The supervisor will verify compliance of apprentice utilization requirements on public works projects as required by RCW
49.04.035.
(1) The apprentice utilization requirement on public works is established in accordance with RCW
39.04.320.
(2) The supervisor must verify compliance in the following manner:
(a) The prevailing wage intents and affidavits system will be the primary method used to verify compliance, however, the supervisor may use any appropriate reporting system or method.
(b) The supervisor may coordinate with any appropriate agency or organization to assist in verification of apprentice labor hours.
(c) The supervisor will compile a compliance report by awarding agencies, contractors, and subcontractors.
(3) Compliance reports on completed projects will be made available to the WSATC each quarter and must be used to determine compliance for the purposes of RCW
39.04.350 and
39.12.055.
(4) The WSATC shall accept or reject the report.
[Statutory Authority: Chapter
49.04 RCW. WSR 20-13-060, § 296-05-217, filed 6/15/20, effective 7/16/20.]