Plan Content | Nonsignificant Revisions | Significant Revisions |
| Submitted but no approval required to implement | Submitted and approval is required to implement |
Binding agreement | Changes to manufacturers participating in the plan or changes to contact information for manufacturers already included in the plan. | No revisions requiring approval. |
Standard plan participant assessment of charges or apportionment of costs | No nonsignificant revisions. | Any changes to the assessment of charges or apportionment of costs. |
Letter of certification | Changes to the contact information included for manufacturers already participating in the plan. | Addition or withdrawal of manufacturers participating in an independent plan. |
Use of Washington businesses | Any changes to the use of Washington state businesses. | No changes requiring approval. |
Collection services | Addition of collection site(s) or services without eliminating or changing existing services. | Changes to the level of services provided by the plan other than additional services. |
Collectors | Any addition or change to registered collectors used by the plan. | No changes requiring approval. |
Transporters | Adding, changing or removing registered transporters used by the plan. | No revisions requiring approval. |
Direct processors | Any additions or changes to direct processors already used by an approved plan. | Use of a direct processor not already registered under this chapter. |
Direct processor compliance audit report | Submission of copies of audit reports for any direct processor the plan uses after the plan was last approved or the plan's annual report was last submitted. | No revisions requiring approval. |
Design for recycling | Any changes to the description of design for recycling included in the plan. | No revisions requiring approval. |
Direct processor contract face sheet | Submission of copies of the contract face sheet as required in WAC 173-900-320(12) for any direct processor the plan uses after the plan was last approved or the plan's annual report was last submitted. | No revisions requiring approval. |
Recordkeeping | Any changes to recordkeeping. | No revisions requiring approval. |
Implementation timeline | No nonsignificant revisions. | Any changes to the implementation timeline. |
Public outreach and marketing requirements | Additional public outreach and marketing efforts. | Any changes to the public outreach plan, other than additional public outreach and marketing. |
Fair compensation | Any changes to fair compensation. | No changes requiring approval. |
(5) Approval process: Within sixty days after receipt of a plan revision or update requiring approval, ecology will determine whether the plan complies with this chapter. Ecology will determine if the revision or update is:
(a) Approved. If approved, ecology will send a letter of approval to the authority or authorized party via certified mail. The approval letter will include an expiration date for the plan.
(b) Disapproved. If disapproved, ecology will send a letter of disapproval to the authority or authorized party via certified mail. The disapproval letter will provide ecology's reasons for not approving the plan.
(i) The authority or authorized party must submit a plan revision or plan update within sixty days after receipt of the letter of disapproval.
(ii) Ecology then has an additional sixty days to review the revised revision or plan update.
(6) Approval criteria: Ecology will consider the following when reviewing a plan revision or update for approval:
(a) The updated plan submittal dates were met;
(b) The updated plan meets the requirements in this chapter;
(c) The updated plan contains all of the information required in WAC
173-900-320 and provides descriptive information sufficient to allow ecology to determine that the implementation of the plan will be in compliance with this chapter;
(d) The updated plan, when implemented, would meet or exceed required service levels; and
(e) Additional information or clarification needed by ecology during the review of a revised or updated plan to determine if the plan is compliant with these rules and chapter
70.95N RCW.
(7) Ecology will post all updated plans on the agency website.
(8) Proprietary information submitted to ecology under this chapter is exempt from public disclosure under RCW
42.56.270.
[Statutory Authority: Chapters
70.95N, 70.105, and
70.105D RCW. WSR 07-21-013 (Order 07-05), § 173-900-335, filed 10/5/07, effective 11/5/07.]