EXCEPTIONS: | 1. Shafts and vertical exit enclosures shall not be considered part of the active mass timber construction. |
| 2. Noncombustible protection on the top surface of mass timber floor assemblies shall not be required before erecting additional floor levels. |
4. Where building construction exceeds six stories above grade plane, required exterior wall coverings shall be installed on floor levels, including mezzanines, more than four levels below active mass timber construction before additional floor levels can be erected.
EXCEPTION: | Shafts and vertical exit enclosures shall not be considered part of the active mass timber construction. |
[Statutory Authority: RCW
19.27.031 and
19.27.074. WSR 22-13-093, 23-12-107, and 23-20-027, § 51-54A-3312, filed 6/14/22, 6/7/23, and 9/25/23, effective 3/15/24.]