(1) The department may adopt rules that establish financial assurance requirements for recycling facilities that do not already have financial assurance requirements under this chapter, or are not already specifically exempted from financial assurance requirements under this chapter. The financial assurance requirements must take into consideration the amounts and types of recyclable materials recycled at the facility, and the potential closure and postclosure costs associated with the recycling facility; which assurance may consist of posting of a surety bond in an amount sufficient to meet these requirements or other financial instrument, but in no case less than ten thousand dollars.
(2) A recycling facility is required to meet financial assurance requirements adopted by the department by rule, unless the facility is already required to provide financial assurance under other provisions of this chapter.
(3) Facilities that collect, recover, process, or otherwise recycle scrap metal, processed scrap metal, unprocessed home scrap metal, and unprocessed prompt scrap metal are exempt from the requirements of this section.