(1) Before construction or modification, a detailed plan that shows how adequate and competent construction inspection will be provided to insure compliance with the requirements of this chapter and the approved engineering documents must be submitted to and approved by the department. The plan must be submitted according to a schedule specified in the permit.
(2) The construction quality assurance plan shall include:
(a) A construction schedule summarizing planned construction activities, noting sequence interrelationships, durations, and terminations;
(b) A description of construction management, organization management procedures, lines of communication, and responsibility;
(c) A description of anticipated quality control testing, including type of test, frequency, and who will perform the tests;
(d) A description of the construction inspection program including inspection responsibilities, anticipated inspection frequency, deficiency resolution, and inspector qualifications; and
(e) For monofills, a description of how WAC
173-306-440 (4)(d) is to be met.
[Statutory Authority: Chapter
70.138 RCW. WSR 00-19-018 (Order 00-17), § 173-306-345, filed 9/8/00, effective 10/9/00; WSR 90-10-047, § 173-306-345, filed 4/30/90, effective 5/31/90.]