(1) Requirement for a permit. Except as provided in subsection (2) of this section, WAC
173-401-722 and
173-401-725, no chapter 401 source may operate after the time that it is required to submit a timely and complete application, except in compliance with a permit issued under this chapter.
(2) Application shield. If a chapter 401 source submits a complete application for permit issuance (including for renewal) within twelve months of the time the source becomes subject to the permit program, operation of the source without a chapter 401 permit is not a violation of this chapter until the permitting authority takes final action on the permit application, except as noted in this section. Chapter 401 sources in existence on the date of EPA approval of the state permit program shall become subject to the program on the effective date of EPA approval. This protection shall cease to apply if, subsequent to the completeness determination made pursuant to WAC
173-401-700(6), the applicant fails to submit by the deadline specified in writing by the permitting authority any additional information identified as being needed to process the application.