan fund to be used to match capitalization funds provided by the federal environmental protection agency under Public Law 100-4.  The department shall also gradually arrange for a transition in the assistance program toward the use of loans.

          (d) The following limitations shall apply to the department's total distribution of funds appropriated under this section:

          (i) Not more than fifty percent for water pollution control facilities which discharge directly into marine waters;

          (ii) Not more than twenty percent for water pollution control activities that prevent or mitigate pollution of underground waters and facilities that protect federally designated sole source aquifers with at least two-thirds for the Spokane-Rathdrum Prairie aquifer;

          (iii) Not more than ten percent for water pollution control activities that protect freshwater lakes and rivers including but not limited to Lake Chelan and the Yakima and Columbia rivers;

          (iv) Not more than ten percent for activities which control nonpoint source water pollution;

          (v) Ten percent and such sums as may be remaining from the categories specified in (i) through (iv) of this subsection for water pollution control activities or facilities as determined by the department.

          (2) In determining compliance schedules for the greatest reasonable reduction of combined sewer overflows, the department shall consider the amount of grant or loan moneys available to assist local governments in the planning, design, acquisition, construction, and improvement of combined sewer overflow facilities.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWater Quality Acct!tj1!tc66,976,344!tc119,737,961

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc8,293,506!tc339,768,412!tc534,776,223

 

 

 

          NEW SECTION.  Sec. 143.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Yakima Greenway acquisition (81-3-098)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj1!tc92,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,000!tj1!tc93,000

 

 

 

          NEW SECTION.  Sec. 144.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Water supply facilities (86-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc197,000

ORA‑-Federal!tj1!tc3,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc735,000!tc935,000

 

 

 

          NEW SECTION.  Sec. 145.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Sewage treatment facilities (86-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA Waste Fac‑-1980!tj1!tc217,500

St Bldg Constr Acct!tj1!tc43,500

ORA‑-Federal!tj1!tc14,500

ORA‑-State!tj1!tc14,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc700,000!tj1!tc990,000

 

 

 

          NEW SECTION.  Sec. 146.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Boating repairs (86-1-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc19,000

ORA‑-Federal!tj1!tc8,000

ORA‑-State!tj1!tc48,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc388,000!tj1!tc463,000

 

 

 

          NEW SECTION.  Sec. 147.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Boating renovation (86-1-021)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc10,800

ORA‑-State!tj1!tc48,200

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc91,000!tj1!tc150,000

 

 

 

          NEW SECTION.  Sec. 148.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Beacon Rock‑-Replace floats and piling, renovate shear boom (86-1-022)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-Federal!tj1!tc6,000

ORA‑-State!tj1!tc54,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc246,000!tj1!tc306,000

 

 

 

          NEW SECTION.  Sec. 149.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Energy conservation and landscape renovation (86-1-027)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc117,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc423,000!tj1!tc540,000

 

 

 

          NEW SECTION.  Sec. 150.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Iron Horse‑-Trail safety and bridge repair/acquisition (86-1-030)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc50,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc50,000!tj1!tc100,000

 

 

 

          NEW SECTION.  Sec. 151.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Fort Worden‑-Point Wilson bank protection, phase 2 (86-1-032)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc108,900

ORA‑-Federal!tj1!tc104,000

ORA‑-State!tj1!tc87,900

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc188,100!tc124,600!tc613,500

 

 

 

          NEW SECTION.  Sec. 152.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Boating improvements (86-3-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-Federal!tj1!tc37,000

ORA‑-State!tj1!tc58,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc124,000!tj1!tc219,000

 

 

 

          NEW SECTION.  Sec. 153.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Mount Spokane‑-Entrance road development (86-3-034)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixMot Veh Fund!tj1!tc20,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc180,000!tj1!tc200,000

 

 

 

          NEW SECTION.  Sec. 154.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          West Hylebos‑-Acquisition and development (86-4-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc195,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc5,000!tj1!tc200,000

 

 

 

          NEW SECTION.  Sec. 155.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Sacajawea‑-Boat launch reconstruction (87-1-025)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-Federal!tj1!tc1,000

ORA‑-State!tj1!tc9,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc91,000!tj1!tc101,000

 

 

 

          NEW SECTION.  Sec. 156.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Lake Sylvia‑-Dam safety renovation and repair, phase 2 (87-1-028)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc15,000!tc165,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc127,000!tj1!tc307,000

 

 

 

          NEW SECTION.  Sec. 157.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Kopachuck‑-Shoreline protection (87-1-031)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj1!tc40,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc64,000!tj1!tc104,000

 

 

 

          NEW SECTION.  Sec. 158.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Moran‑-Mountain Lake CCC building renovation (87-1-049)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc140,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc23,000!tj1!tc163,000

 

 

 

          NEW SECTION.  Sec. 159.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Deception Pass‑-Renovate CCC buildings 2 and 3, Rosario (87-1-050)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc10,000!tj1!tc210,000

 

 

 

          NEW SECTION.  Sec. 160.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Fort Worden‑-Phased weatherization of facilities (87-2-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc350,000!tj1!tc450,000

 

 

 

          NEW SECTION.  Sec. 161.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Flaming geyser‑-Bridge relocation and installation, phase 2 (87-2-029)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc31,000

ORA‑-Federal!tj1!tc180,000

ORA‑-State!tj1!tc170,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc16,000!tc625,000!tc1,022,000

 

 

 

          NEW SECTION.  Sec. 162.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Auburn Game Farm‑-Initial park development (87-3-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc346,000!tj1!tc546,000

 

 

 

          NEW SECTION.  Sec. 163.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Green River Gorge‑-Acquisition, phased project (87-5-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc300,000

ORA‑-Federal!tj1!tc50,000

ORA‑-State!tj1!tc50,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,042,000!tc263,000!tc1,705,000

 

 

 

          NEW SECTION.  Sec. 164.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Potable water supply, omnibus facility contingency (88-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc69,000

LIRA‑-Water Sup Fac!tj1!tc46,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc30,000!tj1!tc145,000

 

 

 

          NEW SECTION.  Sec. 165.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Potable water supply, omnibus minor projects (88-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc360,000

LIRA‑-Water Sup Fac!tj1!tc240,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc93,000!tj1!tc693,000

 

 

 

          NEW SECTION.  Sec. 166.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Sequim Bay‑-Reservoir cover (88-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc24,000

LIRA‑-Water Sup Fac!tj1!tc16,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc92,000!tj1!tc132,000

 

 

 

          NEW SECTION.  Sec. 167.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Sequim Bay‑-Renovate park water system (88-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc48,000

LIRA‑-Water Sup Fac!tj1!tc32,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc110,000!tj1!tc190,000

 

 

 

          NEW SECTION.  Sec. 168.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Moran‑-Renovate potable water system (88-1-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc150,000

LIRA‑-Water Sup Fac!tj1!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc33,000!tj1!tc283,000

 

 

 

          NEW SECTION.  Sec. 169.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Sewer facilities, omnibus facility contingency (88-1-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA Waste Fac‑-1980!tj1!tc135,000

St Bldg Constr Acct!tj1!tc45,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc118,000!tj1!tc298,000

 

 

 

          NEW SECTION.  Sec. 170.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Sewer facilities, omnibus minor projects (88-1-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA Waste Fac‑-1980!tj1!tc228,000

St Bldg Constr Acct!tj1!tc76,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc32,000!tj1!tc336,000

 

 

 

          NEW SECTION.  Sec. 171.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Boat pumpout facilities, phased project (88-1-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA Waste Fac‑-1980!tj1!tc57,000

St Bldg Constr Acct!tj1!tc293,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc199,000!tj1!tc549,000

 

 

 

          NEW SECTION.  Sec. 172.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Ocean City‑-Connect to municipal sewer system (88-1-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixLIRA Waste Fac‑-1980!tj1!tc277,500

St Bldg Constr Acct!tj1!tc92,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc12,000!tj1!tc382,000

 

 

 

          NEW SECTION.  Sec. 173.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Boat traffic control markers and devices (88-1-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj1!tc20,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc90,000!tj1!tc110,000

 

 

 

          NEW SECTION.  Sec. 174.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          St. Edward‑-Main electrical code compliance (88-1-027)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc24,000!tj1!tc124,000

 

 

 

          NEW SECTION.  Sec. 175.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Fort Worden‑-Electrical service renovation to 7,200 volts (88-1-030)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc275,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc50,000!tj1!tc325,000

 

 

 

          NEW SECTION.  Sec. 176.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Boating facilities, omnibus facilities contingency (88-2-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj1!tc135,700

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc85,300!tj1!tc221,000

 

 

 

          NEW SECTION.  Sec. 177.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Boating facilities, omnibus minor projects (88-2-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj1!tc718,400

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc250,600!tj1!tc969,000

 

 

 

          NEW SECTION.  Sec. 178.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Park facilities renovation, omnibus facilities contingency (88-2-025)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc334,000

LIRA, Pub Rec Fac!tj1!tc43,249

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc347,751!tj1!tc725,000

 

 

 

          NEW SECTION.  Sec. 179.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Camp Wooten‑-Replace men's comfort station #23, add showers (88-2-041)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc157,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc109,700!tc266,700

 

 

 

          NEW SECTION.  Sec. 180.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Fort Worden‑-Ballon Hanger, replace roof, renovate interior (88-3-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc47,000!tj1!tc247,000

 

 

 

          NEW SECTION.  Sec. 181.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Camano Island‑-Point Lowell road relocation (88-3-043)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc100,000

Mot Veh Fund!tj2!tc619,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc102,000!tj1!tc821,000

 

 

 

          NEW SECTION.  Sec. 182.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Chief Timothy‑-Boat launch expansion (88-5-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc30,000!tj1!tc230,000

 

 

 

          NEW SECTION.  Sec. 183.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Moses Lake‑-Boat launch with parking and comfort station (88-5-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj1!tc175,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc17,000!tj1!tc192,000

 

 

 

          NEW SECTION.  Sec. 184.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Maryhill‑-Development (88-5-035)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc76,000!tj1!tc1,076,000

 

 

 

          NEW SECTION.  Sec. 185.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Ocean beaches‑-Acquisition of ocean beaches, phased project (88-5-036)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc100,000!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc450,000!tj1!tc750,000

 

 

 

          NEW SECTION.  Sec. 186.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Mount Spokane‑-Winter recreation facilities (88-5-041)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc20,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc63,000!tj1!tc83,000

 

 

 

          NEW SECTION.  Sec. 187.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Crystal Falls‑-Acquisition and development phase 2 (88-5-057)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc40,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc59,500!tc329,600!tc429,100

 

 

 

          NEW SECTION.  Sec. 188.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Blake Island‑-Fire protection system, concession building (89-1-050)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc119,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc119,000

 

 

 

          NEW SECTION.  Sec. 189.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-Water supply/irrigation (89-1-101)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc275,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc275,000

 

 

 

          NEW SECTION.  Sec. 190.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-Sanitary facilities (89-1-102)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc152,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc193,900!tc345,900

 

 

 

          NEW SECTION.  Sec. 191.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-Electrical (89-1-103)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc231,000

ORA‑-State!tj2!tc63,700

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc294,700

 

 

 

          NEW SECTION.  Sec. 192.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Moran‑-Renovate mountain lake dam (89-1-110)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc144,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc144,000

 

 

 

          NEW SECTION.  Sec. 193.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Compliance with safe drinking water act (89-1-116)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc441,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc441,000

 

 

 

          NEW SECTION.  Sec. 194.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Camp Wooten‑-Sewage renovation, phase 2 (89-1-122)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc138,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc138,000

 

 

 

          NEW SECTION.  Sec. 195.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Sacajawea‑-Modify river floats, revise piling anchorage system (89-1-129)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc192,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc192,000

 

 

 

          NEW SECTION.  Sec. 196.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Asbestos removal‑-Forts Worden, Flagler, Columbia (89-1-134)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc150,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc150,000

 

 

 

          NEW SECTION.  Sec. 197.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-Boating/marine construction (89-2-106)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc179,250

ORA‑-State!tj2!tc674,050

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc853,300

 

 

 

          NEW SECTION.  Sec. 198.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-General construction (89-2-107)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc560,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc858,000!tc1,418,000

 

 

 

          NEW SECTION.  Sec. 199.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-Specialized construction (89-2-109)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc219,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc219,000

 

 

 

          NEW SECTION.  Sec. 200.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Lake Sammamish‑-Boat launch repairs (89-2-139)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc114,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc114,000

 

 

 

          NEW SECTION.  Sec. 201.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-Site/environment/protection (89-3-104)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc300,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc300,000

 

 

 

          NEW SECTION.  Sec. 202.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-Acquisition (89-3-105)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc115,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc140,700!tc255,700

 

 

 

          NEW SECTION.  Sec. 203.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus minor projects‑-Weatherproofing (89-3-108)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc167,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc167,000

 

 

 

          NEW SECTION.  Sec. 204.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Fort Worden‑-Rebuild boat launch breakwater, dredge marina (89-3-135)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc315,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc315,000

 

 

 

          NEW SECTION.  Sec. 205.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Larabee‑-Acquisition of Clayton Beach (89-5-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,590,000

ORA‑-Federal!tj2!tc140,540

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc10,000!tj1!tc1,740,540

 

 

 

          NEW SECTION.  Sec. 206.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Hood Canal‑-Acquisition of property, phase 2 (89-5-111)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc49,000!tc393,000

ORA‑-State!tj2!tc60,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,000!tj1!tc503,000

 

 

 

          NEW SECTION.  Sec. 207.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Spokane Centennial Trail‑-Acquisition/initial development (89-5-112)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc120,000

ORA‑-Federal!tj2!tc119,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc239,000

 

 

 

          NEW SECTION.  Sec. 208.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Fort Casey‑-Acquisition of keystone spit, phase 2 (89-5-113)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc373,500!tc104,000

ORA‑-Federal!tj2!tc103,000

ORA‑-State!tj1!tc76,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc50,000!tj1!tc707,000

 

 

 

          NEW SECTION.  Sec. 209.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Belfair‑-Acquisition of adjoining property, phase 2 (89-5-114)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc32,000!tc193,000

ORA‑-Federal!tj2!tc27,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc18,000!tj1!tc270,000

 

 

 

          NEW SECTION.  Sec. 210.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Fort Canby‑-Initial development, Beards Hollow (89-5-115)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc289,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc289,000

 

 

 

          NEW SECTION.  Sec. 211.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Ocean Beach OBA‑-Comfort stations and parking at four locations (89-5-120)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc342,000

ORA‑-Federal!tj2!tc316,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc658,000

 

 

 

          NEW SECTION.  Sec. 212.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          State-wide‑-Omnibus facility contingency request (90-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc464,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc464,000

 

 

 

          NEW SECTION.  Sec. 213.              FOR THE STATE PARKS AND RECREATION COMMISSION

 

          Steamboat Rock‑-Random camp area, Jones Bay (95-2-182)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc150,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc150,000

 

 

 

          NEW SECTION.  Sec. 214.              FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION

 

          Grants to public agencies' recreation projects (90-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,000,000

ORA‑-Federal!tj1!tc150,000!tc800,000

ORA‑-State!tj1!tc1,068,604!tc6,436,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc21,513,197!tc12,000,000!tc42,967,801

 

 

 

          NEW SECTION.  Sec. 215.              FOR THE DEPARTMENT OF TRADE AND ECONOMIC DEVELOPMENT

 

          Community economic revitalization board (86-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc5,340,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc19,025,928!tc24,365,928

 

 

 

          NEW SECTION.  Sec. 216.              FOR THE DEPARTMENT OF TRADE AND ECONOMIC DEVELOPMENT

 

          Washington Technology Center‑-Funds for this project shall be transferred to and administered by the University of Washington (88-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc4,980,000!tc1,200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc9,922,000!tc16,102,000

 

 

 

          NEW SECTION.  Sec. 217.              FOR THE DEPARTMENT OF TRADE AND ECONOMIC DEVELOPMENT

 

          Washington State Agricultural Trade Center‑-Yakima (88-3-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc678,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc5,822,000!tj1!tc6,500,000

 

 

 

          NEW SECTION.  Sec. 218.              FOR THE DEPARTMENT OF TRADE AND ECONOMIC DEVELOPMENT

 

          Agricultural Complex‑-Yakima (89-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc322,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,678,000!tj1!tc2,000,000

 

 

 

          NEW SECTION.  Sec. 219.              FOR THE DEPARTMENT OF TRADE AND ECONOMIC DEVELOPMENT

 

          U.S. Olympic Academy (90-5-001)

 

          The appropriation in this section is subject to the following conditions and limitations:

          (1) Expenditures made under this appropriation shall not exceed twenty-five percent of the total project design and construction costs, and shall not exceed $5,000,000.

          (2) The local match, which shall not be less than seventy-five percent of the total project design and construction costs, shall be cash and the fair market value of donated property.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc5,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc5,000,000

 

 

 

          NEW SECTION.  Sec. 220.              FOR THE DEPARTMENT OF TRADE AND ECONOMIC DEVELOPMENT

 

          Mt. St. Helens Road and Visitor Center (90-5-002)

 

          The appropriation in this section is subject to the following conditions and limitations:

          (1) This appropriation shall fund no more than twenty-five percent of the total project cost.

          (2) Any funds provided for this project by Cowlitz county shall reduce this appropriation by a like amount.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc5,900,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc5,900,000

 

 

 

          NEW SECTION.  Sec. 221.              FOR THE STATE CONSERVATION COMMISSION

 

          Water quality projects (90-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWater Quality Acct!tj1!tc337,700!tc2,146,300

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,524,300!tc4,400,000!tc8,408,300

@la

                                                                          (End of part)

 

!np

                                                                              PART 4

                                                                                  

NATURAL RESOURCES - CONTINUED

 

!af98,400 @lb

 

          NEW SECTION.  Sec. 222.              FOR THE DEPARTMENT OF FISHERIES

 

          Habitat‑-Salmon enhancement program (77-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSalmon Enhancement Acct!tj1!tc221,100

St Bldg Constr Acct!tj2!tc921,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,897,587!tj1!tc5,039,687

 

 

 

          NEW SECTION.  Sec. 223.              FOR THE DEPARTMENT OF FISHERIES

 

          Replacements and alterations (77-2-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFish Cap Proj Acct!tj1!tc2,263

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,996,688!tj1!tc3,998,951

 

 

 

          NEW SECTION.  Sec. 224.              FOR THE DEPARTMENT OF FISHERIES

 

          Hood Canal Bridge‑-Public fishing access (79-2-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc47,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc447,000!tj1!tc494,000

 

 

 

          NEW SECTION.  Sec. 225.              FOR THE DEPARTMENT OF FISHERIES

 

          Oakland Bay tideland access design and construction (81-5-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc11,000

ORA‑-Federal!tj1!tc90,000

ORA‑-State!tj1!tc79,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc180,000

 

 

 

          NEW SECTION.  Sec. 226.              FOR THE DEPARTMENT OF FISHERIES

 

          Health, safety and code compliance (86-1-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc105,000!tc850,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc344,000!tc500,000!tc1,799,000

 

 

 

          NEW SECTION.  Sec. 227.              FOR THE DEPARTMENT OF FISHERIES

 

          Towhead Island public access‑-Renovation (86-2-028)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-Federal!tj1!tc20,000

ORA‑-State!tj1!tc191,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc211,000

 

 

 

          NEW SECTION.  Sec. 228.              FOR THE DEPARTMENT OF FISHERIES

 

          Issaquah Hatchery Interpretative Center (86-2-029)

 

 

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc35,200

ORA‑-Federal!tj1!tc53,000

ORA‑-State!tj1!tc17,800

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc24,000!tj1!tc130,000

 

 

 

          NEW SECTION.  Sec. 229.              FOR THE DEPARTMENT OF FISHERIES

 

          Minor capital projects‑-Salmon (86-3-022)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc136,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc286,000!tj1!tc422,000

 

 

 

          NEW SECTION.  Sec. 230.              FOR THE DEPARTMENT OF FISHERIES

 

          Minor capital projects‑-Shellfish (86-3-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc50,000

Fish Cap Proj Acct!tj1!tc5,975

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc380,597!tj1!tc436,572

 

 

 

          NEW SECTION.  Sec. 231.              FOR THE DEPARTMENT OF FISHERIES

 

          Paving and maintenance‑-Asphalt ponds (86-3-024)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc10,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc285,401!tj1!tc295,401

 

 

 

          NEW SECTION.  Sec. 232.              FOR THE DEPARTMENT OF FISHERIES

 

          Bremerton public fishing pier‑-Design and construction (86-3-027)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc89,000

ORA‑-Federal!tj1!tc410,000

ORA‑-State!tj1!tc285,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc36,000!tj1!tc820,000

 

 

 

          NEW SECTION.  Sec. 233.              FOR THE DEPARTMENT OF FISHERIES

 

          Willapa Hatchery‑-New main pipeline (86-3-030)

 

 

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc12,640

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc373,000!tj1!tc385,640

 

 

 

          NEW SECTION.  Sec. 234.              FOR THE DEPARTMENT OF FISHERIES

 

          Patrol seized gear storage (86-3-033)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc50,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc48,000!tj1!tc98,000

 

 

 

          NEW SECTION.  Sec. 235.              FOR THE DEPARTMENT OF FISHERIES

 

          Hood Canal boat access development (86-3-035)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-Federal!tj1!tc30,000

ORA‑-State!tj1!tc270,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc300,000

 

 

 

          NEW SECTION.  Sec. 236.              FOR THE DEPARTMENT OF FISHERIES

 

          Hood Canal Smelt Beach acquisition (86-3-036)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-Federal!tj1!tc150,000

ORA‑-State!tj1!tc150,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc300,000

 

 

 

          NEW SECTION.  Sec. 237.              FOR THE DEPARTMENT OF FISHERIES

 

          Point Whitney Beach access acquisition (86-3-037)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc250,000

ORA‑-Federal!tj2!tc250,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc255,000!tc150,000!tc905,000

 

 

 

          NEW SECTION.  Sec. 238.              FOR THE DEPARTMENT OF FISHERIES

 

          Knappton public access (86-3-038)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-Federal!tj1!tc54,000

ORA‑-State!tj1!tc55,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc109,000

 

 

 

          NEW SECTION.  Sec. 239.              FOR THE DEPARTMENT OF FISHERIES

 

          McAllister‑-Improvements (88-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc246,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc13,000!tj1!tc259,000

 

 

 

          NEW SECTION.  Sec. 240.              FOR THE DEPARTMENT OF FISHERIES

 

          Minor capital projects‑-Salmon north (88-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc308,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc132,000!tj1!tc440,000

 

 

 

          NEW SECTION.  Sec. 241.              FOR THE DEPARTMENT OF FISHERIES

 

          Minor capital projects‑-Salmon south (88-2-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral Fund‑-Federal!tj1!tc853,000

St Bldg Constr Acct!tj1!tc387,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc11,000!tj1!tc1,251,000

 

 

 

          NEW SECTION.  Sec. 242.              FOR THE DEPARTMENT OF FISHERIES

 

          Minor capital projects‑-Salmon coast (88-2-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc40,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc152,200!tj1!tc192,200

 

 

 

          NEW SECTION.  Sec. 243.              FOR THE DEPARTMENT OF FISHERIES

 

          Salmon culture‑-Repair and replacement (88-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc105,000!tj1!tc305,000

 

 

 

          NEW SECTION.  Sec. 244.              FOR THE DEPARTMENT OF FISHERIES

 

          Concrete ponds‑-Repair and replacement (88-2-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc137,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc666,000!tj1!tc803,000

 

 

 

          NEW SECTION.  Sec. 245.              FOR THE DEPARTMENT OF FISHERIES

 

          Small repairs and improvements (88-2-019)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral Fund‑-Federal!tj1!tc159,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc159,000

 

 

 

          NEW SECTION.  Sec. 246.              FOR THE DEPARTMENT OF FISHERIES

 

          Clam and Oyster Beach enhancement (88-5-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,013,000!tc1,200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc200,000!tc1,200,000!tc2,413,000

 

 

 

          NEW SECTION.  Sec. 247.              FOR THE DEPARTMENT OF FISHERIES

 

          Fish protection facilities (88-5-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc50,000!tc235,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc154,000!tc400,000!tc839,000

 

 

 

          NEW SECTION.  Sec. 248.              FOR THE DEPARTMENT OF FISHERIES

 

          Columbia River‑-Fishing access (88-5-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc186,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc129,000!tj1!tc315,000

 

 

 

          NEW SECTION.  Sec. 249.              FOR THE DEPARTMENT OF FISHERIES

 

          Coast and Puget Sound Salmon enhancement (88-5-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSalmon Enhancement Acct!tj1!tc2,020,000

St Bldg Constr Acct!tj2!tc2,500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,000,000!tc3,750,000!tc7,770,000

 

 

 

          NEW SECTION.  Sec. 250.              FOR THE DEPARTMENT OF FISHERIES

 

          Shorefishing access development (88-5-018)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc623,000!tc450,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc250,000!tc1,273,000!tc2,596,000

 

 

 

          NEW SECTION.  Sec. 251.              FOR THE DEPARTMENT OF FISHERIES

 

          South Sound net pen support facility (90-2-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc343,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc343,000

 

 

 

          NEW SECTION.  Sec. 252.              FOR THE DEPARTMENT OF FISHERIES

 

          Humptulips upgrade intake dam (90-2-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc213,100

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc213,100

 

 

 

          NEW SECTION.  Sec. 253.              FOR THE DEPARTMENT OF FISHERIES

 

          Salmon culture minor works projects (90-2-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc655,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc655,000

 

 

 

          NEW SECTION.  Sec. 254.              FOR THE DEPARTMENT OF FISHERIES

 

          Habitat management shop building  (90-2-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc435,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc435,000

 

 

 

          NEW SECTION.  Sec. 255.              FOR THE DEPARTMENT OF FISHERIES

 

          Field services‑-Minor works (90-2-015)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc235,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc100,000!tc335,000

 

 

 

          NEW SECTION.  Sec. 256.              FOR THE DEPARTMENT OF FISHERIES

 

          Salmon culture‑-Minor capital (90-2-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc668,700

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,350,000!tc2,018,700

 

 

 

          NEW SECTION.  Sec. 257.              FOR THE DEPARTMENT OF FISHERIES

 

          George Adams, water supply  (90-2-019)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc175,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc175,000

 

 

 

          NEW SECTION.  Sec. 258.              FOR THE DEPARTMENT OF FISHERIES

 

          Ilwaco boat access expansion  (90-2-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc300,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc300,000

 

 

 

          NEW SECTION.  Sec. 259.              FOR THE DEPARTMENT OF FISHERIES

 

          Bonneville pool access expansion (90-2-028)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc100,000!tc200,000

 

 

 

          NEW SECTION.  Sec. 260.              FOR THE DEPARTMENT OF FISHERIES

 

          Property acquisition  (90-3-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc330,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc330,000

 

 

 

          NEW SECTION.  Sec. 261.              FOR THE DEPARTMENT OF FISHERIES

 

          Shellfish surveys and Point Whitney repairs (90-3-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc175,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc350,000!tc525,000

 

 

 

          NEW SECTION.  Sec. 262.              FOR THE DEPARTMENT OF FISHERIES

 

          Point Whitney‑-Property acquisition (90-3-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc150,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc150,000

 

 

 

          NEW SECTION.  Sec. 263.              FOR THE DEPARTMENT OF FISHERIES

 

          Cedar River spawning channel (90-5-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc800,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc2,000,000!tc2,800,000

 

 

 

          NEW SECTION.  Sec. 264.              FOR THE DEPARTMENT OF FISHERIES

 

          Strait of Juan De Fuca shoreline acquisition (90-5-025)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc350,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc200,000!tc550,000

 

 

 

          NEW SECTION.  Sec. 265.              FOR THE DEPARTMENT OF FISHERIES

 

          Kingston boat launch development (90-5-027)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc100,000

 

 

 

          NEW SECTION.  Sec. 266.              FOR THE DEPARTMENT OF WILDLIFE

 

          Aberdeen Fish Hatchery expansion (89-5-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGame Spec Wildlife Acct!tj1!tc700,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc119,000!tj1!tc819,000

 

 

 

          NEW SECTION.  Sec. 267.              FOR THE DEPARTMENT OF WILDLIFE

 

          Asbestos abatement health safety and code compliance, phase 1 (90-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc600,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,200,000!tc1,800,000

 

 

 

          NEW SECTION.  Sec. 268.              FOR THE DEPARTMENT OF WILDLIFE

 

          Public fishing access minor works repair (90-1-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-Federal!tj1!tc200,000!tc500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc216,000!tc1,300,000!tc2,216,000

 

 

 

          NEW SECTION.  Sec. 269.              FOR THE DEPARTMENT OF WILDLIFE

 

          Emergency repair and replacement (90-2-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-State!tj2!tc300,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc303,000!tc900,000!tc1,503,000

 

 

 

          NEW SECTION.  Sec. 270.              FOR THE DEPARTMENT OF WILDLIFE

 

          Facility maintenance small repair and improvements (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-State!tj2!tc500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc629,000!tc1,100,000!tc2,229,000

 

 

 

          NEW SECTION.  Sec. 271.              FOR THE DEPARTMENT OF WILDLIFE

 

          Hatchery renovation and improvement (90-2-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,150,000

Wildlife Acct‑-Federal!tj1!tc400,000!tc1,100,000

Wildlife Acct‑-State!tj2!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc915,000!tc13,000,000!tc17,565,000

 

 

 

          NEW SECTION.  Sec. 272.              FOR THE DEPARTMENT OF WILDLIFE

 

          Redevelopment of public fishing access sites (IAC) (90-2-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc1,126,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc2,115,000!tc3,241,000

 

 

 

          NEW SECTION.  Sec. 273.              FOR THE DEPARTMENT OF WILDLIFE

 

          Development of public fishing access sites (IAC) (90-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc294,000

ORA‑-State!tj2!tc136,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc300,000!tc730,000

 

 

 

          NEW SECTION.  Sec. 274.              FOR THE DEPARTMENT OF WILDLIFE

 

          Wildlife area repair and development (90-2-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-State!tj2!tc250,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc500,000!tc750,000

 

 

 

          NEW SECTION.  Sec. 275.              FOR THE DEPARTMENT OF WILDLIFE

 

          Wells wildlife area repair and improvements (90-2-018)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGame Spec Wildlife Acct!tj2!tc50,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc100,000!tc100,000!tc250,000

 

 

 

          NEW SECTION.  Sec. 276.              FOR THE DEPARTMENT OF WILDLIFE

 

          State-wide fencing repair and replacement (90-3-015)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-State!tj2!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc368,000!tc2,000,000!tc3,368,000

 

 

 

          NEW SECTION.  Sec. 277.              FOR THE DEPARTMENT OF WILDLIFE

 

          Migratory waterfowl habitat acquisition (90-5-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-State!tj2!tc350,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc396,000!tc700,000!tc1,446,000

 

 

 

          NEW SECTION.  Sec. 278.              FOR THE DEPARTMENT OF WILDLIFE

 

          Acquisition of critical habitat (90-5-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-State!tj2!tc250,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc500,000!tc750,000

 

 

 

          NEW SECTION.  Sec. 279.              FOR THE DEPARTMENT OF WILDLIFE

 

          Acquisition of critical water oriented access (IAC) (90-5-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc20,250

Wildlife Acct‑-Federal!tj2!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc120,250

 

 

 

          NEW SECTION.  Sec. 280.              FOR THE DEPARTMENT OF WILDLIFE

 

          Acquisition of wildlife habitat (90-5-012)

 

          The appropriation in this section is subject to the following conditions and limitations:  No moneys appropriated for this project may be expended without first selling owned land of equal or greater value.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-State!tj2!tc600,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc800,000!tc1,400,000

 

 

 

          NEW SECTION.  Sec. 281.              FOR THE DEPARTMENT OF WILDLIFE

 

          Migratory waterfowl habitat development (90-5-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-State!tj2!tc300,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc362,000!tc700,000!tc1,362,000

 

 

 

          NEW SECTION.  Sec. 282.              FOR THE DEPARTMENT OF WILDLIFE

 

          Habitat enhancement fund (90-5-019)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWildlife Acct‑-Private/local!tj2!tc500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,000,000!tc1,500,000

 

 

 

          NEW SECTION.  Sec. 283.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Right-of-way acquisition (86-3-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc213,000

Res Mgmt Cost Acct!tj2!tc577,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,646,000!tc950,000!tc3,386,000

 

 

 

          NEW SECTION.  Sec. 284.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Unforeseen emergency repairs, irrigation (86-3-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc492,000!tc400,000!tc1,092,000

 

 

 

          NEW SECTION.  Sec. 285.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Commercial development and electronics (86-3-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc420,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc20,000!tc400,000!tc840,000

 

 

 

          NEW SECTION.  Sec. 286.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Recreation sites renovation (86-3-018)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORV Acct!tj1!tc300,000

ORA‑-State!tj1!tc300,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc123,000!tj1!tc723,000

 

 

 

          NEW SECTION.  Sec. 287.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Aquatic land enhancement (86-3-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixAquatic Lands Acct!tj1!tc1,150,000!tc5,040,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,607,000!tc14,400,000!tc22,197,000

 

 

 

          NEW SECTION.  Sec. 288.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Land bank (86-4-003)

 

          The appropriation in this section is subject to the following conditions and limitations:  No moneys appropriated for this project may be expended without first selling owned land of equal or greater value.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc12,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc11,440,000!tc30,000,000!tc53,440,000

 

 

 

          NEW SECTION.  Sec. 289.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          State-wide emergency repairs (88-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc8,600

Res Mgmt Cost Acct!tj2!tc32,300

St Bldg Constr Acct!tj2!tc18,300

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc54,000!tc135,900!tc249,100

 

 

 

          NEW SECTION.  Sec. 290.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          State-wide nonemergency repairs (88-2-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc8,700

Res Mgmt Cost Acct!tj2!tc32,900

St Bldg Constr Acct!tj2!tc18,700

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc55,000!tc138,500!tc253,800

 

 

 

          NEW SECTION.  Sec. 291.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Commercial development/L.I.D. (88-2-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc710,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc745,000!tc1,420,000!tc2,875,000

 

 

 

          NEW SECTION.  Sec. 292.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Timber‑-Fish‑-Wildlife (88-2-021)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc100,000!tj1!tc300,000

 

 

 

          NEW SECTION.  Sec. 293.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Natural resources conservation areas (88-2-060)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixConservation Area Acct!tj1!tc4,000,000!tc8,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,900,000!tc16,000,000!tc31,900,000

 

          $8,000,000 of this appropriation is subject to the extension of the additional real property excise tax beyond June 30, 1989 (RCW 82.45.060(2)).

 

 

          NEW SECTION.  Sec. 294.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          NAP property purchases (88-2-061)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixConservation Area Acct!tj1!tc2,000,000!tc4,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,000,000!tc8,000,000!tc16,000,000

 

          $4,000,000 of this appropriation is subject to the extension of the additional real property excise tax beyond June 30, 1989 (RCW 82.45.060(2)).

 

 

          NEW SECTION.  Sec. 295.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Seed orchard irrigation (89-2-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc19,500

Res Mgmt Cost Acct!tj2!tc45,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc165,000!tc160,000!tc390,000

 

 

 

          NEW SECTION.  Sec. 296.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Irrigation development (89-2-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj1!tc150,000!tc452,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc200,000!tc802,500

 

 

 

          NEW SECTION.  Sec. 297.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Management roads (89-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj1!tc122,400

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc305,600!tj1!tc428,000

 

 

 

          NEW SECTION.  Sec. 298.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Communication site maintenance (89-2-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc150,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc177,000!tc300,000!tc627,000

 

 

 

          NEW SECTION.  Sec. 299.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Real estate improved property minor works (89-2-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc25,000

Res Mgmt Cost Acct!tj2!tc365,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc250,000!tc780,000!tc1,420,000

 

 

 

          NEW SECTION.  Sec. 300.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Recreation site renovation (89-3-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc500,000

ORA‑-State!tj1!tc500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc148,000!tj1!tc1,148,000

 

 

 

          NEW SECTION.  Sec. 301.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Wharf demolition/dock renovation (90-1-403)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc200,000

 

 

 

          NEW SECTION.  Sec. 302.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Asbestos surveys/removal (90-1-703)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc35,700

Res Mgmt Cost Acct!tj2!tc49,200

St Bldg Constr Acct!tj2!tc30,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc114,900

 

 

 

          NEW SECTION.  Sec. 303.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Environmental cleanup (90-1-704)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc75,900

Res Mgmt Cost Acct!tj2!tc273,500

St Bldg Constr Acct!tj2!tc235,600

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc554,900!tc1,139,900

 

 

 

          NEW SECTION.  Sec. 304.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Environmental protection (90-1-706)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc13,700

Res Mgmt Cost Acct!tj2!tc119,300

St Bldg Constr Acct!tj2!tc151,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc284,000!tc568,000

 

 

 

          NEW SECTION.  Sec. 305.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          NE city code compliance (90-1-708)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc31,500

St Bldg Constr Acct!tj2!tc15,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc47,000

 

 

 

          NEW SECTION.  Sec. 306.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Regional cold storage (90-2-310)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixFor Dev Acct!tj2!tc150,000

Res Mgmt Cost Acct!tj2!tc362,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc142,000!tc654,000

 

 

 

          NEW SECTION.  Sec. 307.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Irrigation pipeline replacement (90-2-311)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc532,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc400,000!tc932,000

 

 

 

          NEW SECTION.  Sec. 308.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Administration sites repairs (90-2-312)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc65,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc130,000!tc195,000

 

 

 

          NEW SECTION.  Sec. 309.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Bridge and road replacement (90-2-503)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORV Acct!tj2!tc15,000

For Dev Acct!tj2!tc15,000

Res Mgmt Cost Acct!tj2!tc35,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc2,240,000!tc3,512,000

 

 

 

          NEW SECTION.  Sec. 310.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Woodard Bay NRCA fencing dev. (90-3-103)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc200,000

 

 

 

          NEW SECTION.  Sec. 311.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Dishman Hills protection dev. (90-3-104)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc100,000

 

 

 

          NEW SECTION.  Sec. 312.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Natural area preserves management (90-3-105)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc150,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc200,000!tc350,000

 

 

 

          NEW SECTION.  Sec. 313.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Construct and improve recreation sites (90-5-201)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORV Acct!tj2!tc117,000

St Bldg Constr Acct!tj2!tc363,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc480,000

 

 

 

          NEW SECTION.  Sec. 314.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Seattle waterfront phase 1 dev. (90-5-202)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORA‑-State!tj2!tc750,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc750,000!tc1,500,000

 

 

 

          NEW SECTION.  Sec. 315.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Woodard Bay health and safety dev. (90-5-203)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc250,000

ORA‑-Federal!tj2!tc250,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc500,000

 

 

 

          NEW SECTION.  Sec. 316.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Long Lake phase 2 dev. (90-5-204)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixORV Acct!tj2!tc150,000

ORA‑-State!tj2!tc205,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc355,000

 

 

 

          NEW SECTION.  Sec. 317.              FOR THE DEPARTMENT OF NATURAL RESOURCES

 

          Geoduck Hatchery (90-5-402)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixRes Mgmt Cost Acct!tj2!tc333,927

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc333,927

@la

                                                                          (End of part)

 

!np !af98,500

                                                                              PART 5

                                                                                  

NATURAL RESOURCES - CONTINUED

 

@lb

 

          NEW SECTION.  Sec. 318.              FOR THE STATE AND TRADE CONVENTION CENTER

 

          Washington State Convention and Trade Center (83-5-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixConv Cntr Acct!tj1!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc35,618,000!tj1!tc36,618,000

 

 

 

          NEW SECTION.  Sec. 319.              FOR THE STATE AND TRADE CONVENTION CENTER

 

          Project reserves and contingency funds (89-5-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixConv Cntr Acct!tj1!tc3,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,765,000!tj1!tc4,765,000

 

 

 

          NEW SECTION.  Sec. 320.              FOR THE STATE AND TRADE CONVENTION CENTER

 

          Conversion of retail space to meeting rooms (89-5-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixConv Cntr Acct!tj1!tc12,250,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc750,000!tj1!tc13,000,000

 

 

 

          NEW SECTION.  Sec. 321.              FOR THE STATE AND TRADE CONVENTION CENTER

 

          Expansion of the nine hundred level (89-5-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixConv Cntr Acct!tj1!tc12,750,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc550,000!tj1!tc13,300,000

 

 

 

          NEW SECTION.  Sec. 322.              FOR THE STATE AND TRADE CONVENTION CENTER

 

          Purchase of McKay parcel (89-5-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixConv Cntr Acct!tj1!tc10,400,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc10,400,000

 

 

 

          NEW SECTION.  Sec. 323.              FOR THE STATE AND TRADE CONVENTION CENTER

 

          Eagles building:  Exterior cleanup and repair (89-5-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixConv Cntr Acct!tj1!tc300,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc300,000

@la

                                                                          (End of part)

 

!np

                                                                              PART 6

                                                                                  

TRANSPORTATION

 

!af98,600 @lb

 

          NEW SECTION.  Sec. 324.              FOR THE WASHINGTON STATE PATROL

 

          Crime laboratory renovation‑-Seattle (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc703,900

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc15,000!tj1!tc718,900

 

 

 

          NEW SECTION.  Sec. 325.              FOR THE WASHINGTON STATE PATROL

 

          Expand and renovate laboratory‑-Tacoma (90-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Const Acct!tj2!tc165,200

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc6,000!tj1!tc171,200

 

 

 

          NEW SECTION.  Sec. 326.              FOR THE WASHINGTON STATE PATROL

 

          Crime laboratory renovation‑-Spokane (90-2-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc287,200

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc10,000!tj1!tc297,200

 

 

 

          NEW SECTION.  Sec. 327.              FOR THE DEPARTMENT OF TRANSPORTATION

 

          Acquisition of dredge spoils sites (83-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,369,430

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,420,000!tj1!tc4,789,430

 

 

 

          NEW SECTION.  Sec. 328.              FOR THE DEPARTMENT OF TRANSPORTATION

 

          Retention dam:  Green/Toutle River site acquisition (87-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc5,387,043

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc13,289,430!tj1!tc18,676,473

 

 

 

          NEW SECTION.  Sec. 329.              FOR THE DEPARTMENT OF TRANSPORTATION

 

          Freight rail assistance and banking (90-5-001)

 

          The appropriations in this section are subject to the following conditions and limitations:

          (1) $4,700,000 from the essential rail assistance account shall be distributed to county rail districts and port districts only for the purposes of acquiring, maintaining, or improving branch lines.

          (2) $2,200,000 from the essential rail bank account shall be used to provide the department with up to eighty percent matching funds to purchase unused rail rights of way.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixEss Rail Assis Acct!tj2!tc4,700,000

Ess Rail Bank Acct!tj2!tc2,200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc10,000,000!tc16,900,000

@la

                                                                          (End of part)

 

!np

                                                                              PART 7

                                                                                  

EDUCATION

 

!af98,700 @lb

 

          NEW SECTION.  Sec. 330.              FOR THE STATE BOARD OF EDUCATION

 

          Public school building construction:  1979 (79-3-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj1!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc66,425!tj1!tc166,425

 

 

 

          NEW SECTION.  Sec. 331.              FOR THE STATE BOARD OF EDUCATION

 

          Public school building construction:  1981 (81-3-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj1!tc140,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc163,758!tj1!tc303,758

 

 

 

          NEW SECTION.  Sec. 332.              FOR THE STATE BOARD OF EDUCATION

 

          Public school building construction:  1983 (83-3-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj1!tc600,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,000,000!tj1!tc1,600,000

 

 

 

          NEW SECTION.  Sec. 333.              FOR THE STATE BOARD OF EDUCATION

 

          Public school building construction:  1985-87 (86-4-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj1!tc3,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc29,000,000!tj1!tc32,000,000

 

 

 

          NEW SECTION.  Sec. 334.              FOR THE STATE BOARD OF EDUCATION

 

          Planning grants:  1985-87 (86-4-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj1!tc152,275

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc200,000!tj1!tc352,275

 

 

 

          NEW SECTION.  Sec. 335.              FOR THE STATE BOARD OF EDUCATION

 

          Artwork grants:  1985-87 (86-4-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj1!tc150,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc144,000!tj1!tc294,000

 

 

 

          NEW SECTION.  Sec. 336.              FOR THE STATE BOARD OF EDUCATION

 

          Public school building construction:  1987 (88-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj1!tc50,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc158,262,000!tj1!tc208,262,000

 

 

 

          NEW SECTION.  Sec. 337.              FOR THE STATE BOARD OF EDUCATION

 

          Darrington school district:  New elementary and middle school (89-2-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj1!tc3,405,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc3,405,000

 

 

 

          NEW SECTION.  Sec. 338.              FOR THE STATE BOARD OF EDUCATION

 

          Public school building construction:  1989 (90-2-001)

 

          The appropriation in this section is subject to the following condition and limitation:  A maximum of $1,050,000 may be spent for state administration of school construction funding.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCommon School Constr Fund!tj2!tc147,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc147,000,000

 

 

 

          NEW SECTION.  Sec. 339.              FOR THE STATE BOARD OF EDUCATION

 

          Common school disbursement limit

 

          A maximum of $147,000,000 of the appropriations and reappropriations in sections 701 through 709 of this act may be disbursed during the 1989-91 biennium.

 

 

 

          NEW SECTION.  Sec. 340.              FOR THE WASHINGTON INSTITUTE OF APPLIED TECHNOLOGY

 

          Vocational Technology Center (88-2-003)

 

 

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc475,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc5,525,000!tj1!tc6,000,000

 

 

 

          NEW SECTION.  Sec. 341.              FOR THE STATE SCHOOL FOR THE BLIND

 

          Automatic sliding doors‑-Irwin education building (90-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc14,580

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc14,580

 

 

 

          NEW SECTION.  Sec. 342.              FOR THE STATE SCHOOL FOR THE BLIND

 

          Replace heating and ventilation system and roof repairs:  Irwin building (90-2-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc130,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc130,000

 

 

 

          NEW SECTION.  Sec. 343.              FOR THE STATE SCHOOL FOR THE BLIND

 

          Driveway/parking lot repaving (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc21,270

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc21,270

 

 

 

          NEW SECTION.  Sec. 344.              FOR THE STATE SCHOOL FOR THE DEAF

 

          Remove and replace three transformers/clerk (90-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc36,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc36,500

 

 

 

          NEW SECTION.  Sec. 345.              FOR THE STATE SCHOOL FOR THE DEAF

 

          Wheelchair lifts‑-Clark Hall, vocational, Northrup School (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc147,100

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc147,100

 

 

 

          NEW SECTION.  Sec. 346.              FOR THE STATE SCHOOL FOR THE DEAF

 

          Roof repair (91-2-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc50,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc50,000

 

 

 

          NEW SECTION.  Sec. 347.              FOR THE UNIVERSITY OF WASHINGTON

 

          Safety‑-Fire code, PCB and life safety (86-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc3,125,000

UW Bldg Acct!tj2!tc8,600,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,582,000!tc14,000,000!tc30,507,000

 

 

 

          NEW SECTION.  Sec. 348.              FOR THE UNIVERSITY OF WASHINGTON

 

          Safety‑-Asbestos removal (86-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,008,000

UW Bldg Acct!tj1!tc808,000!tc5,500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,184,000!tc20,000,000!tc29,500,000

 

 

 

          NEW SECTION.  Sec. 349.              FOR THE UNIVERSITY OF WASHINGTON

 

          Safety‑-General (86-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc798,382

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc201,618!tj1!tc1,000,000

 

 

 

          NEW SECTION.  Sec. 350.              FOR THE UNIVERSITY OF WASHINGTON

 

          Minor works‑-Building renewal (86-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,090,000

UW Bldg Acct!tj1!tc776,000!tc9,733,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc5,748,325!tc26,000,000!tc49,597,325

 

 

 

          NEW SECTION.  Sec. 351.              FOR THE UNIVERSITY OF WASHINGTON

 

          Fisheries repairs and expansion (86-1-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc1,868,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,882,805!tj1!tc5,750,805

 

 

 

          NEW SECTION.  Sec. 352.              FOR THE UNIVERSITY OF WASHINGTON

 

          HSC G Court, H Wing and I Court addition (86-2-021)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc20,300,000!tc24,692,000

UW Bldg Acct!tj1!tc3,500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,011,000!tj1!tc49,503,000

 

 

 

          NEW SECTION.  Sec. 353.              FOR THE UNIVERSITY OF WASHINGTON

 

          Minor works‑-Program renewal (86-3-005)

 

          The appropriation in this section is subject to the following condition and limitation:  No funds shall be expended for land acquisition.

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixUW Bldg Acct!tj1!tc969,000!tc9,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc10,483,000!tc42,270,000!tc69,141,000

 

 

 

          NEW SECTION.  Sec. 354.              FOR THE UNIVERSITY OF WASHINGTON

 

          Energy conservation (86-4-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc750,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc250,000!tj1!tc1,000,000

 

 

 

          NEW SECTION.  Sec. 355.              FOR THE UNIVERSITY OF WASHINGTON

 

          Electrical distribution system (88-1-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,000,000!tc5,139,000!tc6,639,000

 

 

 

          NEW SECTION.  Sec. 356.              FOR THE UNIVERSITY OF WASHINGTON

 

          Power plant chiller (88-1-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc180,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc820,000!tj1!tc1,000,000

 

 

 

          NEW SECTION.  Sec. 357.              FOR THE UNIVERSITY OF WASHINGTON

 

          Power plant stack replacement (88-1-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixUW Bldg Acct!tj1!tc1,200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc300,000!tj1!tc1,500,000

 

 

 

          NEW SECTION.  Sec. 358.              FOR THE UNIVERSITY OF WASHINGTON

 

          Suzzallo Library addition (88-2-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc16,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc15,283,000!tj1!tc32,583,000

 

 

 

          NEW SECTION.  Sec. 359.              FOR THE UNIVERSITY OF WASHINGTON

 

          Communications building renovation (88-2-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc4,300,000!tc1,015,000

UW Bldg Acct!tj2!tc1,167,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc255,000!tj1!tc6,737,000

 

 

 

          NEW SECTION.  Sec. 360.              FOR THE UNIVERSITY OF WASHINGTON

 

          Power plant boiler retrofit (88-4-024)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixUW Bldg Acct!tj1!tc1,600,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc700,000!tj1!tc2,300,000

 

 

 

          NEW SECTION.  Sec. 361.              FOR THE UNIVERSITY OF WASHINGTON

 

          Emergency power generation (90-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc11,110,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc11,110,000

 

 

 

          NEW SECTION.  Sec. 362.              FOR THE UNIVERSITY OF WASHINGTON

 

          Physics I (90-2-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc4,155,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc4,155,000

 

 

 

          NEW SECTION.  Sec. 363.              FOR THE UNIVERSITY OF WASHINGTON

 

          Chemistry I (90-2-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc39,152,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc39,152,000

 

 

 

          NEW SECTION.  Sec. 364.              FOR THE UNIVERSITY OF WASHINGTON

 

          Electrical engineering building addition (90-2-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc3,111,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc3,111,000

 

 

 

          NEW SECTION.  Sec. 365.              FOR THE UNIVERSITY OF WASHINGTON

 

          Computer sciences building (92-2-024)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,000,000

 

 

 

          NEW SECTION.  Sec. 366.              FOR WASHINGTON STATE UNIVERSITY

 

          Chemistry building, phase 2 (86-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixH Ed Construct Acct!tj1!tc982,000

WSU Bldg Acct!tj1!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc12,810,000!tj1!tc14,792,000

 

 

 

          NEW SECTION.  Sec. 367.              FOR WASHINGTON STATE UNIVERSITY

 

          Food‑-Human nutrition facility‑-Equipment (86-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj1!tc1,977,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,517,000!tj1!tc4,494,000

 

 

 

          NEW SECTION.  Sec. 368.              FOR WASHINGTON STATE UNIVERSITY

 

          McCoy Hall capital renewal (86-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixH Ed Construct Acct!tj1!tc111,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,138,000!tj1!tc2,249,000

 

 

 

          NEW SECTION.  Sec. 369.              FOR WASHINGTON STATE UNIVERSITY

 

          Science Hall renewal, phase 2 (86-1-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixH Ed Construct Acct!tj1!tc2,807,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc8,902,000!tj1!tc11,709,000

 

 

 

          NEW SECTION.  Sec. 370.              FOR WASHINGTON STATE UNIVERSITY

 

          Neill Hall renewal (86-1-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj1!tc2,191,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,059,000!tj1!tc3,250,000

 

 

 

          NEW SECTION.  Sec. 371.              FOR WASHINGTON STATE UNIVERSITY

 

          Minor capital improvement (88-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj1!tc1,896,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,827,000!tj1!tc4,723,000

 

 

 

          NEW SECTION.  Sec. 372.              FOR WASHINGTON STATE UNIVERSITY

 

          Minor capital renewal (88-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,109,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,593,000!tj1!tc5,702,000

 

 

 

          NEW SECTION.  Sec. 373.              FOR WASHINGTON STATE UNIVERSITY

 

          Preplanning (88-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj1!tc107,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc107,000

 

 

 

          NEW SECTION.  Sec. 374.              FOR WASHINGTON STATE UNIVERSITY

 

          Todd Hall addition (88-1-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc3,898,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,434,000!tj1!tc5,332,000

 

 

 

          NEW SECTION.  Sec. 375.              FOR WASHINGTON STATE UNIVERSITY

 

          Fine arts mechanical renovation (88-1-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj1!tc450,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,669,000!tj1!tc3,119,000

 

 

 

          NEW SECTION.  Sec. 376.              FOR WASHINGTON STATE UNIVERSITY

 

          Carpenter Hall renewal (88-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixH Ed Construct Acct!tj1!tc2,615,000

WSU Bldg Acct!tj1!tc1,083,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,502,000!tj1!tc6,200,000

 

 

 

          NEW SECTION.  Sec. 377.              FOR WASHINGTON STATE UNIVERSITY

 

          Dairy forage facility (88-3-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj1!tc763,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc419,000!tj1!tc1,182,000

 

 

 

          NEW SECTION.  Sec. 378.              FOR WASHINGTON STATE UNIVERSITY

 

          Veterinary research diagnostic center (88-5-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc91,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc159,000!tc3,172,600!tc3,422,600

 

 

 

          NEW SECTION.  Sec. 379.              FOR WASHINGTON STATE UNIVERSITY

 

          Minor capital improvements (90-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj2!tc5,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc8,233,000

 

 

 

          NEW SECTION.  Sec. 380.              FOR WASHINGTON STATE UNIVERSITY

 

          Hazardous, pathological, radioactive waste handling facilities (90-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj2!tc152,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc11,000,000!tc11,152,000

 

 

 

          NEW SECTION.  Sec. 381.              FOR WASHINGTON STATE UNIVERSITY

 

          Nuclear radiation center study (90-1-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj2!tc53,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc4,000,000!tc4,053,000

 

 

 

          NEW SECTION.  Sec. 382.              FOR WASHINGTON STATE UNIVERSITY

 

          Expansion of east campus electrical substation (90-1-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj2!tc533,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc533,000

 

 

 

          NEW SECTION.  Sec. 383.              FOR WASHINGTON STATE UNIVERSITY

 

          Smith Gym electrical system renewal (90-1-018)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj2!tc648,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc648,000

 

 

 

          NEW SECTION.  Sec. 384.              FOR WASHINGTON STATE UNIVERSITY

 

          Holland Library addition (90-2-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc33,400,000

WSU Bldg Acct!tj1!tc184,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc87,000!tj1!tc33,671,000

 

 

 

          NEW SECTION.  Sec. 385.              FOR WASHINGTON STATE UNIVERSITY

 

          Veterinary Teaching Hospital (90-2-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,300,000

WSU Bldg Acct!tj2!tc200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc327,000!tc29,438,000!tc31,265,000

 

 

 

          NEW SECTION.  Sec. 386.              FOR WASHINGTON STATE UNIVERSITY

 

          Food‑-Human nutrition building, phase 2 (90-2-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral Fund‑-Federal!tj2!tc12,688,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc12,688,000

 

 

 

          NEW SECTION.  Sec. 387.              FOR WASHINGTON STATE UNIVERSITY

 

          Whets expansion, phase 1 (90-2-902)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc2,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc2,000,000

 

 

 

          NEW SECTION.  Sec. 388.              FOR WASHINGTON STATE UNIVERSITY

 

          Minor capital renewal (90-3-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc5,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc5,000,000

 

 

 

          NEW SECTION.  Sec. 389.              FOR WASHINGTON STATE UNIVERSITY

 

          Todd Hall renewal (90-3-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWSU Bldg Acct!tj2!tc182,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc182,000

 

 

 

          NEW SECTION.  Sec. 390.              FOR WASHINGTON STATE UNIVERSITY

 

          WSU Tri-Cities University Center (90-5-901)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc213,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc509,000!tj1!tc722,000

 

 

 

          NEW SECTION.  Sec. 391.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Mathematical science and technology remodel (81-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc82,900

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc5,789,700!tc6,219,600

 

 

 

          NEW SECTION.  Sec. 392.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Science building addition/remodel (83-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc3,000,000!tc6,784,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc6,028,000!tc2,952,600!tc18,765,100

 

 

 

          NEW SECTION.  Sec. 393.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Electrical system renewal (86-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,414,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,013,000!tj1!tc3,427,000

 

 

 

          NEW SECTION.  Sec. 394.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Roof replacement (86-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc915,000!tc1,500,000!tc2,915,000

 

 

 

          NEW SECTION.  Sec. 395.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Water storage and distribution (86-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct !tj1!tc300,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc870,000!tj1!tc1,170,000

 

 

 

          NEW SECTION.  Sec. 396.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Minor works projects (86-1-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixEWU Cap Proj Acct!tj1!tc100,000!tc2,100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,800,000!tc8,536,000!tc12,536,000

 

 

 

          NEW SECTION.  Sec. 397.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Small repairs projects (86-1-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixEWU Cap Proj Acct!tj2!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc693,000!tc3,200,000!tc4,893,000

 

 

 

          NEW SECTION.  Sec. 398.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Energy conservation (86-2-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc100,000

St Bldg Constr Acct!tj1!tc37,839

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc418,161!tj1!tc556,000

 

 

 

          NEW SECTION.  Sec. 399.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Life/safety and code compliance:  Asbestos (88-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc209,000!tc1,900,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc474,000!tc4,000,000!tc6,583,000

 

 

 

          NEW SECTION.  Sec. 400.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Fire suppression (88-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc126,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc450,000!tc2,158,000!tc2,734,000

 

 

 

          NEW SECTION.  Sec. 401.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Computer replacement (90-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixEWU Cap Proj Acct!tj2!tc1,611,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,611,000

 

 

 

          NEW SECTION.  Sec. 402.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Deferred maintenance (90-3-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixEWU Cap Proj Acct!tj2!tc516,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc516,000

 

 

 

          NEW SECTION.  Sec. 403.              FOR EASTERN WASHINGTON UNIVERSITY

 

          Kennedy Library addition/HVAC‑-Preplanning (90-5-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixEWU Cap Proj Acct!tj2!tc165,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc165,000

 

 

 

          NEW SECTION.  Sec. 404.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Energy savings projects (86-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCWU Cap Proj Acct!tj1!tc18,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc697,000!tj1!tc715,000

 

 

 

          NEW SECTION.  Sec. 405.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Small repairs and improvements (86-3-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCWU Cap Proj Acct!tj1!tc20,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc513,000!tj1!tc533,000

 

 

 

          NEW SECTION.  Sec. 406.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Handicap modifications (88-1-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCWU Cap Proj Acct!tj1!tc272,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc443,000!tj1!tc715,000

 

 

 

          NEW SECTION.  Sec. 407.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Nicholson Pavilion phase 2 (88-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,845,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,018,000!tj1!tc3,863,000

 

 

 

          NEW SECTION.  Sec. 408.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Life/safety  (90-1-030)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc831,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,000,000!tc1,831,000

 

 

 

          NEW SECTION.  Sec. 409.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Asbestos abatement (90-1-040)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc509,000!tc1,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,735,000!tc1,000,000!tc4,244,000

 

 

 

          NEW SECTION.  Sec. 410.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Psychology animal research facility (90-1-060)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,547,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,547,000

 

 

 

          NEW SECTION.  Sec. 411.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Barge Hall renovation (90-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc600,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc7,744,800!tc8,344,800

 

 

 

          NEW SECTION.  Sec. 412.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Telecommunications system‑-Phase 2 (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCWU Cap Proj Acct!tj1!tc875,000!tc1,443,600

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc925,000!tj1!tc3,243,600

 

 

 

          NEW SECTION.  Sec. 413.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Shaw/Smyser Hall remodel (90-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc2,405,900

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc2,405,900

 

 

 

          NEW SECTION.  Sec. 414.              FOR CENTRAL WASHINGTON UNIVERSITY

 

          Minor works projects group I (90-2-050)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixCWU Cap Proj Acct!tj1!tc809,000!tc5,156,600

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,203,958!tc10,450,000!tc18,619,558

 

 

 

          NEW SECTION.  Sec. 415.              FOR THE EVERGREEN STATE COLLEGE

 

          Life safety‑-Code compliance (88-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc819,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc2,003,000

 

 

 

          NEW SECTION.  Sec. 416.              FOR THE EVERGREEN STATE COLLEGE

 

          Asbestos removal (90-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc60,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc443,000!tc503,000

 

 

 

          NEW SECTION.  Sec. 417.              FOR THE EVERGREEN STATE COLLEGE

 

          Failed systems (90-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc544,070

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc544,070

 

 

 

          NEW SECTION.  Sec. 418.              FOR THE EVERGREEN STATE COLLEGE

 

          Minor works (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc178,720

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc178,720

 

 

 

          NEW SECTION.  Sec. 419.              FOR THE EVERGREEN STATE COLLEGE

 

          Emergency repairs (90-2-022)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixTESC Cap Proj Acct!tj2!tc81,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc81,000

 

 

 

          NEW SECTION.  Sec. 420.              FOR THE EVERGREEN STATE COLLEGE

 

          Small repairs and improvements (90-2-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixTESC Cap Proj Acct!tj2!tc162,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc162,000

 

 

 

          NEW SECTION.  Sec. 421.              FOR THE EVERGREEN STATE COLLEGE

 

          Deferred maintenance (90-3-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,641,870

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,641,870

 

 

 

          NEW SECTION.  Sec. 422.              FOR THE EVERGREEN STATE COLLEGE

 

          Public service building‑-Preplanning (90-5-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc210,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc210,000

@la

                                                                          (End of part)

 

!np

                                                                              PART 8

                                                                                  

EDUCATION - CONTINUED

 

!af98,800 @lb

 

          NEW SECTION.  Sec. 423.              FOR WESTERN WASHINGTON UNIVERSITY

 

          Const Tech Bldg/remodel Art Tech building phase 2 (84-3-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc100,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc9,809,055!tj1!tc9,909,055

 

 

 

          NEW SECTION.  Sec. 424.              FOR WESTERN WASHINGTON UNIVERSITY

 

          Construct/equip science facility phase 1 (90-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc20,730,700

WWU Cap Proj Acct!tj1!tc450,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc800,000!tj1!tc21,980,700

 

 

 

          NEW SECTION.  Sec. 425.              FOR WESTERN WASHINGTON UNIVERSITY

 

          Asbestos abatement‑-Multiple buildings (90-1-002)

 

 

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc3,000,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc3,000,000

 

 

 

          NEW SECTION.  Sec. 426.              FOR WESTERN WASHINGTON UNIVERSITY

 

          Minor works request/small repairs and improvements (90-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWWU Cap Proj Acct!tj1!tc2,503,000!tc3,900,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc8,948,481!tc12,000,000!tc27,351,481

 

 

 

          NEW SECTION.  Sec. 427.              FOR WESTERN WASHINGTON UNIVERSITY

 

          Science facility, phase 2 (design) (90-1-005)

 

 

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc887,300

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc19,332,800!tc20,220,100

 

 

 

          NEW SECTION.  Sec. 428.              FOR WESTERN WASHINGTON UNIVERSITY

 

          Institute of Wildlife Toxicology‑-Facility acquisition (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixWWU Cap Proj Acct!tj2!tc1,500,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,500,000

 

 

 

          NEW SECTION.  Sec. 429.              FOR THE WASHINGTON STATE HISTORICAL SOCIETY

 

          Addition to air conditioning (86-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc206,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc125,000!tj1!tc331,000

 

 

 

          NEW SECTION.  Sec. 430.              FOR THE WASHINGTON STATE HISTORICAL SOCIETY

 

          Museum interior remodeling (88-3-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,937,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc305,000!tj1!tc2,242,000

 

 

 

          NEW SECTION.  Sec. 431.              FOR THE WASHINGTON STATE HISTORICAL SOCIETY

 

          Small improvement project to extend building's useful life (90-3-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc151,500

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc151,500

 

 

 

          NEW SECTION.  Sec. 432.              FOR THE EASTERN WASHINGTON STATE HISTORICAL SOCIETY

 

          Campbell House‑-Restoration (86-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc750,700

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc343,000!tj1!tc1,093,700

 

 

 

          NEW SECTION.  Sec. 433.              FOR THE EASTERN WASHINGTON STATE HISTORICAL SOCIETY

 

          Cheney Cowles Museum‑-Repair roof and heating/cooling (89-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc80,100

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc80,100

 

 

 

          NEW SECTION.  Sec. 434.              FOR THE STATE CAPITOL HISTORICAL ASSOCIATION

 

          Minor works State Museum Olympia (90-1-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc9,000!tc27,100

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc91,000!tc48,000!tc175,100

 

 

 

          NEW SECTION.  Sec. 435.              FOR THE STATE CAPITOL HISTORICAL ASSOCIATION

 

          Design and construct agency headquarters, Capitol Campus, Olympia (90-5-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc7,890,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc10,000!tj1!tc7,900,000

 

 

 

          NEW SECTION.  Sec. 436.              FOR THE STATE CAPITOL HISTORICAL ASSOCIATION

 

          Energy efficiency agency headquarters‑-Olympia (91-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc15,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,000!tj1!tc16,000

 

 

 

          NEW SECTION.  Sec. 437.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          HVAC repairs (83-2-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc55,161

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc33,187!tj1!tc88,348

 

 

 

          NEW SECTION.  Sec. 438.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Minor works request (RMI) (86-1-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixH Ed Reimb S/T Bonds Acct!tj1!tc145,007

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc695,558!tj1!tc840,565

 

 

 

          NEW SECTION.  Sec. 439.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Critical repair projects (86-1-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixH Ed Reimb S/T Bonds Acct!tj1!tc578,666

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc508,335!tj1!tc1,087,001

 

 

 

          NEW SECTION.  Sec. 440.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          General repair projects (86-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Fac Renew‑-Acct!tj1!tc1,145,540

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,906,325!tj1!tc4,051,865

 

 

 

          NEW SECTION.  Sec. 441.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Energy conservation projects (86-1-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Fac Renew Acct!tj1!tc680,782

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc699,155!tj1!tc1,379,937

 

 

 

          NEW SECTION.  Sec. 442.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Food service building:  Olympic (86-1-019)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc166,665

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,154,206!tj1!tc2,320,871

 

 

 

          NEW SECTION.  Sec. 443.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Minor renovations (86-2-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Fac Renew Acct!tj1!tc1,149,227

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,519,681!tj1!tc3,668,908

 

 

 

          NEW SECTION.  Sec. 444.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Program/plan/construct:  Library/student Center, Everett (86-2-031)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral Fund!tj1!tc21,425

St Bldg Constr Acct!tj1!tc2,501,830

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc5,653,092!tj1!tc8,176,347

 

 

 

          NEW SECTION.  Sec. 445.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Construct main storage building‑-Clark (86-3-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc4,687

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc172,909!tj1!tc177,596

 

 

 

          NEW SECTION.  Sec. 446.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Minor improvements (86-3-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc30,886

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc872,234!tj1!tc903,120

 

 

 

          NEW SECTION.  Sec. 447.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Edison North renovation II:  Seattle central (86-3-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc592,093

St Bldg Constr Acct!tj1!tc4,211,350

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,112,869!tj1!tc7,916,312

 

 

 

          NEW SECTION.  Sec. 448.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Construct core facility and instructional space:  Whatcom (86-3-015)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc112,403

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,107,565!tj1!tc1,219,968

 

 

 

          NEW SECTION.  Sec. 449.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Replace relocatable buildings:  Pierce (86-3-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc78,117

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc849,284!tj1!tc927,401

 

 

 

          NEW SECTION.  Sec. 450.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Vocational science facility:  Wenatchee (86-3-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc341,554

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,901,445!tj1!tc2,242,999

 

 

 

          NEW SECTION.  Sec. 451.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Extension facility:  Puyallup (86-3-021)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc25,988

St Bldg Constr Acct!tj1!tc5,376,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc177,161!tj1!tc5,579,149

 

 

 

          NEW SECTION.  Sec. 452.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Tech building and related remodeling:  Skagit Valley (86-3-022)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc545,486

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc3,054,514!tj1!tc3,600,000

 

 

 

          NEW SECTION.  Sec. 453.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Heavy equipment building:  Grays Harbor (86-3-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc176,659

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc601,341!tj1!tc778,000

 

 

 

          NEW SECTION.  Sec. 454.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Learning Resource Center:  South Puget Sound CC (86-3-025)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc4,860,816

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,373,184!tj1!tc7,234,000

 

 

 

          NEW SECTION.  Sec. 455.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Heavy equipment building:  South Seattle (86-3-026)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc3,110,473

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,502,527!tj1!tc4,613,000

 

 

 

          NEW SECTION.  Sec. 456.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Energy grant:  Tacoma (86-3-030)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixGeneral Fund!tj1!tc97,857

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc87,143!tj1!tc185,000

 

 

 

          NEW SECTION.  Sec. 457.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Preplanning for 1987-89 major projects (86-4-999)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt H Ed Constr Acct!tj1!tc21,512

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc155,477!tj1!tc176,989

 

 

 

          NEW SECTION.  Sec. 458.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Minor works (RMI) (88-2-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,002,615

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,497,385!tj1!tc3,500,000

 

 

 

          NEW SECTION.  Sec. 459.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Repairs‑-Exterior walls (88-3-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,208,444

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,055,556!tj1!tc4,264,000

 

 

 

          NEW SECTION.  Sec. 460.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Repairs‑-Mechanical/HVAC (88-3-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,946,849

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,128,151!tj1!tc4,075,000

 

 

 

          NEW SECTION.  Sec. 461.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Minor improvements (88-3-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc6,824,863

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc6,939,137!tj1!tc13,764,000

 

 

 

          NEW SECTION.  Sec. 462.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Repairs‑-Electrical (88-3-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,044,047

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc347,953!tj1!tc1,392,000

 

 

 

          NEW SECTION.  Sec. 463.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Repairs‑-Sites and interiors (88-3-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc685,604

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc1,240,396!tj1!tc1,926,000

 

 

 

          NEW SECTION.  Sec. 464.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Agricultural technology building (Walla Walla) (88-3-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc166,325!tc2,946,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc50,478!tj1!tc3,162,803

 

 

 

          NEW SECTION.  Sec. 465.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Vocational shop (Wenatchee Valley) (88-3-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc64,747!tc880,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc17,253!tj1!tc962,000

 

 

 

          NEW SECTION.  Sec. 466.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Computer facility (Edmonds) (88-3-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc168,568!tc3,624,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc79,434!tj1!tc3,872,002

 

 

 

          NEW SECTION.  Sec. 467.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Learning Resource Center (Clark) (88-3-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc201,334!tc6,077,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc145,666!tj1!tc6,424,000

 

 

 

          NEW SECTION.  Sec. 468.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Extension center (Yakima Valley) (88-3-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc76,381!tc1,586,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc48,145!tj1!tc1,710,526

 

 

 

          NEW SECTION.  Sec. 469.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Math/science building (Spokane Falls) (88-3-015)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc144,486!tc5,510,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc172,152!tj1!tc5,826,638

 

 

 

          NEW SECTION.  Sec. 470.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          LRC (Spokane) (88-3-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc82,296!tc5,270,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc257,277!tj1!tc5,609,573

 

 

 

          NEW SECTION.  Sec. 471.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Construct Clarkston Extension Center:  (Walla Walla) (88-3-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc248,670

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc2,783,330!tj1!tc3,032,000

 

 

 

          NEW SECTION.  Sec. 472.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Tacoma Computer Center:  TCC (88-3-018)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc2,392,889

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc165,111!tj1!tc2,558,000

 

 

 

          NEW SECTION.  Sec. 473.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Preplanning for 1989-93 major projects (88-4-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc145,226

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc351,774!tj1!tc497,000

 

 

 

          NEW SECTION.  Sec. 474.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Whidbey LRC/instruc. (Skagit Valley) (88-5-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc108,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc37,000!tc1,927,000!tc2,072,000

 

 

 

          NEW SECTION.  Sec. 475.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Science/fine arts/PE (South Puget Sound) (88-5-021)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc256,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc72,000!tc5,494,000!tc5,822,000

 

 

 

          NEW SECTION.  Sec. 476.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Early childhood education (Shoreline) (88-5-022)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc78,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc41,000!tc1,258,000!tc1,377,000

 

 

 

          NEW SECTION.  Sec. 477.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Library remodel (Columbia Basin) (88-5-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc113,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc48,000!tc1,893,000!tc2,054,000

 

 

 

          NEW SECTION.  Sec. 478.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Vocational shops (Centralia) (88-5-024)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc95,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc43,000!tc2,089,000!tc2,227,000

 

 

 

          NEW SECTION.  Sec. 479.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          LRC addition/remodel (Tacoma) (88-5-025)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc90,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc34,000!tc1,720,000!tc1,844,000

 

 

 

          NEW SECTION.  Sec. 480.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Vocational food addition (Lower Columbia) (88-5-026)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc140,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc42,000!tc2,934,000!tc3,116,000

 

 

 

          NEW SECTION.  Sec. 481.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Business education building (Spokane) (88-5-027)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc245,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc76,000!tc6,398,000!tc6,719,000

 

 

 

          NEW SECTION.  Sec. 482.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Student activity/PE (Seattle Central) (88-5-028)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc400,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc107,000!tj1!tc507,000

 

 

 

          NEW SECTION.  Sec. 483.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          WSU Education Center:  Clark (89-5-019)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc1,800,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,800,000

 

 

 

          NEW SECTION.  Sec. 484.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Multipurpose Child Care Center:  Everett (89-5-020)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc600,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc600,000

 

 

 

          NEW SECTION.  Sec. 485.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Fire/security repairs (7) (90-1-004)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc947,610

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc947,610

 

 

 

          NEW SECTION.  Sec. 486.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Asbestos repairs (4) (90-1-008)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc1,217,200

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc1,217,200

 

 

 

          NEW SECTION.  Sec. 487.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Roof/structural repairs (20) (90-2-002)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc3,658,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc3,658,000

 

 

 

          NEW SECTION.  Sec. 488.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          HVAC/mechanical repairs (15) (90-2-003)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc2,972,830

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc2,972,830

 

 

 

          NEW SECTION.  Sec. 489.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Electrical repairs (4) (90-2-005)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc371,240

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc371,240

 

 

 

          NEW SECTION.  Sec. 490.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Small repairs and improvements (90-3-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc4,200,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc4,200,000

 

 

 

          NEW SECTION.  Sec. 491.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          LARC (Centralia) (90-3-006)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc133,680!tc4,012,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc118,800!tj1!tc4,263,970

 

 

 

          NEW SECTION.  Sec. 492.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Facility repairs (18) (90-3-007)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc3,848,180

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc3,848,180

 

 

 

          NEW SECTION.  Sec. 493.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Technology labs (Highline) (90-3-023)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj1!tc147,098!tc2,595,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tc56,040!tj1!tc2,798,138

 

 

 

          NEW SECTION.  Sec. 494.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Minor improvements (50) (90-5-009)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc13,292,940

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc13,292,940

 

 

 

          NEW SECTION.  Sec. 495.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Technology center (Whatcom) (90-5-010)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc63,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc185,000!tc248,000

 

 

 

          NEW SECTION.  Sec. 496.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          PE facility (North Seattle) (90-5-011)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc45,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc165,000!tc210,000

 

 

 

          NEW SECTION.  Sec. 497.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Applied arts building (Spokane Falls) (90-5-012)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc68,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc190,000!tc258,000

 

 

 

          NEW SECTION.  Sec. 498.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Industrial technology building (Spokane) (90-5-013)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc64,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc204,000!tc268,000

 

 

 

          NEW SECTION.  Sec. 499.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Vocational art facility (Shoreline) (90-5-014)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc51,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc125,000!tc176,000

 

 

 

          NEW SECTION.  Sec. 500.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Business education building (Clark) (90-5-015)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc73,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc231,000!tc304,000

 

 

 

          NEW SECTION.  Sec. 501.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Student center (South Seattle) (90-5-016)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc59,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc185,000!tc244,000

 

 

 

          NEW SECTION.  Sec. 502.              FOR THE COMMUNITY COLLEGE SYSTEM

 

          Library addition (Skagit Valley) (90-5-017)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc44,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj1!tc1,879,000!tc1,923,000

@la

                                                                          (End of part)

 

!np

                                                                              PART 9

                                                                                  

ALL OTHER EXPENDITURES

 

!af98,900 @lb

 

          NEW SECTION.  Sec. 503.              FOR SPECIAL APPROPRIATION TO THE GOVERNOR

 

          Puyallup tribal settlement (90-5-001)

 

!tm4,2,2!tj1!tcReappropriation!tcAppropriation

 

!ixSt Bldg Constr Acct!tj2!tc9,417,000

 

!tm1,1,1!tcProject!tcEstimated!tcEstimated

!tcCosts!tcCosts!tcTotal

!tcThrough!tc7/1/91!sc ,1and!tcCosts

!tc6/30/89!tcThereafter

 

!tj2!tc9,417,000

 

 

 

          NEW SECTION.  Sec. 504.              FOR THE ARTS COMMISSION‑-ART WORK ALLOWANCE

 

          Artwork allowance pooling:  Up to one-half of one percent of moneys appropriated in this act shall be spent as provided in RCW 28A.58.055, 28B.10.027, and 43.17.200.

@la

 

          NEW SECTION.  Sec. 505.              To carry out effectively the provisions of this act, the governor may assign responsibility for planning, engineering, construction, and other related activities to any appropriate agency.

 

 

          NEW SECTION.  Sec. 506.              Reappropriations shall be limited to the unexpended balances remaining June 30, 1989, in the current appropriation for each project.

 

 

          NEW SECTION.  Sec. 507.              In order to provide for consistent and comparable asbestos survey data, and to insure that the chain of evidence requirements for asbestos samples and survey data are met in regard to pending asbestos manufacturer litigation:

          (1) No state agency shall expend new funds appropriated in the 1989-91 biennium for asbestos surveys prior to approval by the department of general administration of the agency's asbestos survey policies and procedures.  At the completion of each survey, state agencies shall submit the findings to the department in a format to be determined by the department.

          (2) The department of general administration shall distribute to all state agencies chain of evidence requirements, as developed by the department and the office of the attorney general.  State agencies expending appropriated funds for asbestos survey and abatement projects shall make every effort to conform with chain of evidence requirements.

 

 

          NEW SECTION.  Sec. 508.              As part of the annual six year update to the State Facilities and Capital Plan, agencies shall provide lease development projects to the office of financial management.

 

 

          NEW SECTION.  Sec. 509.              If any federal moneys appropriated by this act for capital projects are not received by the state, the department or agency to which the moneys were appropriated may replace the federal moneys with any moneys available from private or local sources.  No replacement may occur under this section without the prior approval of the director of financial management in consultation with the committees on ways and means of the senate and house of representatives.

 

          NEW SECTION.  Sec. 510.              Notwithstanding any other provisions of law, for the 1989-91 biennium, state treasurer transfers of reimbursement to the general fund from the community college capital projects account for debt service payments made under the provisions of Title 28B RCW shall occur only after such debt service payment has been made and only to the extent that funds are actually available in the account.  Any unpaid reimbursements shall be a continuing obligation against the community college capital projects account until paid.  The state board for community college education need not accumulate any specific balance in the community college capital projects account in anticipation of transfers to reimburse the general fund.

 

 

          NEW SECTION.  Sec. 511.              Any capital improvements or capital project involving construction or major expansion of a state office facility, including district headquarters, detachment offices, and off-campus faculty offices, shall be reviewed by the department of general administration for possible consolidation and compliance with state office standards prior to allotment of funds.  The intent of the requirement imposed by this section is to eliminate duplication and reduce total office space requirements where feasible, while ensuring proper service to the public.

 

          NEW SECTION.  Sec. 512.              The governor, through the director of financial management, may authorize a transfer of appropriation authority provided for a capital project which is in excess of the amount required for the completion of such project to another capital project for which the appropriation is insufficient.  No such transfer shall be used to expand the capacity of any facility beyond that intended by the legislature in making the appropriation.  Such transfers may be effected only between capital appropriations to a specific department, commission, agency, or institution of higher education and only between capital projects which are funded from the same fund or account.

          For the purposes of this section, the governor may find that an amount is in excess of the amount required for the completion of a project only if (1) the project as defined in the notes to the budget document is substantially complete and there are funds remaining or (2) bids have been let on a project and it appears to a substantial certainty that the project as defined in the notes to the budget document can be completed within the biennium for less than the amount appropriated herein.

          For the purposes of this section, the legislature intends that each project be defined as proposed to the legislature in the governor's budget document, unless it clearly appears from the legislative history that the legislature intended to define the scope of a project in a different way.

          A report of any transfer effected under this section shall be filed with the legislative auditor by the director of financial management within thirty days of the date the transfer  is effected.  The legislative auditor shall review and compile these filings and periodically report thereon to the legislative budget committee and the appropriate standing committees of the senate and house of representatives.

 

 

          NEW SECTION.  Sec. 513.              (1) The legislature finds:

          (a) Estimates of capital project costs are prepared in a manner to ensure sufficient funds are available for the completion of projects.

          (b) Actual project costs are influenced by variations in cost factors, changing unit price levels, available inventories, inflation rates, gross construction volume at the time of project bid, and other factors that cannot be predicted at the time of estimating capital project costs.

          (c) Due to funding limitations, necessary capital projects are deferred to ensuing biennia.

          (d) The deferral of capital projects results in increased project costs due to the effects of inflation and increased deterioration of facilities.

          (e) No statutory authority currently exists to allow project cost savings to be used to implement necessary capital projects that were deferred to ensuing biennia due to lack of funds.

          (2) There is hereby authorized a capital projects cost control incentive program for the 1989-91 biennium.

          (3) Appropriations not required by an agency to complete capital projects authorized in this act, may be expended to implement, in priority sequence, those capital projects of the agency listed in the Governor's Six-Year Capital and Facility Plan for the 1991-93 Biennium, as that list exists in the Governor's final 1990 update of the six-year plan.  Expenditures under this section are subject to the following conditions:

          (a) No expenditure may be made without the prior allotment approval of the office of financial management.

          (b) The office of financial management shall notify the senate and house ways and means committees prior to authorizing any project for implementation under this section.

          (c) No project may be authorized under this section by the office of financial management unless sufficient funds are available to complete a project's design phase, construction phase, or both.

          (d) Appropriations in this act for a capital project shall not be expended under this section unless:

          (i) All contracts associated with the performance of the project have been completed and accepted by the state of Washington;

          (ii) The statutory thirty-day lien period for each project has expired;

          (iii) All claims of lien against project contracts have been satisfied;

          (iv) There are no outstanding claims against the state of Washington by any contracted party to the project construction contract; and

          (v) Any and all negotiated settlements or settlements arising from the findings of an arbitration board or court of jurisdiction have been satisfied.

 

          NEW SECTION.  Sec. 514.              To assure that major construction projects are carried out in accordance with legislative and executive intent, capital projects for renovation or additional space contained in this act that exceed two million five hundred thousand dollars and have not completed a program document prior to September 1, 1988, shall not expend funds for planning and construction until the office of financial management has reviewed the agency's programmatic document and approved the continuation of the project.  The program document shall include but not be limited to projected workload, site conditions, user requirements, current space available, and an overall budget and cost  estimate breakdown.

 

          NEW SECTION.  Sec. 515.              The appropriations contained in this act are maximum expenditure authorizations.  Pursuant to RCW 43.88.037, moneys disbursed from the treasury on the basis of a formalized loan agreement with another governmental entity shall be treated as a loan and are to be recorded as loans receivable and not as expenditures for accounting purposes.  To the extent that moneys are disbursed on a loan basis, the corresponding appropriation shall be reduced by the amount of loan moneys disbursed from the treasury during the 1989-91 biennium.

 

          NEW SECTION.  Sec. 516.              If any provision of this act or its application to any person or circumstance is held invalid, the remainder of the act or the application of the provision to other persons or circumstances is not affected.

 

          NEW SECTION.  Sec. 517.              This act is necessary for the immediate preservation of the public peace, health, and safety, the support of the state government and its existing public institutions, and shall take effect immediately.