(1) Amount required/rate of use/efficiency. The application shall describe the rate of use and efficiency of consumption of energy and natural resources during both construction and operation of the proposed facility.
(2) Source/availability. The application shall describe the sources of supply, locations of use, types, amounts, and availability of energy or resources to be used or consumed during construction and operation of the facility.
(3) Nonrenewable resources. The application shall describe all nonrenewable resources that will be used, made inaccessible or unusable by construction and operation of the facility.
(4) Conservation and renewable resources. The application shall describe conservation measures and/or renewable resources which will or could be used during construction and operation of the facility.
(5) Scenic resources. The application shall describe any scenic resources which may be affected by the facility or discharges from the facility.
[Statutory Authority: RCW
80.50.040 (1) and (12). WSR 04-21-013, amended and recodified as § 463-60-342, filed 10/11/04, effective 11/11/04. Statutory Authority: RCW
80.50.040. WSR 92-23-012, § 463-42-342, filed 11/6/92, effective 12/7/92.]