PDFRCW 90.58.143

Time requirementsSubstantial development permits, variances, conditional use permits.

(1) The time requirements of this section shall apply to all substantial development permits and to any development authorized pursuant to a variance or conditional use permit authorized under this chapter. Upon a finding of good cause, based on the requirements and circumstances of the project proposed and consistent with the policy and provisions of the master program and this chapter, local government may adopt different time limits from those set forth in subsections (2) and (3) of this section as a part of action on a substantial development permit.
(2) Construction activities shall be commenced or, where no construction activities are involved, the use or activity shall be commenced within two years of the effective date of a substantial development permit. However, local government may authorize a single extension for a period not to exceed one year based on reasonable factors, if a request for extension has been filed before the expiration date and notice of the proposed extension is given to parties of record on the substantial development permit and to the department.
(3) Authorization to conduct construction activities shall terminate five years after the effective date of a substantial development permit. However, local government may authorize a single extension for a period not to exceed one year based on reasonable factors, if a request for extension has been filed before the expiration date and notice of the proposed extension is given to parties of record and to the department.
(4) The effective date of a substantial development permit shall be the date of filing as provided in RCW 90.58.140(6). The permit time periods in subsections (2) and (3) of this section do not include the time during which a use or activity was not actually pursued due to the pendency of administrative appeals or legal actions or due to the need to obtain any other government permits and approvals for the development that authorize the development to proceed, including all reasonably related administrative or legal actions on any such permits or approvals.
[ 1997 c 429 s 51; 1996 c 62 s 1.]