(Effective until January 1, 2025)

PDFWAC 296-150M-3000

Manufactured/mobile home fees.

DESIGN PLAN FEES:
 
 
STRUCTURAL ALTERATION
$216.00
 
RESUBMITTAL FEE
$95.30
 
ADDENDUM (Approval expires on the same date as original plan.)
$95.30
 
ELECTRONIC PLAN SUBMITTAL FEE $6.50 per page for the first set of plans and $1.00 per page for each additional set of plans. These fees are in addition to any applicable design plan fees required under this section.
 
DEPARTMENT INSPECTION FEES:
 
 
Combination permit - Mechanical and electrical inspections
$236.10
 
Heat pump
$236.10
 
Air conditioning
$236.10
 
Air conditioning with replacement furnace
$236.10
 
Gas furnace installation includes gas piping
$236.10
 
Fire safety inspection
$236.10
MECHANICAL
 
 
Gas*** piping
$104.80
 
Wood stove
$104.80
 
Pellet stove
$104.80
 
Gas*** Room heater
$104.80
 
Gas*** Decorative appliance
$104.80
 
Range: Changing from electric to gas***
$104.80
 
Gas*** Water heater replacement
$78.40
ELECTRICAL
 
 
Electric water heater replacement
$131.20
 
Electric water heater replacing gas*** water heater
$131.20
 
Each added or modified 120 volt circuit (maximum charge is two circuits)
$131.20
 
Each added 240 volt circuit (for other than heat pumps, air conditioners, furnaces, water heaters, ranges, hot tubs or spas)
$131.20
 
Hot tub or spa (power from home electrical panel)
$131.20
 
Replace main electrical panel/permanently installed transfer equipment
$131.20
 
Low voltage fire/intrusion alarm
$131.20
 
Any combination of furnace, range and water heater changing from electric to gas***
$131.20
PLUMBING
 
 
Fire sprinkler system
$294.90
 
Each added fixture
$78.40
 
Replacement of water piping system (this includes two inspections)
$263.30
STRUCTURAL
 
 
Inspection as part of a mechanical/fire safety installation (cut truss/floor joist, sheet rocking)
$117.60
 
Reroofs (may require a plan review)
$210.30
 
Changes to home when additions bear loads on home per the design of a professional (also requires a plan review)
$210.30
 
Other structural changes (may require a plan review)
$210.30
MISCELLANEOUS
 
 
OTHER REQUIRED INSPECTIONS (per hour*)
$86.00
 
ALL REINSPECTIONS (per hour*)
$86.00
 
Manufactured home installation inspection permit (only available in cities and counties with L&I inspection contract)
$602.90
 
Refund
$25.90
INSIGNIA FEES:
 
 
REISSUED - LOST/DAMAGED
$25.90
IPIA
 
DEPARTMENT AUDIT FEES
 
 
REGULARLY SCHEDULED IPIA AUDIT:
 
 
 
First inspection on each section (one time only)
$43.10
 
 
Second and succeeding inspections of unlabeled sections (per hour*)
$95.30
 
OTHER IPIA FEES:
 
 
 
Red tag removal during a regularly scheduled IPIA audit (per hour* separate from other fees)
$95.30
 
 
Red tag removal at a time other than a regularly scheduled IPIA audit (per hour* plus travel time* and mileage**)
$95.30
 
 
Increased frequency surveillance (per hour* plus travel time* and mileage**)
$95.30
 
 
Attendance at manufacturers training classes (per hour* only)
$95.30
 
 
Subpart "I" investigations (per hour* plus travel time* and mileage**)
$95.30
 
 
Alterations to a labeled unit (per hour* plus travel time* and mileage**)
$95.30
 
 
IPIA Issues/Responses (per hour* plus travel time* and mileage**)
$95.30
 
 
Monthly surveillance during a regularly scheduled IPIA audit (per hour* plus travel time* and mileage**)
$95.30
 
 
Monthly surveillance at a time other than a regularly scheduled IPIA audit (per hour* plus travel time* and mileage**)
$95.30
 
 
Plant certifications, recertifications and addenda updates (per hour* plus travel time* and mileage** per each inspector)
$95.30
 
 
Response to HBT audit during a regularly scheduled IPIA audit (per hour*)
$95.30
 
 
Response to HBT audit at a time other than a regularly scheduled IPIA audit (per hour* plus travel time* and mileage**)
$95.30
 
 
Alternative construction (AC) letter inspections at placement site (per hour* plus travel time* and mileage**)
$95.30
 
 
Replacement of HUD labels (per hour* plus travel time* and mileage**)
$95.30
 
 
State administrative agency (SAA) inspection fee (per hour* plus travel time* and mileage**)
$95.30
 
 
State administrative agency (SAA) dispute resolution filing fee
$95.30
 
 
State administrative agency (SAA) dispute resolution (per hour*)
$95.30
OTHER FEES:
 
 
FIELD TECHNICAL SERVICE (per hour plus travel time* and mileage**)
$88.60
 
PUBLICATION PRINTING AND DISTRIBUTION OF RCWs AND WACs (one free copy per year upon request)
$17.30
 
VARIANCE INSPECTION FEE
$210.30
 
HOMEOWNER REQUESTED INSPECTION
$210.30
 
DECERTIFICATION OF A MOBILE/MANUFACTURED HOME
$210.30
 
DEMOLITION OF A MOBILE/MANUFACTURED HOME
$210.30
 
ENERGY CONSERVATION PERMIT
$35.60
NOTE: 
Local jurisdictions may have other fees that apply.
*
Minimum charge of 1 hour; time spent greater than 1 hour is charged in 1/2 hour increments.
**
Per state guidelines.
***
Gas means all gases; natural, propane, etc.
[Statutory Authority: Chapters 43.22 and 43.22A RCW. WSR 23-21-084, § 296-150M-3000, filed 10/17/23, effective 12/1/23; WSR 22-19-074, § 296-150M-3000, filed 9/20/22, effective 11/1/22; WSR 22-01-193, § 296-150M-3000, filed 12/21/21, effective 1/31/22; WSR 21-07-126, § 296-150M-3000, filed 3/23/21, effective 4/23/21; WSR 20-04-081, § 296-150M-3000, filed 2/4/20, effective 3/6/20. Statutory Authority: Chapters 18.27, 70.87, 43.22, and 43.22A RCW. WSR 18-24-102, § 296-150M-3000, filed 12/4/18, effective 1/4/19. Statutory Authority: Chapter 43.22 RCW and 2011 1st sp.s. c 50. WSR 12-06-069, § 296-150M-3000, filed 3/6/12, effective 4/30/12. Statutory Authority: Chapters 18.106, 43.22 RCW, 2008 c 285 and c 329. WSR 08-12-042, § 296-150M-3000, filed 5/30/08, effective 6/30/08. Statutory Authority: Chapters 18.27, 18.106, 43.22, and 70.87 RCW. WSR 07-11-128, § 296-150M-3000, filed 5/22/07, effective 6/30/07. Statutory Authority: Chapter 43.22 RCW. WSR 07-05-063, § 296-150M-3000, filed 2/20/07, effective 4/1/07. Statutory Authority: Chapters 18.106, 43.22, and 70.87 RCW. WSR 06-10-066, § 296-150M-3000, filed 5/2/06, effective 6/30/06. Statutory Authority: Chapter 43.22 RCW and 2005 c 399. WSR 05-24-020, § 296-150M-3000, filed 11/29/05, effective 1/1/06. Statutory Authority: Chapters 18.27, 43.22, and 70.87 RCW. WSR 05-12-032, § 296-150M-3000, filed 5/24/05, effective 6/30/05. Statutory Authority: Chapters 18.27 and 43.22 RCW. WSR 04-12-048, § 296-150M-3000, filed 5/28/04, effective 6/30/04. Statutory Authority: RCW 43.22.340, 43.22.400, 43.22.432, 43.22.433, 43.22.434, 43.22.480, and 43.22.485, 2002 c 268, and chapter 43.22 RCW. WSR 03-12-044, § 296-150M-3000, filed 5/30/03, effective 5/30/03. Statutory Authority: RCW 43.22.350, 43.22.434, 43.22.480, 43.22.500, 18.27.070, 18.27.075, 70.87.030, 19.28.041, 19.28.051, 19.28.101, 19.28.121, 19.28.161, 19.28.201, 19.28.211, 19.28.341, 2001 c 159, and chapters 43.22, 19.28, 18.27, and 70.87 RCW. WSR 01-12-035, § 296-150M-3000, filed 5/29/01, effective 6/29/01. Statutory Authority: RCW 43.22.340, 43.22.350, 43.22.355, 43.22.360, 43.22.400, 43.22.432, 43.22.433, 43.22.434, 43.22.450, 43.22.480, and 43.22.485. WSR 00-17-148, § 296-150M-3000, filed 8/22/00, effective 9/30/00. Statutory Authority: Chapters 43.22, 18.27, 70.87 and 19.28 RCW. WSR 99-12-080, § 296-150M-3000, filed 5/28/99, effective 6/28/99. Statutory Authority: Chapters 18.106, 18.27 and 43.22 RCW. WSR 98-12-041, § 296-150M-3000, filed 5/29/98, effective 6/30/98. Statutory Authority: RCW 70.87.030, 18.27.070, [18.27.]075, 43.22.350, [43.22.]355, [43.22.]434 and [43.22.]480(2). WSR 97-11-053, § 296-150M-3000, filed 5/20/97, effective 6/30/97. Statutory Authority: RCW 43.22.340, [43.22.]355, [43.22.]360, [43.22.]432, [43.22.]440 and [43.22.]480. WSR 96-21-146, § 296-150M-3000, filed 10/23/96, effective 11/25/96.]
(Effective January 1, 2025)

PDFWAC 296-150M-3000

Manufactured/mobile home fees.

DESIGN PLAN FEES:
 
 
STRUCTURAL ALTERATION
$229.80
 
RESUBMITTAL FEE
$101.30
 
ADDENDUM (Approval expires on the same date as original plan.)
$101.30
 
ELECTRONIC PLAN SUBMITTAL FEE $6.90 per page for the first set of plans and $1.00 per page for each additional set of plans. These fees are in addition to any applicable design plan fees required under this section.
 
DEPARTMENT INSPECTION FEES:
 
 
Combination permit - Mechanical and electrical inspections
$251.20
 
Heat pump
$251.20
 
Air conditioning
$251.20
 
Air conditioning with replacement furnace
$251.20
 
Gas furnace installation includes gas piping
$251.20
 
Fire safety inspection
$251.20
MECHANICAL
 
 
Gas*** piping
$111.50
 
Wood stove
$111.50
 
Pellet stove
$111.50
 
Gas*** Room heater
$111.50
 
Gas*** Decorative appliance
$111.50
 
Range: Changing from electric to gas***
$111.50
 
Gas*** Water heater replacement
$83.40
ELECTRICAL
 
 
Electric water heater replacement
$139.50
 
Electric water heater replacing gas*** water heater
$139.50
 
Each added or modified 120 volt circuit (maximum charge is two circuits)
$139.50
 
Each added 240 volt circuit (for other than heat pumps, air conditioners, furnaces, water heaters, ranges, hot tubs or spas)
$139.50
 
Hot tub or spa (power from home electrical panel)
$139.50
 
Replace main electrical panel/permanently installed transfer equipment
$139.50
 
Low voltage fire/intrusion alarm
$139.50
 
Any combination of furnace, range and water heater changing from electric to gas***
$139.50
PLUMBING
 
 
Fire sprinkler system
$313.70
 
Each added fixture
$83.40
 
Replacement of water piping system (this includes two inspections)
$280.10
STRUCTURAL
 
 
Inspection as part of a mechanical/fire safety installation (cut truss/floor joist, sheet rocking)
$125.10
 
Reroofs (may require a plan review)
$223.70
 
Changes to home when additions bear loads on home per the design of a professional (also requires a plan review)
$223.70
 
Other structural changes (may require a plan review)
$223.70
MISCELLANEOUS
 
 
OTHER REQUIRED INSPECTIONS (per hour*)
$91.50
 
ALL REINSPECTIONS (per hour*)
$91.50
 
Manufactured home installation inspection permit (only available in cities and counties with L&I inspection contract)
$641.40
 
Refund
$27.50
INSIGNIA FEES:
 
 
REISSUED - LOST/DAMAGED
$27.50
IPIA
 
DEPARTMENT AUDIT FEES
 
 
REGULARLY SCHEDULED IPIA AUDIT:
 
 
 
First inspection on each section (one time only)
$45.80
 
 
Second and succeeding inspections of unlabeled sections (per hour*)
$101.30
 
OTHER IPIA FEES:
 
 
 
Red tag removal during a regularly scheduled IPIA audit (per hour* separate from other fees)
$101.30
 
 
Red tag removal at a time other than a regularly scheduled IPIA audit (per hour* plus travel time* and mileage**)
$101.30
 
 
Increased frequency surveillance (per hour* plus travel time* and mileage**)
$101.30
 
 
Attendance at manufacturers training classes (per hour* only)
$101.30
 
 
Subpart "I" investigations (per hour* plus travel time* and mileage**)
$101.30
 
 
Alterations to a labeled unit (per hour* plus travel time* and mileage**)
$101.30
 
 
IPIA Issues/Responses (per hour* plus travel time* and mileage**)
$101.30
 
 
Monthly surveillance during a regularly scheduled IPIA audit (per hour* plus travel time* and mileage**)
$101.30
 
 
Monthly surveillance at a time other than a regularly scheduled IPIA audit (per hour* plus travel time* and mileage**)
$101.30
 
 
Plant certifications, recertifications and addenda updates (per hour* plus travel time* and mileage** per each inspector)
$101.30
 
 
Response to HBT audit during a regularly scheduled IPIA audit (per hour*)
$101.30
 
 
Response to HBT audit at a time other than a regularly scheduled IPIA audit (per hour* plus travel time* and mileage**)
$101.30
 
 
Alternative construction (AC) letter inspections at placement site (per hour* plus travel time* and mileage**)
$101.30
 
 
Replacement of HUD labels (per hour* plus travel time* and mileage**)
$101.30
 
 
State administrative agency (SAA) inspection fee (per hour* plus travel time* and mileage**)
$101.30
 
 
State administrative agency (SAA) dispute resolution filing fee
$101.30
 
 
State administrative agency (SAA) dispute resolution (per hour*)
$101.30
OTHER FEES:
 
 
FIELD TECHNICAL SERVICE (per hour plus travel time* and mileage**)
$94.20
 
PUBLICATION PRINTING AND DISTRIBUTION OF RCWs AND WACs (one free copy per year upon request)
$18.40
 
VARIANCE INSPECTION FEE
$223.70
 
HOMEOWNER REQUESTED INSPECTION
$223.70
 
DECERTIFICATION OF A MOBILE/MANUFACTURED HOME
$223.70
 
DEMOLITION OF A MOBILE/MANUFACTURED HOME
$223.70
 
ENERGY CONSERVATION PERMIT
$37.80
NOTE: 
Local jurisdictions may have other fees that apply.
*
Minimum charge of 1 hour; time spent greater than 1 hour is charged in 1/2 hour increments.
**
Per state guidelines.
***
Gas means all gases; natural, propane, etc.
[Statutory Authority: Chapters 43.22 and 43.22A RCW. WSR 24-21-131, s 296-150M-3000, filed 10/22/24, effective 1/1/25; WSR 23-21-084, § 296-150M-3000, filed 10/17/23, effective 12/1/23; WSR 22-19-074, § 296-150M-3000, filed 9/20/22, effective 11/1/22; WSR 22-01-193, § 296-150M-3000, filed 12/21/21, effective 1/31/22; WSR 21-07-126, § 296-150M-3000, filed 3/23/21, effective 4/23/21; WSR 20-04-081, § 296-150M-3000, filed 2/4/20, effective 3/6/20. Statutory Authority: Chapters 18.27, 70.87, 43.22, and 43.22A RCW. WSR 18-24-102, § 296-150M-3000, filed 12/4/18, effective 1/4/19. Statutory Authority: Chapter 43.22 RCW and 2011 1st sp.s. c 50. WSR 12-06-069, § 296-150M-3000, filed 3/6/12, effective 4/30/12. Statutory Authority: Chapters 18.106, 43.22 RCW, 2008 c 285 and c 329. WSR 08-12-042, § 296-150M-3000, filed 5/30/08, effective 6/30/08. Statutory Authority: Chapters 18.27, 18.106, 43.22, and 70.87 RCW. WSR 07-11-128, § 296-150M-3000, filed 5/22/07, effective 6/30/07. Statutory Authority: Chapter 43.22 RCW. WSR 07-05-063, § 296-150M-3000, filed 2/20/07, effective 4/1/07. Statutory Authority: Chapters 18.106, 43.22, and 70.87 RCW. WSR 06-10-066, § 296-150M-3000, filed 5/2/06, effective 6/30/06. Statutory Authority: Chapter 43.22 RCW and 2005 c 399. WSR 05-24-020, § 296-150M-3000, filed 11/29/05, effective 1/1/06. Statutory Authority: Chapters 18.27, 43.22, and 70.87 RCW. WSR 05-12-032, § 296-150M-3000, filed 5/24/05, effective 6/30/05. Statutory Authority: Chapters 18.27 and 43.22 RCW. WSR 04-12-048, § 296-150M-3000, filed 5/28/04, effective 6/30/04. Statutory Authority: RCW 43.22.340, 43.22.400, 43.22.432, 43.22.433, 43.22.434, 43.22.480, and 43.22.485, 2002 c 268, and chapter 43.22 RCW. WSR 03-12-044, § 296-150M-3000, filed 5/30/03, effective 5/30/03. Statutory Authority: RCW 43.22.350, 43.22.434, 43.22.480, 43.22.500, 18.27.070, 18.27.075, 70.87.030, 19.28.041, 19.28.051, 19.28.101, 19.28.121, 19.28.161, 19.28.201, 19.28.211, 19.28.341, 2001 c 159, and chapters 43.22, 19.28, 18.27, and 70.87 RCW. WSR 01-12-035, § 296-150M-3000, filed 5/29/01, effective 6/29/01. Statutory Authority: RCW 43.22.340, 43.22.350, 43.22.355, 43.22.360, 43.22.400, 43.22.432, 43.22.433, 43.22.434, 43.22.450, 43.22.480, and 43.22.485. WSR 00-17-148, § 296-150M-3000, filed 8/22/00, effective 9/30/00. Statutory Authority: Chapters 43.22, 18.27, 70.87 and 19.28 RCW. WSR 99-12-080, § 296-150M-3000, filed 5/28/99, effective 6/28/99. Statutory Authority: Chapters 18.106, 18.27 and 43.22 RCW. WSR 98-12-041, § 296-150M-3000, filed 5/29/98, effective 6/30/98. Statutory Authority: RCW 70.87.030, 18.27.070, [18.27.]075, 43.22.350, [43.22.]355, [43.22.]434 and [43.22.]480(2). WSR 97-11-053, § 296-150M-3000, filed 5/20/97, effective 6/30/97. Statutory Authority: RCW 43.22.340, [43.22.]355, [43.22.]360, [43.22.]432, [43.22.]440 and [43.22.]480. WSR 96-21-146, § 296-150M-3000, filed 10/23/96, effective 11/25/96.]