(1) If the remedial action will not have a probable significant adverse environmental impact, a DNS shall be issued no earlier than the RI/FS and no later than the draft cleanup action plan. If the lead agency made a preliminary decision under WAC
197-11-256 (1)(a) that a DS was unlikely, prior to issuing a DNS the responsible official shall consider any additional information about adverse environmental impacts generated during the RI/FS process.
(2) The public comment period on the DNS shall be the same as the comment period on the MTCA document, provided that for proposals listed in WAC
197-11-340 (2)(a) the comment period is no less than fourteen days prior to the effective date of the MTCA document. One public notice shall be used to announce the availability of both the DNS and MTCA document, consistent with the requirements of WAC
173-340-600 and
197-11-340.
[Statutory Authority: 1995 c 347 (ESHB 1724) and RCW
43.21C.110. WSR 97-21-030 (Order 95-16), § 197-11-259, filed 10/10/97, effective 11/10/97. Statutory Authority: RCW
43.21C.110. WSR 95-08-041 (Order 94-22), § 197-11-259, filed 3/31/95, effective 5/1/95.]