Exemption: | You do not have to have written energy control procedures for a particular machine or equipment if all of the following apply: |
| 1. The machine or equipment has a single energy source that is easily identified and can be isolated. |
| 2. The machine or equipment is completely deenergized and deactivated by isolating and locking out the energy source. |
| 3. There is no stored or residual energy that could be a hazard to employees, and the machine or equipment cannot reaccumulate such energy after it has been shut down. |
| 4. The energy source can be locked out with a single lockout device. |
| 5. The machine or equipment is isolated from the energy source and locked out during service or maintenance. |
| 6. The authorized employee doing the service or maintenance has exclusive control of the lockout device. |
| 7. The service or maintenance does not create a hazard for other employees. |
| 8. The machine or equipment has never been unexpectedly energized or activated during service or maintenance. |
(4) You must make sure energy control procedures clearly and specifically outline:
(a) The scope, purpose, authorization, rules, and techniques to control hazardous energy; and
(b) How you will make sure employees follow the procedures.
(5) You must make sure energy control procedures specifically identify at least the following:
(a) When the procedure must be used.
(b) What the specific procedural steps are for:
(i) Shutting down, isolating, blocking, and securing the machine or equipment.
(ii) Placing, removing, and transferring lockout or tagout devices and who is responsible for them.
(c) How to test the machine or equipment to verify the effectiveness of lockout devices, tagout devices, and other energy control measures.
Note: | Similar machines and equipment may be covered by a single written procedure if all of the following apply: |
| 1. They use the same type and magnitude of energy. |
| 2. They have the same or similar types of controls. |
| 3. The specific machines and equipment covered by the procedure are identified by at least type and location. |
[Statutory Authority: RCW
49.17.010,
49.17.040,
49.17.050, and
49.17.060. WSR 17-18-075, § 296-803-20005, filed 9/5/17, effective 10/6/17; WSR 04-15-105, § 296-803-20005, filed 7/20/04, effective 11/1/04.]