(1) Construction documents must be resubmitted for review as a new project according to current requirements if construction:
(a) Has not started within one year from the date of approval; or
(b) Is not completed within two years from the date of approval.
(2) To obtain an extension beyond two years, a written request must be submitted and approved thirty days prior to the end of the two-year period.
[Statutory Authority: Chapters
18.51 and
74.42 RCW and 42 C.F.R. 489.52. WSR 08-20-062, § 388-97-3480, filed 9/24/08, effective 11/1/08.]