(1) EFSEC shall consider and may recommend certification of electrical transmission facilities in corridors designated for this purpose by affected cities, towns, or counties where:
(a) Jurisdictions have identified electrical transmission facility corridors as part of their land use plans and zoning maps based on policies adopted in their plans.
(b) The proposed electrical transmission facility is consistent with any adopted development regulations that govern the siting of electrical transmission facilities in such corridors.
(c) Contiguous jurisdictions and jurisdictions in which related regional electrical transmission facilities are located have either prior to or during the preapplication process undertaken good faith efforts to coordinate the locations of their corridors consistent with RCW
36.70A.100.
(2) If EFSEC determines that negotiations as required in WAC
463-61-080 have failed, EFSEC shall consider the applicant's proposed corridor and transmission facilities consistent with RCW
80.50.090 and
80.50.100 taking into consideration the positions of the preapplicant and the affected cities, towns or counties.
[Statutory Authority: Chapter
80.50 RCW and RCW
80.50.040. WSR 08-21-092, § 463-61-070, filed 10/15/08, effective 11/15/08.]