Complete permit application. A complete acid rain permit application shall be submitted on a form approved by the permitting authority, which includes the following elements:
(1) Identification of the affected source for which the permit application is submitted;
(2) Identification of each affected unit at the source for which the permit application is submitted;
(3) A complete compliance plan for each unit, in accordance with WAC
173-406-400;
(5) If the unit is a new unit, the date that the unit has commenced or will commence operation and the deadline for monitor certification; and
(6) The name of the designated representative, his or her signature, and the date of signature.
[Statutory Authority: Chapter
70.94 RCW. WSR 94-23-127 (Order 94-23), § 173-406-302, filed 11/23/94, effective 12/24/94.]