(1) The agency may require an owner or operator to return any cost overpayment made by the program. Overpayments may occur if:
(a) Another party, such as an insurer, has paid costs prior to payments from the program; or
(b) The agency discovers an accidental overpayment has been made to an owner or operator for any reason.
(2) If a cost overpayment is not paid upon demand, the agency may pursue the following actions:
(a) Collections. The agency may request cost recovery with a debt collection agency.
(b) Lien filing. The agency may seek cost recovery of remedial action costs by filing a lien on the petroleum underground storage tank facility as authorized under RCW
70A.545.070.
(c) Civil action. The agency may request the attorney general office to commence a civil action against the owner or operator in superior court to recover costs and the agency's administrative and legal expenses to pursue recovery.
[Statutory Authority: RCW
70A.545.100(1). WSR 24-18-050, § 374-10-120, filed 8/27/24, effective 9/27/24.]