Before a certificate of inspection as defined in RCW
70.79.290 is issued, a boiler or unfired pressure vessel must be inspected by an inspector and have all necessary permits. In addition, the owner or user shall pay the fees scheduled in WAC
296-104-700 directly to the chief inspector. The inspection process is not complete until the certificate of inspection is posted.
If the owner or user of each boiler or unfired pressure vessel required to be inspected refuses to allow an inspection to be made, or refuses to pay the above fee, the certificate of inspection shall be suspended by the chief inspector until the owner or user complies with the requirements.
[Statutory Authority: RCW
70.79.030,
70.79.040,
70.79.150,
70.79.290,
70.79.330,
70.79.350, and chapter
70.79 RCW. WSR 02-23-036, § 296-104-125, filed 11/13/02, effective 12/14/02. Statutory Authority: RCW
70.79.030 and
70.79.040. WSR 99-22-026, § 296-104-125, filed 10/26/99, effective 11/26/99; Part III, § 6, filed 3/23/60.]