PDFWAC 296-826-30060

Reinstallation.

You must make sure moved and reinstalled containers of a size to require field fabrication are reconstructed and reinspected to meet the original Unfired Pressure Vessel Code under which the tank was manufactured and do the following according to the same code:
(1) A pressure retest;
(2) Any necessary rerating.
[Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050. WSR 15-23-086, § 296-826-30060, filed 11/17/15, effective 12/18/15. Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050, 49.17.060. WSR 06-10-067, § 296-826-30060, filed 5/2/06, effective 9/1/06.]